Council Minutes - Section B: Reports - 12 May 2015

Contents | Previous Page: Section A - Procedural Matters | Next Page: Section C - Assembly of Councillors

Reports tabled at the Ordinary Meeting of Council on Tuesday date held at City Hall, Little Malop Street in Geelong.


  1. Budget Referrals 2015-2016

  2. 2015-2016 Proposed Budget

  3. Proposed City Plan 2013-2017 (2015-2016 Update)

  4. City Plan 2013-2017 Progress Report to March 2015

  5. Combined Amendment C261 and Planning Permit 1163/2013 130-150 Forest Road South, Lara - Adoption

  6. C274 HO1600 Heritage Review, Batman Park Indented Head

  7. Private Sporting Infrastructure Capital Co-Contribution Policy

  8. Revised Terms of Reference for Special Committees

  9. Highton Drainage/Flood Study


1. Budget Referrals 2015-2016

Portfolio:

Finance – Cr Lyons (Mayor), Cr Farrell, Cr E Kontelj

Source:

Strategy and Performance - Administration and Governance

General Manager:

Dean Frost

Index Reference:

Subject: Budget Financial Year 2015-2016


Purpose

To declare any conflicts of interest that Councillors may have with the 2015-2016 Budget.


Summary

Cr Farrell moved, Cr E Kontelj seconded -

That Councillors who have a Conflict of Interest in items proposed for the inclusion in the 2015-2016 Budget declare the nature of that interest:

Victorian Local Governance Association (VLGA) membership

Cr Farrell declared an indirect interest in that she works as a contractor for the Victorian Local Governance Association (VLGA) Membership.

Cr Farrell left the meeting room at 7:23pm

Cr Heagney moved, Cr Macdonald seconded -

That funding of VLGA Annual Membership be approved for inclusion in the 2015-2016 Council Budget.

Carried.


Cr Farrell returned to the meeting room at 7:23pm

Managing Future Growth Batesford South Study

Cr Heagney declared an indirect interest due to her close association with a ratepayer who has significant property interests in the area.

Cr Heagney left the meeting room at 7.24pm

Cr Ansett moved, Cr Farrell seconded -

That funding of D65A12 Managing Future Growth Batesford South Study for $100,000 be approved for inclusion in the 2015-2016 Council Budget.

Cr Heagney returned to the meeting room at 7:24pm

St Albans Breakwater Cricket Club

Cr Irvine declared an indirect interest in that he is the president of the St Albans Breakwater Cricket Club.

Cr Irvine left the meeting room at 7:25pm

Cr Fisher moved, Cr Ellis seconded -

That funding of D66A31 St Albans Breakwater Cricket Club for $35,000 be approved for inclusion in the 2015-2016 Council Budget

Cr Irvine returned to the meeting at 7:25pm

Composting Site Setup Works

Cr Harwood declared an indirect interest in that he undertakes consultancy work for a company that is assisting Council in establishing a green organics site.

Cr Harwood left the meeting room at 7:25pm

Cr Nelson moved, Cr Richards seconded -

That funding of C16303 Composting Site Setup Works for $250,000 be approved for inclusion in the 2015-2016 Council Budget.
Cr Harwood returned to the meeting at 7.26pm

Geelong Soccer Club Facilities Upgrade

Cr E Kontelj declared an indirect interest due to his close association with a committee member.

Cr E Kontelj left the meeting room at 7:26pm

Cr Irvine moved, Cr Fisher seconded -

That funding of C16840 Geelong Soccer Club Facilities Upgrade for $250,000 be approved for inclusion in the 2015-2016 Council Budget.

Cr E Kontelj returned to the meeting at 7:27pm

Town Centre Tree Lighting

Cr Lyons declared a direct interest in that he owns property in the CBD that may be impacted by the continuation of the lighting and decoration program.

Cr Heagney declared a direct interest in that she owns property in the CBD that may be impacted by the continuation of the lighting and decoration program.

Cr Macdonald moved, Cr Richards seconded –

That Cr Harwood be nominated to Chair the Meeting in the absence of the Mayor and Cr Heagney.

Carried.

Cr Lyons vacated the Chair and left the meeting room at 7:29pm

Cr Heagney left the meeting room at 7:29pm

Cr Harwood assumed the Chair at 7:29pm.

Cr Farrell moved, Cr Irvine seconded - That funding of C16849 Town Centre Tree Lighting for $300,000 be approved for inclusion in the 2015-2016 Council Budget.

Cr Lyons returned to the meeting and assumed the Chair at 7:29pm.

Cr Heagney returned to the meeting at 7:29pm.

Carried.


Background

In developing the 2015-2016 Budget an extensive range of activities and initiatives have been considered for funding. Councillors who may have a conflict of interest in any items to be considered are required to disclose the nature of any conflict of interest.

The Local Government Act 1989 requires a Councillor to declare any conflict of interest in relation to matters to be considered by Council and to leave the meeting for the duration of discussion and vote on that matter.


Discussion

A number of Councillors have indicated conflicts of interest in items contained within the proposed budget and to facilitate disclosure the following are suggested as categories for disclosure:


Environmental Implications

There are no environmental implications relative to this report.


Financial Implications

Financial implications are addressed in the 2015-2016 Proposed Budget.


Policy/Legal/Statutory Implications

This report has been prepared to address requirements of the Local Government Act 1989, specifically section 79C (2) which deal with conflicts of interests in the Budget adoption process.


Alignment to City Plan

Aligns to How We do Business in City Plan.


Officer Direct or Indirect Interest

No officer involved in the preparation of this report has an interest relative to the advice provided.


Risk Assessment

The declaration of any interests ensures transparency.


Social Considerations

There are no social considerations relative to this report.


Human Rights Charter

This report has no impact on Human Rights.


Consultation and Communication

Councillors have been consulted in the preparation of this report and the report is available as a public document.


[Back to Top]

2. 2015-2016 Proposed Budget

Portfolio:

Finance – Cr Lyons (Mayor), Cr E Kontelj and Cr Farrell

Source:

Strategy and Performance – Financial Services

General Manager:

Dean Frost

Index Reference:

Financial Management / Budget – Financial Year 2015/2016


Purpose

Adopt the Proposed 2015-2016 Budget to allow for a 28 day public submission period prior to adoption of the final budget by 30 June 2015.


Summary

Cr Farrell moved, Cr E Kontelj seconded -

That Council:

  1. Pursuant to Section 127 of the LGA, the Council:

    1. Receive and consider the Proposed 2015-2016 Budget document, (Appendix 1), which includes the Budgeted Statements of Comprehensive Income, Cash Flows, Balance Sheet, Capital Works, Changes in Equity and Human Resources.

    2. Receive and consider the Four Year Strategic Resource Plan (Appendix 1, Section 3) including Budgeted Statements of Comprehensive Income, Cash Flows, Balance Sheet, Capital Works, Changes in Equity and Human Resources (under Section 126 of the LGA).

    3. Receive and consider the Rates, Municipal Charge, Waste Collection and Recycling charge and other income (required to meet the appropriate financial requirements as proposed in the 2015-2016 Budget package).

    4. Receive and consider the proposed declaration of Rates and Charges (Appendix 2), for the purpose of:

      1. public scrutiny and comment, and

      2. inclusion within the Rating Strategy 2015-2016 of Rate waivers under section 171of the LGA as detailed therein.

      3. inclusion within the Rating Strategy 2015-2016 of Rate rebates, under section 169 of the LGA as detailed therein.

    5. Receive and consider Councillor allowances in accordance with the notification published under section 73B of the LGA in the Victorian Government Gazette on 6 November 2014.

  2. Advertise the Proposed Budget and make it available for inspection at Customer Service Centres and the Council website. The advertisement be placed in the Geelong Advertiser on Wednesday, 13 May 2015 inviting written submissions from the public by 5pm on Tuesday, 9 June 2015.

  3. Appoint a Budget Submissions Panel to hear submissions made in relation to the Budget, Differential Rating, and Councillor allowances, such Panel to:

    1. consist of councillors each of whom shall have voting rights, with the quorum being three members;

    2. meet on Friday, 12 June 2015 to consider any written submissions and to hear any person who wishes to address the Panel in support of a submission; and

    3. report to Council in relation to the submissions that have been received and any recommended amendments to the Proposed Budget.

  4. After considering the report of the Budget Submissions Panel, adopt the budget, declare the rates, and also adopt the Councillor allowance, the Deputy Mayor allowance and also the Mayoral allowance, at a Council Meeting to be held on Tuesday, 23 June 2015.

  5. Advertise the adoption of the budget, declaration of the rates, and Councillor allowances, following the Council meeting on 23 June 2015.

Cr Ansett left the meeting room at 7:38pm for the evening.

Cr Fisher left the meeting room at 7:39pm.

Cr Fisher re-entered the meeting room at :.41pm.

Carried.


Background

In accordance with Section 127 of the LGA, Council is required to prepare a budget for each financial year and must ensure that it contains:

  1. The budgeted statements in the form and containing the matters required by the regulations;

  2. A description of the activities and initiatives to be funded in the budget.

  3. A statement as to how the activities and initiatives described under paragraph (b) will contribute to achieving the strategic objectives specified in the Council Plan;

  4. Separately identified Strategic Objectives to be undertaken during the financial year and service performance outcome indicators in relation to each Strategic Objective;

  5. Any other details required by the regulations.

In addition, Council must ensure the budget considers the following:

  1. The information the Council is required to declare under section 158(1);

  2. If the Council intends to declare a differential rate under section 161, the details listed in section161(2), and

If the Council intends to declare a differential rate under section 161A, the details listed in section 161(2).


Discussion

The Proposed 2015-2016 Budget for the financial year commencing 1 July 2015, as reviewed during recent Councillor Budget sessions, has been completed.

The Proposed 2015-2016 Budget document (Appendix 1) has been prepared on the basis of the Best Practice Guidelines as developed by a Local Government industry taskforce and issued to all municipalities across Victoria. The Proposed Budget document has been developed under the following sections:

In accordance with the LGA, the Proposed 2015-2016 Budget also includes clear linkages to Council’s Proposed “City Plan 2013-2017, (2015-2016 Update)”, and its supporting Key Strategies and Actions.
Specific inclusions in the Proposed Budget are a summary by Strategic Directions:

In addition, a component of the Proposed Budget is the setting of Rates and Charges. The Declaration of Rates and Charges for 2015-2016 is attached (Appendix 2). The formal Rating Strategy document will be updated that reflects Council’s statements of policy, procedure, general information and historical trends.

Council has declared a special rate in respect of the central business district of Geelong applicable to non-residential, non-exempt properties. The special rate is the Central Activities Area (CAA) Rate and is in addition to other rates and charges. The purpose of the special rate is to promote the CAA as a commercial shopping precinct using events, marketing and media.

Mayor and Councillor Allowances

The LGA regulates the allowance payable to the Mayor and Councillors of Local Governments in Victoria.

By notice in the Government Gazette published on 6 November 2014 the Minister for Local Government implemented an annual adjustment of allowances payable to Mayor, Deputy Mayor and Councillors effective from 1 December 2014. For the City of Greater Geelong the Mayoral Allowance is $187,414.73, the Deputy Mayoral Allowance is $58,673.39 and for Councillors $30,881. These allowances have been provided for in the 2015 2016 Budget.

Rating Strategy 2015-2016

The Rating Strategy document will be updated to reflect the outcome of Council’s Budget deliberations.

Rates and Charges are the major source of Council revenue accounting for 62% of the total Council revenue annually. An increase in rate income is required to meet the objectives of Council aspirations and community expectations for new infrastructure.

The proposed rate increase for 2015-2016 at 4.5% is consistent with the previous years Strategic Resource Plan which advocated sustainable rate increases over the next four years, required to fund new initiatives and maintain existing service levels.

The State Government has announced that Local Government rates will be capped to CPI from the 2016-2017 financial year.

Current Year Rate Increases

Changes proposed for 2015-2016 are:

  1. Rates and Charges on a residential property will increase overall by 4.45%, including rate in $ movement 4.5%, Municipal Charge movement 3%, and Waste Collection Service Charge 4.77%. The residential rate has been set at $0.002832 per $ of CIV valuation.

  2. Vacant Land rate in the dollar will remain at 145% of residential in order to encourage building activity and development.

  3. The Waste Collection Service charge is calculated based on a fee for service, including direct, indirect and overhead costs. The charge is impacted by cost estimates of EPA levy $28.75 per tenement. The charge for 2015 2016 will increase from $246.50 to $258.25 or 4.77%.

  4. The Municipal Charge represents a fee on all rateable assessments as a contribution to the fixed and unavoidable costs of governance. The Municipal Charge is to increase from $91.55 to $94.30 or 3%.

  5. The Farm rebate will remain at 34% and represents a cost to Council of $1.289M.

  6. The Housing Support Waiver for eligible Charitable Housing will be maintained for 2015 2016 and is available upon application.

  7. A rates waiver introduced for the New Corio Estate from 2013-2014 recognising this inappropriate subdivision and Planning Scheme Amendment C243 will be maintained.

  8. The pensioner concession will increase from $208.00 in accordance with movement in CPI for Melbourne as advised by the Australian Bureau of Statistics to an estimated $212.70 (to be confirmed in May 2015).

  9. The transitional rebate introduced in 2010-2011 for nominated charitable housing properties was reduced to 25% in 2014-2015 and has been withdrawn from 2015-2016.

  10. Petroleum and Automobile differentials have been aligned to the same rate in the dollar. Council’s adopted Statement of Principle is to reduce the gap between the rate in the dollar for these differentials and the industrial differential. For 2015-2016 Petroleum and Automobile differential have moved from 367% to 322% relative to residential.

These increases are required in order to fund increases to recurrent expenditure, and the continuing capital works program.

Residential Rates and Charges

The average Capital Improved Value of residential properties within the municipality has increased from $375,674 to $377,721.

The total increase in rates and charges for the average property with a capital improved value of $377,721 is $60.55 or 4.45%.

This increase is made up of $46.05 for General Rates, $2.75 for Municipal Charge and $11.75 for the Waste Collection Service.

Residential Properties

2014-2015 Rates on Average CIV $

2015-2016 Budget Rates on Average CIV $

Increase %

General Rates CIV x Rate in $

1023.60

1069.65

4.50%

Municipal Charge

91.55

94.30

3.00%

Waste Collection Service

246.50

258.25

4.77%

Total Rates and Charges

1,361.65

1,422.20

4.45%



Rate Waiver

Council declares a waiver under Section 171 of the LGA for residential land and farm land properties where the valuation of the assessment has increased between the 2012 valuation and the 2014 valuation by 50% or more and that increase is purely attributable to market factors, not attributable, in whole or in part, to improvements made to the assessment by the owner (or occupier). The amount of the waiver be set at:

The waiver is designed to mitigate the rates shock of a valuation increase and is only claimable once in a two year valuation cycle.

Council declare a Housing Support waiver under section 171 of the LGA of 100% of general rates and municipal charge for the following types of housing. Transitional, Emergency, Crisis Housing, Housing for Legatees or War Widows provided by the Geelong Legacy Club or provided by RSL, and supported Housing for disabled people. This waiver recognises that these properties provide specific needs within the community. Application can be made to Council to have land classified as being eligible for the waiver.

The New Corio Estate is an old and inappropriate subdivision within an established farming zone in Corio. Since the land is zoned as farming land it cannot be developed for residential use with no services available for the area. There is no prospect of these services becoming available in the future. In addition, environment reports in recent years have shown that the land contains significant native vegetation which Council is obligated to protect for future generations. Council adopted Planning Scheme amendment C243 which formally protects the native vegetation and provides some certainty over the future of the land. This amendment was approved by the Minister of Environment and Climate Control on 30 April 2013.

From 2013-2014 Council declared a waiver under section 171 of the LGA of 100% of general rates and municipal charge for privately owned properties in the New Corio Estate. This rates assistance waiver recognises the financial burden associated with ownership of the land and the encumbrances that prevents property owners from making any demands on Council services now and into the future.

Rate Rebates

Council has declared a Farm rebate to support the continuation of broad acre farming at 34% of general rates.

Rate Structure

Council has 12 rating or tariff groups with the application of differential rates to each of these groups in accordance with Section 161 of the LGA. The finalised Ministerial Guidelines for Differential Rating were gazetted on 26 April 2013 and came into effect from 1 July 2013. The intention of the Guidelines is to provide clarity, consistency and transparency.

Council needs to consider the objectives, the suitable uses and the types of classes of land when introducing a differential rate. The Guidelines establish three groups of types and classes of land categories for differential rates – those which are considered ‘appropriate’, those which must be ‘carefully considered’ by a council and those which would ‘not be appropriate’.

Fire Services Property Levy

The Fire Services Property Levy Act 2012 (FSPL) came into effect from 1 July 2013 and requires Local Government to bill, receipt and collect FSPL on rateable and non-rateable properties. The FSPL is billed on the annual rate notice in accordance with legislative requirements.
The FSPL rates applicable for 2015-2016 will be released in May 2015. The levy amount to be remitted to the State Revenue Office in 2015-2016 will be approximately $23.4M.


Environmental Implications

The Proposed Budget identifies the sources and allocation of the resources to implement the many environmental initiatives that impact on the community as outlined with Council’s 2013 2017 City Plan, (2015-2016 Update).


Financial Implications

The budget has been prepared in accordance with the direction provided by Council. Changes in rates, fees and charges have been structured to meet the financial requirements as proposed for the 2015-2016 financial year.

Expenditure includes the continuation of Council services to the community.

The Budget includes a recurrent operating surplus of $0.7M.

The gross capital expenditure of $94.9M includes new funding of $13.7M on Infrastructure Leisure, $24.8M on roads, footpaths, kerb and channel and drains and $21.9M on buildings.

New loans of $27.9M are proposed for 2015-2016 including $14.9M deferred loans from 2014 2015. The projected total amount of borrowings as at 30 June 2016 is $81.7M.


Policy/Legal/Statutory Implications

The Annual budget is prepared to comply with the requirements of the Local Government Act 1989 and the Local Government (Planning and Reporting) Regulations 2014.

The annual budget process also recognises the need to align the Annual Budget to the direction and allocation of resources identified within the proposed City Plan update.


Alignment to City Plan

This report contributes to responsible and sustainable financial management as aligned in Council’s City Plan objective on How We Do Business.


Officer Direct or Indirect Interest

No Council officers involved in the preparation of this report have a direct or indirect interest in any matter to which this report relates.


Risk Assessment

Under Section 130 of the Local Government Act Council must adopt the Annual Budget by 30 June each year commencing 2015-2016 Budget.
On 28 October 2014 Council adopted a budget timetable to include community consultation, meetings of the executive and Council to prepare the 2015-2016 Budget/City Plan update. The timetable provides a framework to manage risk in order for Council to meet its statutory obligations and avoid adverse implications if the process is delayed. These include:


Social Considerations

The Proposed Budget identifies the sources and allocation of resources to implement the many social initiatives that impact on the community as outlined with Council’s 2013–2017 (2015-2016 Update) City Plan.


Human Rights Charter

There are no known positive or negative effects.


Consultation and Communication

A Public Notice is scheduled to be published in the Geelong Advertiser on Wednesday, 13 May 2015 advising that the Proposed 2015-2016 Budget will be available for public scrutiny and inviting written submissions to be made.

Following the closing date for the written submissions, it is proposed to convene a Budget Submissions Panel on Friday, 12 June 2015 to review any submissions that have been received and put forward to Council a report on any recommended amendments to the Proposed Budget.

Council is scheduled to meet on Tuesday, 23 June 2015 at which time the report from the Budget Submissions Panel will be considered.

Public Notice of the adopted budget and declaration of rates and charges will be advertised following the Council Meeting.


APPENDIX 1

2015-2016 Proposed Budget


APPENDIX 2

DECLARATION OF RATES and CHARGES

  1. Amount Intended to be raised by General Rates, Municipal Charge, and Annual Service Charge for the period 1 July 2015 - 30 June 2016.

    An amount of $190,839,558 be declared as the amount which Council intends to raise by General Rates, Municipal Charge and the Annual Service Charge, which amount is calculated as follows:

    General Rates $153,337,132
    Municipal Charge $10,799,024; and
    Annual Service Charge $26,703,402.

  1. General Rates

  2. 2.1 A general rate be declared for the period 1 July 2015 to 30 June 2016.

    2.2 It be further declared that the general rate be raised by the application of differential rates.

    2.3 A differential rate be respectively declared for rateable land having the respective characteristics specified below, which characteristics will form the criteria for each differential rate so declared.

    1. 2.3.1. Farm Land – means any land which:

      1. is not less than 2 hectares in area; and

      2. is used predominantly for the business of grazing (including agistment), dairying, pig-farming, poultry farming, fish farming, tree farming, bee-keeping, viticulture, horticulture, fruit growing or the growing of crops of any kind or for any combination of those activities; or

      3. satisfies the criteria for municipal purpose benefit for large holdings to the extent that it is, for example, land that is predominantly used and maintained for heritage, cultural or environmental purposes, or land that is held as natural bushland under a trust for nature covenant, or land that is held under some other type of similar formal undertaking.

      To avoid doubt, 'business' for the purposes of identifying Farm Land has the same meaning as that given to it by section 2(1) of the Valuation of Land Act 1960 for the same purpose, being a business that:

      1. has a significant and substantial commercial purpose or character; and

      2. seeks to make a profit on a continuous or repetitive basis form its activities on the land; and

      3. is making a profit from its activities on the land, or that has a reasonable prospect of making a profit from its activities on the land if it continues to operate in the way that it is operating.

    2. 2.3.2 Residential Land - means any land:

      1. that is used exclusively for residential purposes; or

      2. on which a habitable building is erected, which building is unoccupied, and which is zoned residential under the Greater Geelong Planning Scheme.

    3. 2.3.3 Vacant Land - means any land:

      1. that does not have the characteristics of Farm Land; and

      2. on which no building is erected, save for any uninhabitable shed or shelter, the size of which does not exceed 5% of the total area of the land.

    4. 2.3.4 Petroleum Production Land – means any land that is:

      1. used primarily for the production or conveyance of petroleum and/or petroleum by-products; and

      2. is described as such in Schedule A.

    5. 2.3.5 Industrial Land – means any land that:

      1. does not have the characteristics of

        1. Vacant Land; or

        2. Commercial Land; or

        3. Petroleum Production Land; or

        4. Automobile Manufacture Land; and

      2. is used predominantly for industrial purposes, which includes manufacturing, repairing, servicing, processing and reprocessing.

    6. 2.3.6 Commercial Land – means any land that:

      1. does not have the characteristics of:

        1. Farm Land; or

        2. Industrial Land; or

        3. Petroleum Production Land; or

        4. Automobile Manufacture Land; and

      2. is used predominantly for the sale of goods or services or other commercial purposes; or

      3. on which a habitable building is erected, which building is unoccupied, and which is zoned other than residential under the Greater Geelong Planning Scheme.

    7. 2.3.7 Aluminium Production Land –

      The Aluminium Production Land differential rate has been discontinued from 2015-2016, given there are no applicable rateable properties. This follows the closure of the Alcoa smelter in December 2014.

    8. 2.3.8 Automobile Manufacture Land – means any land that is:

      1. used primarily for the manufacture of automobiles or automobile products;
        and

      2. is described as such in Schedule A.

    9. 2.3.9 Mixed Use Land – means any land that:

      1. has the characteristics of Residential Land combined with the characteristics of Commercial Land or Industrial Land; and

      2. is used partly for residential purposes and partly for commercial and/or industrial purposes.

    10. 2.3.10 The Point – Residential Land - means any land that:

      1. is used exclusively for residential purposes; or

      2. on which a habitable building is erected, which building is unoccupied, and which is zoned residential under the Greater Geelong Planning Scheme; and

      3. is described as such in Schedule A.

    11. 2.3.11 The Point – Vacant Land - means any land:

      1. that does not have the characteristics of Farm Land; and

      2. on which no building is erected save for any small uninhabitable storage shed or shelter, the size of which does not exceed 5% of the total land area; and

      3. is described as such in Schedule A.

    12. 2.3.12 The Point – Commercial Land - means any land that:

      1. does not have the characteristics of:

        1. Farm Land; or

        2. Industrial Land; and

      2. is used predominantly for the sale of goods or services, or other commercial purposes; or

      3. on which a habitable building is erected, which building is unoccupied, and which is zoned other than residential under the Greater Geelong Planning Scheme; and

      4. is described as such in Schedule A.

    2.4 A rate pursuant to the Cultural and Recreational Lands Act 1963 be declared for rateable land having the respective characteristics specified below.

    1. 2.4.1 Cultural and Recreational Land -

      Any land which -

      1. has the characteristics of Recreational land as defined by the Cultural and Recreational Lands Act 1963; and

      2. is described as such in Schedule A.

    2.5 Each differential rate and Cultural and Recreation Lands Rate will be determined by multiplying the Capital Improved Value of each rateable land (categorised by the characteristics described in paragraph 2.3 and 2.4 by the relevant percentages indicated in the following table:

    CATEGORY

    %

    Farm Land

    .002832 (or .2832 percent of Capital Improved Value).
    A rebate of 34% of the CIV by rate in dollar in accordance with Council policy for farm rating.

    Residential Land

    .002832 (or .2832 percent of Capital Improved Value).

    Vacant Land

    .004107 (or .4107 percent of Capital Improved Value).

    The Point Residential Land

    .002832 (or .2832 percent of Capital Improved Value).

    The Point Vacant Land

    .004107 (or .4107 percent of Capital Improved Value).

    The Point Commercial Land

    .005908 (or .5908 percent of Capital Improved Value).

    Petroleum Production Land

    .009133 (or .9133 percent of Capital Improved Value).

    Industrial Land

    .007881 (or .7881 percent of Capital Improved Value).

    Commercial Land

    .005908 (or .5908 percent of Capital Improved Value).

    Automobile - Production Land

    .009133 (or .9133 percent of Capital Improved Value).

    Mixed Use Land

    .004333 (or .4333 percent of Capital Improved Value).

    Cultural and Recreational

    .001846 (or .1846 percent of Capital Improved Value).


    2.6 It be recorded that Council considers that each differential rate will contribute to the equitable and efficient carrying out of Council functions; and that

    1. 2.6.1 the respective objectives of each differential rate be those specified in Schedule B;

    2. 2.6.2 the respective types or classes of land which are subject to each differential rate be those defined in Schedule B;

    3. 2.6.3 the respective uses and levels of each differential rate in relation to those respective types or classes of land be those described in Schedule B; and

    4. 2.6.4 the relevant

      1. uses of; and

      2. geographical locations of; and

      3. planning scheme zonings of; and

      4. types of buildings on the respective types or classes of land be those identified in Schedule B; and

    2.7 It be confirmed that no amount is fixed as the minimum amount payable by way of general rate in respect of each rateable land within the municipal district.

  1. Rebates

  2. 3.1 Farm Rebate

    For 2015 2016 Council declare a rebate under section 169 of the LGA of 34% for all land classified and rated as farm land. Properties defined as farms will be entitled to a rebate recognising that there is a benefit to the community in encouraging the retention of large lot primary producing holdings. An application can be made to Council to have land classified as Farm land.

  3. Waivers

  4. 4.1 Rates Assistance Waivers

    1.1. Council declares a waiver of general rates under Section 171 of the LGA for the class of persons comprised of ratepayers in respect of assessments which are categorised as Residential Land or Farm Land where the valuation of the assessment has increased, between the 2012 valuation and the 2014 valuation, by 50% or more and that increase is purely attributable to market factors, not attributable, in whole or in part, to improvements made to the assessment by the owner (or occupier). The amount of the waiver is set at:

    1. 4.1.1 between 25% and 49.99% of the general rates payable for the 2015-2016 financial year, increasing pro rata according to the valuation increase, for valuation increases between 50% and 59.99%; and

    2. 4.1.2. 50% of the general rates payable for the 2015-2016 financial year for valuation increases of 60% or more.

    3. 4.1.3. The waiver is designed to mitigate the rates shock of a valuation increase and can only be claimed in respect of an assessment once in a two year valuation cycle.

    4.2 Council declares a Housing Support waiver of 100% of general rates and municipal charge under section 171 of the LGA for the class of persons comprised of ratepayers in respect of assessments which contain the following types of housing:

    1. 4.2.1 transitional, emergency or crisis housing;

    2. 4.2.2 housing for Legatees or War Widows, provided by the Geelong Legacy Club or provided by RSL; and

    3. 4.2.3 supported housing for disabled people.

    This waiver recognises that these properties provide for specific needs within the community. Application can be made to Council to have land classified as being eligible for the waiver.

    4.3 New Corio Estate (Inappropriate Subdivision)

    For 2015-2016 financial year, Council declares a waiver of 100% of general rates and municipal charge under Section 171 of the LGA for the class of persons comprised of ratepayers in respect of assessments which are in private ownership within the inappropriate subdivision known as New Corio Estate. This rates assistance waiver recognises the financial burden associated with ownership of this land. Land within the New Corio Estate is zoned as farming land and the area has been determined to be an inappropriate subdivision due to the difficulty of providing utilities and drainage and due to its distance from other residential areas. The Minister for Environment and Climate Change has approved a native vegetation plan for this land in support of natural temperate grassland of the Victorian Volcanic Plains. The waiver recognises the ongoing encumbrances on the land that prevent owners from making any demands on Council services now and into the future.

  5. Municipal Charge

  6. 5.1 An annual municipal charge be declared for the period commencing 1 July 2015 to 30 June 2016.

    5.2 The purpose of the municipal charge is to recover some of the administrative costs of the Council.

    5.3 The charge be the sum of $94.30 for each rateable property in the municipality.

    5.4 Applications for exemption for farm land in accordance with section 159 of the LGA, is to be made within two months from the date of issue of annual rate notice.

  7. Annual Service Charge

  8. 6.1 An Annual Service Charge be declared for the period commencing 1 July 2015 to 30 June 2016.

    6.2 The Annual Service Charge be declared for the collection and disposal of refuse.

    6.3 The Annual Service Charge be $258.25 for each rateable land and non-rateable land (or part) in respect of which the Annual Service Charge may be levied.

    6.4 The criteria specified below, be the criteria, which form the basis of the Annual Service Charge, so declared:

    Geographic existence within those areas of the municipal district in which Council provides a domestic refuse collection and disposal service. The charge will be raised irrespective of whether the service is used or not.

  9. Central Activities Area Rate

  10. Council has declared a special rate in respect of the central business district of Geelong applicable to non-residential, non-exempt properties. The special rate is the Central Activities Area (CAA) Rate and is in addition to other rates and charges. The purpose of the special rate is to promote the CAA as a commercial shopping precinct using events, marketing and media.

    2015 2016 represents the final year of the Special Rate and Charge scheme. The scheme provides a 2.5% increase to raise $824,510 ($804,400 in 2014-2015). The rate in dollar for 2015-2016 is set at $0.0006478 and $0.0002024 for Cultural and Recreation (Cultural and Recreation properties are charged a reduced CAA rate, in accordance with the ratio of the recreation rate to the commercial rate).

  11. Incentives

  12. No incentives be declared as the incentives to be given by Council for the payment of General Rates, Municipal Charge and the Annual Service Charge (described earlier in this document) before the dates fixed for their payment under Section 167 of the LGA.

  13. Consequential

  14. 9.1 Notwithstanding anything said in any earlier Resolution of Council, the Geelong Advertiser be chosen, as the newspaper in which the public notice will appear.

    9.2 The Responsible Officer of Council be authorised to levy and recover the General Rates, Municipal Charge and the Annual Service Charge described earlier in accordance with the LGA.

  15. Interest

  16. Interest on unpaid rates and charges will be charged in accordance with Section 172 of the LGA. Interest will be charged at the penalty interest rate of 10.5% for 2015-2016. In proven cases of hardship where Council allows rates to be deferred, interest will be charged at 5.82% for 2015 2016.


SCHEDULE A

  1. Petroleum Production Land

    All that land generally bounded more or less by Princes Highway, Shell Parade, Corio Bay Foreshore, Wharf Road, Station Road and neighbouring land.

  2. Automobile Manufacture Land

    1. All that land generally bounded more or less by Cowies Creek, Melbourne Road, North Shore Road and Geelong – Melbourne Railway, excluding the land known as 60-80 North Shore Road being the Ford Research and Development Facility.

    2. All that land generally bounded more or less by Sea Beach Parade, St Georges Road, Geelong-Melbourne Railway and neighbouring southern land.

  3. The Point Residential Land

    All the residential land formerly described in Certificate of Title Volume 11423 Folio 073 and 074 and also described in Lot C PS 638301 and PS 722214.

  4. The Point Vacant Land

    All the vacant land formerly described in Certificate of Title Volume 11423 Folio 073 and 074 and also described in Lot C PS 638301 and PS 722214.

  5. The Point Commercial Land

    All the commercial land formerly described in Certificate of Title Volume 11423 Folio 073 and 074 and also described in Lot C PS 638301 and PS 722214.

  6. Cultural and Recreational Land

    Any land reserved under the Cultural and Recreational Lands Act 1963 including the following:

    Ratepayer Name

    Property Address

    Bareena Bowling Club Incorporated

    89 Noble Street, Newtown VIC 3220

    Drumcondra Bowling Club

    9 Glenleith Court, Geelong VIC 3220

    Geelong Race Course Trustees

    99 Breakwater Road, Breakwater VIC 3219

    Geelong Agricultural and Pastoral Society

    79 Breakwater Road, Breakwater VIC 3219

    Royal Geelong Yacht Club

    25 Eastern Beach Road, Geelong VIC 3220

    Eastern Park Bowling Club Inc

    51-55 Garden Street, East Geelong VIC 3219

    Geelong Football Club Incorporated

    360-380 Moorabool Street, South Geelong VIC 3220

    East Geelong Golf Club

    Eastern Park Circuit, East Geelong VIC 3219

    Highton Bowling Club Inc

    204 Roslyn Road, Highton VIC 3216

    Barwon Heads Golf Club Incorporated

    Golf Links Road, Barwon Heads VIC 3227

    Belmont Bowling Club Incorporated

    16-36 Reynolds Road, Belmont VIC 3216

    Geelong Lawn Tennis Club Incorporated

    12-20 Sommers Street, Belmont VIC 3216

    Geelong Bowls Club Incorporated

    4-10 Sommers Street, Belmont VIC 3216

    Beckley Park Committee of Management Inc

    40 Broderick Road, Corio VIC 3214

    Bell Park Sport and Rec Club Inc

    68 Calvert Street, Hamlyn Heights VIC 3215

    St Leonards Golf Club Inc

    79-175 Harvey Road, St Leonards VIC 3223

    Clifton Springs Golf Club Incorporated

    86-88 Clear Water Drive, Clifton Springs VIC 3222

    Clifton Springs Bowling Club

    Clifton Street, Clifton Springs VIC 3222

    Drysdale Bowling and Croquet Club inc

    19-29 Collins Street, Drysdale VIC 3222

    Lonsdale Golf Club

    31-69 Fellows Road, Point Lonsdale VIC 3225

    Portarlington Bowls Club Incorporated

    Harding Street, Portarlington VIC 3223

    Portarlington Golf Club

    92-160 Hood Road, Portarlington VIC 3223

    Leopold Sportsmans Club Inc

    131-139 Kensington Road, Leopold VIC 3224

    Ocean Grove Bowling Club

    16-24 The Terrace, Ocean Grove VIC 3226

    St Leonards Bowling Club

    1274 Murradoc Road, St Leonards VIC 3223

    Curlewis Golf Club Incorporated

    1201-1419 Portarlington Road, Curlewis VIC 3222

    Australian Croatian Sporting Centre

    15 Gibbons Road, Lara VIC 3212

    Bell Park Sports Club Inc

    515 Ballarat Road, Batesford VIC 3221

    Geelong West Bowling Club Incorporated

    12 Bowlers Avenue, Geelong West VIC 3218

    Barwon Rowing Club Inc

    2 Barwon Terrace, South Geelong VIC 3220

    Geelong Grammar School Rowing

    6 Barwon Terrace, South Geelong VIC 3220

    Geelong Rowing Association

    8 Barwon Terrace, South Geelong VIC 3220

    Corio Bay Rowing Club

    10 Barwon Terrace, South Geelong VIC 3220

    East Geelong Uniting Church Tennis Club Inc

    39 Denman Street, East Geelong VIC 3219

    East Geelong Recreation Reserve Committee

    137-139 McKillop Street, Geelong VIC 3220

    Portarlington Sailing Club

    219 Point Richards Road, Portarlington VIC 3223

    Indented Head Boat Club

    The Esplanade, Indented Head VIC 3223

    Indented Head Yacht Club

    The Esplanade, Indented Head VIC 3223

    St Leonards Yacht Club and Motor Squadron

    Lower Bluff Road, St Leonards VIC 3223

    Geelong Watersports Club Incorporated

    493-499 Wilsons Road, St Albans Park VIC 3219

    Geelong College Rowing Club

    4 Barwon Terrace, South Geelong VIC 3220

    Geelong Pistol Club

    70-80 Williams Road, Mount Duneed VIC 3216

    Geelong Table Tennis Association

    84-88 Church Street, North Geelong VIC 3215

    Western Beach Boat Club Incorporated

    74-90 Western Foreshore Road, Geelong VIC 3220

    Lagoon Boat Club Inc

    Foreshore Road, Corio VIC 3214

    Lara Sporting Club Incorporated

    4 Walkers Road, Lara VIC 3212

    Western District Car Club

    55 Beach Road, Avalon VIC 3212

    Corio Bay Sailing Club

    Foreshore Road, Corio VIC 3214

    North Shore Sports and Community Club Inc

    39 Rose Avenue, Norlane VIC 3214

    Herne Hill Bowls Club Inc

    180 McCurdy Road, Fyansford VIC 3221

    Norlane Bowling Club Incorporated

    26-36 St Georges Road, Corio VIC 3214

    Lara Bowling Club Inc

    10 Alkara Avenue, Lara VIC 3212

    Barwon Heads Bowling Club

    18 Geelong Road East, Barwon Heads VIC 3227

    Geelong and Dist Angling Club and Fish Protect Society

    9 Yuille Street, Geelong West VIC 3218

    Seabrae Boat Owners Club Inc

    302 Clifton Avenue, Leopold VIC 3224


    Properties granted Cultural and Recreational Rate status include any other not-for-profit clubs or associations having similar characteristics and objectives to Cultural and Recreational land as defined which is extended to include indoor sporting, recreational and cultural activities.

    To be considered, each property should have limited venue hire, restricted liquor licensing provisions and have little impact on neighbouring amenity.

  7. Ratepayer Name

    Property Address

    Geelong Bridge Club

    148-152 Portarlington Road, Newcomb Vic 3219

    Austrian Club Geelong Incorporated

    258 Plantation Road, Lovely Banks Vic 3221

    Serbian Parish Youth Club

    256 Plantation Road, Lovely Banks, Vic 3221

    Polish Community Association in Geelong

    35 Ryrie Street, Geelong Vic 3220

    Geelong Speedway Drivers Club Inc

    1/4 Wood Street, South Geelong VIC 3220

    Wood Street Public Recreation Reserve COM Inc.

    2/4 Wood Street, South Geelong VIC 3220

    Wood Street Public Recreation Reserve COM Inc.

    3/4 Wood Street, South Geelong VIC 3220

    Geelong Transport Drivers Social Club Inc

    4/4 Wood Street, South Geelong VIC 3220

    Croatian Community Centre of Geelong (Inc)

    172-178 Cox Road, CORIO VIC 3214

    Association of Ukrainians - Victoria

    16-21 Monastery Court, Lovely Banks VIC 3213


SCHEDULE B

  1. Farm Land

  2. Rating Objectives:

    1. To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

      1. construction and maintenance of public infrastructure;

      2. development and provision of health and community services; and

      3. provision of general support services.

    2. To encourage and support the business of primary production and, where appropriate, expand the business of primary production.

    These objectives will be met by setting the Farm Land differential at 100% of the Residential Land differential and by the provision of a farm rebate under Section 169 of the LGA.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.1

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    The level of the differential rate less the applicable rebate is the level, which Council considers it necessary to achieve the objectives specified above.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  3. Residential Land

  4. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.2

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    The level of the differential rate is the level which Council considers is necessary to achieve the objectives specified above.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  5. Vacant Land

  6. Rating Objectives:

    1. To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

      1. construction and maintenance of public infrastructure;

      2. development and provision of health and community services; and

      3. provision of general support services.

    2. To encourage the prompt development of vacant land to attract new residents and businesses to the City of Greater Geelong.

    3. To discourage untimely and unnecessary divisions of land.

    These objectives will be met by setting the Vacant Land differential at 145% of the Residential Land differential.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.3

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Geelong Regional Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Geelong Regional Planning Scheme.

    Types of Buildings

    No building must be located on the land or constructed prior to 30 June 2016 save for any uninhabitable shed or shelter that does not exceed more than 5% of the total area of the land.

  7. Petroleum Production Land

  8. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    The Petroleum Production Land differential is set at 322% of the Residential Land differential with the intention that the Petroleum Production Land differential be at the Industrial Land rate differential from 2017-2018.

    Types and Classes

    Rateable land having the relevant characteristics described previously 2.3.4

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  9. Industrial Land

  10. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.5

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  11. Commercial Land

  12. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.6

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  13. Aluminium Production Land

  14. The Aluminium Production Land differential rate has been discontinued from 2015-2016, given there are no applicable rateable properties. This follows the closure of the Alcoa smelter in December 2014.

  15. Automobile Manufacture Land

  16. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    The Automobile Manufacture Land differential is set at 322% of the Residential Land differential with the intention that it will be at the Industrial Land differential rate from 2017-2018.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.8

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  17. Mixed Use Land

  18. Rating Objective:

    To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

    1. construction and maintenance of public infrastructure;

    2. development and provision of health and community services; and

    3. provision of general support services.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.9

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    Wherever located within the municipal district.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  19. The Point – Residential Land

  20. Rating Objectives:

    1. To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council generally, including the:

      1. construction and maintenance of public infrastructure;

      2. development and provision of health and community services;

      3. provision of general support services; and

      4. management of environmentally sensitive land.

    2. To ensure that, following the development of the Point Land, and transfer to Council of the management of environmentally sensitive land, including the provision of a range of services around an existing waterway, constructed lake and canal system, an equitable and efficient financial contribution to the cost of Council's management responsibilities will be made by the ratepayers in respect of that land.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.10

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  21. The Point – Vacant Land

  22. Rating Objectives:

    1. To ensure that all rateable land makes an equitable and efficient financial contribution to the cost of carrying out the functions of Council, generally including the:

      1. construction and maintenance of public infrastructure;

      2. development and provision of health and community services;

      3. provision of general support services; and

      4. management of environmentally sensitive land.

    2. To ensure that, following the development of the Point Land, and transfer to Council of the management of environmentally sensitive land, including the provision of a range of services around an existing waterway, constructed lake and canal system, an equitable and efficient financial contribution to the cost of Council's management responsibilities will be made by the ratepayers in respect of that land.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.11

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  23. The Point – Commercial Land

  24. Rating Objectives:

    1. To ensure that all rateable land makes an equitable and efficient financial contribution to cost of carrying out the functions of Council, generally including the:

      1. construction and maintenance of public infrastructure;

      2. development and provision of health and community services;

      3. provision of general support services; and

      4. management of environmentally sensitive land.

    2. To ensure that, following the development of the Point Land, and transfer to Council of the management of environmentally sensitive land, including the provision of a range of services around an existing waterway, constructed lake and canal system, to ensure that an equitable and efficient financial contribution to the cost of Council's management responsibilities will be made by the ratepayers in respect of that land.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.3.12

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.

  25. Cultural and Recreational Land

  26. Has the characteristics of Recreational land as defined by the Cultural and Recreational Lands Act 1963.

    Types and Classes

    Rateable land having the relevant characteristics described previously in 2.4.1

    Use and Level of Differential Rate

    The differential rate will be used to fund some of those items of expenditure described in the Budget adopted by Council.

    Geographic Location

    As described in Schedule A.

    Use of Land

    Any use permitted under the Greater Geelong Planning Scheme.

    Planning Scheme Zoning

    The zoning applicable to each rateable land within this category, as determined by consulting maps referred to in the Greater Geelong Planning Scheme.

    Types of Buildings

    All buildings which are now constructed on the land or which are constructed prior to 30 June 2016.


[Back to Top]

3. Proposed City Plan 2013-2017 (2015-2016 Update)

Portfolio:

Governance - Cr Lyons (Mayor)

Source:

Strategy and Performance - Corporate Strategy

General Manager:

Dean Frost

Index Reference:

Subject: Corporate Strategy


Purpose

City Plan 2013-2017 has been reviewed as per section 125(7) of the Local Government Act 1989. This report is to advise Council of the proposed amendments/update.


Summary

Cr E Kontelj moved, Cr Harwood seconded -

That Council:

  1. note that in accordance with section 125(7) of the Local Government Act 1989, City Plan 2013-2017 has been reviewed and as a result:

    1. 2015-2016 Draft City Plan Actions have been added under each Strategic Direction/Priority;

    2. Strategic Resource Plan has been updated using the draft 2015-2016 Annual Budget as the base year; and

    3. Revised message from the Mayor.

  2. note the adjustments to City Plan 2013-2017 (2015-2016 Update) (as per Appendix 1-1) and take the necessary steps to advise the Minister of these adjustments pursuant to section 125(10) of the Local Government Act 1989.

Carried.


Background

The Local Government Act 1989 requires that a Council must prepare and approve a Council Plan within the period of six months after each general election or by the next 30 June, whichever is later.
Section 125 of the Local Government Act also prescribes that a Council Plan must include:

In subsequent years, councils are required to, at least once in each financial year; consider whether the current Council Plan requires any adjustment in respect of the remaining period of the Council Plan.

The Council’s performance and results in achieving the strategic indicators of the City Plan are required to be reported in the Council’s Annual Report.

City Plan 2013-2017 was developed to reflect the results of the extensive community engagement which was undertaken, Council’s current priorities and the supporting resource allocation.

The framework for the City Plan 2013-2017 incorporates the planning framework based on the on the Quadruple Bottom Line framework and features four strategic directions (Community Wellbeing, Growing our Economy, Sustainable Built and Natural Environment and How We Do Business), supporting internal objectives and the Council’s Vision, Mission, Values and Behaviours section.

City Plan identifies the key priorities, strategies and progress indicators that are currently planned over the said four-year period, as well as detailed actions associated with implementing this four-year City Plan.

The priorities under each of the four strategic directions are as follows:

Community Wellbeing

Growing our Economy

Sustainable Built and Natural Environment

How We Do Business

All the actions within City Plan have been developed collaboratively across the organisation and support the long-term social, environmental and economic benefits for the community articulated through the Vision, Mission and Objectives established by the Council.


Discussion

City Plan 2013-2017 (2015-2016 Update) has been reviewed pursuant to section 125(10) of the Local Government Act 1989. It contains the following amendments:

Two indicators have been removed:

The remainder (and majority) of City Plan 2013-2017 remains unchanged.

A draft ‘City Plan 2013-2017 (2014-2015 Update)’ has been developed and will be available at Customer Service Centres and on Council’s website as per section 125(11) of the Local Government Act 1989.

Pursuant to section 125(10) of the Local Government Act 1989, the Minister will be notified of these adjustments and receive a copy of the updated City Plan.


Environmental Implications

City Plan 2013-2017 (2015-2016 Update) outlines the objectives and strategies to deliver the environmental benefits to the community. Details of these can be found within the Sustainable Built and Natural Environment Strategic Direction.


Financial Implications

City Plan 2013-2017 (2015-2016 Update) includes Council’s four-year financial strategy and plan. The proposed 2015-2016 Annual Budget is the base year in the Strategic Resource Plan in this revised City Plan.


Policy/Legal/Statutory Implications

The Local Government Act 1989 requires that a Council must prepare and approve a Council Plan within the period of 6 months after each general election or by the next 30 June, whichever is later.

Section 125(2) of the Local Government Act also prescribes that a Council Plan must include:

If a Council makes an adjustment to the Council Plan, the Council must within 30 days of making the adjustment advise the Minister of the details of the adjustment to the Council Plan.

The draft City Plan 2013-2017 (2015-2016 Update) complies with the Local Government Act, 1989.


Alignment to City Plan

Not applicable.


Officer Direct or Indirect Interest

There is no direct or indirect officer interest to which this report relates.


Risk Assessment

Failing to notify the Minister of any adjustments would result in non-compliance.


Social Considerations

City Plan 2013-2017 (2015-2016 Update) outlines the objectives and strategies to deliver the social benefits to the community.


Human Rights Charter

City Plan 2013-2017 (2015-2016 Update) will be made available on Council’s website and on request at Council’s Customer Service Centres. There are no known positive or negative effects.


Consultation and Communication

City Plan 2013-2017 (2015-2016 Update) will be available for inspection at Council’s Customer Service Centres and on Council’s Internet site (www.geelongaustralia.com.au).

Public submissions on the revised City Plan are not required as per the Local Government Act 1989, these are only required when the new Council Plan is prepared post a general Council election.

The Minister will be notified of any amendments to City Plan following review each subsequent year.


[Back to Top]

4. City Plan 2013-2017 Progress Report to March 2015

Portfolio:

Governance - Cr Lyons (Mayor)

Source

Strategy and Performance

General Manager:

Dean Frost

Index Reference

Corporate Strategy Planning


Purpose

Council at its meeting on 24 June 2014 adopted the 2014-2015 Update of City Plan 2013-2017, which outlines the Strategic Directions and Priorities planned by the Council over the four-year period, and the Annual Business Plan Actions planned for the coming 12 months.

This report is the progress report to Council of the organisations achievements against these actions.


Summary

Attachment A details the status and provides commentary against the Annual Business Plan actions (previously provided with Briefing papers). The key to the status of actions is:

On Schedule:

Green

171

Completed:

Black

29

Major Issue:

Red

1

Minor Issue:

Yellow

26

Not Started:

White

5

Total Actions

 

232


Cr Harwood moved, Cr E Kontelj seconded -

That Council receives and notes the City Plan Progress Report to 31 March 2015.

Carried.


Background

Council at its meeting on 24 June 2014 adopted the 2014-2015 Update of City Plan 2013-2017 which outlines the Strategic Directions and Priorities planned by the Council over the four-year period, and the Annual Business Plan Actions planned for the coming 12 months.

Community Wellbeing

Healthy Together Geelong: to enhance health, wellbeing and quality of life of Greater Geelong Communities.

Growing Our Economy

Securing Geelong’s economic future.

A Sustainable Built and Natural Environment

Partnering with our community to protect and enhance our natural ecosystems and to encourage sustainable design and reduced resource consumption.

How We Do Business

We will focus on developing and maintaining effective working relationships to deliver Council’s strategic directions and cost effective services that meet the changing needs of the community.


Discussion

This report and attachment indicates the status of the actions in City Plan 2013-2017 for the 2014-2015 financial year as at 31 March, 2015.

The attachment provides status and comments for each of the 232 actions within the four strategic directions.

There has been significant progress in the March quarter towards achieving the actions in 2014-2015 including:

Community Wellbeing

Status Summary:

On Schedule:

78

Completed:

14

Major Issue:

1

Minor Issue:

13

Not Started:

4

 

 

Growing Our Economy

Status Summary:

On Schedule:

44

Completed:

6

Major Issue:

0

Minor Issue:

4

Not Started:

1

 


Sustainable Built and Natural Environment

Status Summary:

On Schedule:

22

Completed:

3

Major Issue:

0

Minor Issue:

8

Not Started:

0

 


How We Do Business

On Schedule:

27

Completed:

6

Major Issue:

0

Minor Issue:

1

Not Started:

0

 



Environmental Implications

There are several actions under the Sustainable Built and Natural Environment Strategic Direction within City Plan that aim to enhance and protect natural areas and ecosystem health, support our community to live sustainably, advocate for and promote sustainable design and development, and minimise our environmental footprint.


Financial Implications

Council’s Annual Budget provides the Resource Plan to support the initiatives identified within the adopted Annual Business Plan.


Policy/Legal/Statutory Implications

Council’s external auditors will undertake a Performance Audit of the planned Key Strategic Activities and prepare a report as part of the ‘sign off’ of the Annual Accounts.


Alignment to City Plan

This report is the quarterly progress report of the organisation’s achievements against the adopted City Plan 2013-2017, 2014-2015 actions.


Officer Direct or Indirect Interest

There is no conflict of interest to be disclosed.


Risk Assessment

The risks arising from the actions are managed within the framework of the Council’s adopted Policies, Procedures and Risk Management strategies.


Social Considerations

Several of the actions identified within City Plan are aimed at improving the quality of life for the residents in the City of Greater Geelong. This is particularly the case for actions within the Community Wellbeing Strategic Direction.


Human Rights Charter

This report provides an update on the implementation of City Plan 2013-2017 and will be made available on Council’s website and on request at Council’s Customer Service Centres as part of the Council meeting minutes. There are no known positive or negative effects.


Consultation and Communication

A comprehensive report on the 2014-2015 City Plan actions will be published in the City of Greater Geelong Annual Report by 30 September 2015, which will be submitted to the Minister for Local Government and available to the public in hard copy and on the Council’s website (www.geelongaustralia.com.au).


[Back to Top]

5. Combined Amendment C261 and Planning Permit 1163/2013 130-150 Forest Road South, Lara - Adoption

Portfolio:

Planning - Cr Michelle Heagney

Source:

Planning and Tourism - Strategic Implementation

General Manager:

Peter Bettess

Index Reference:

Amendment C261 and Planning Permit 1163/2013


Purpose

The purpose of this report is to consider the submissions about Amendment C261 which is a Combined Amendment/Planning Permit to enable a residential development in Forest Road South, Lara and to adopt the Amendment.


Summary

Cr Heagney moved, Cr E Kontelj seconded -

That Council resolves to:

  1. adopt Amendment C261 in the form as outlined in Appendix 6 of this report;

  2. submit the adopted Amendment with the prescribed information to the Minister for Planning requesting approval;

  3. recommend to the Minister for Planning that Planning Permit 1163/2013 be approved in the form outlined in Appendix 7 of this report; and

  4. sign and seal the accompanying Section 173 Agreement (Appendix 5 of this report).

Carried.


Background

Amendment 261 resulted from an application made by TGM Group P/L on behalf of L. Bisinella Developments P/L for a combined Planning Scheme Amendment/Planning Permit on land situated at 130-150 Forest Road South, Lara, pursuant to section 96A of the Planning and Environment Act.

The exhibited Amendment proposes the rezoning of the vacant 15.48 hectare site from Farming Zone to part General Residential Zone Schedule 1 (GRZ1), part Public Use Zone 6 and part Public Park and Recreation Zone. The permit would approve a conventional 108 lot residential subdivision on the northern half of the site and removal of some native grassland. Most of the southern half of the land has been set aside for a retarding basin and open space which will be transferred to Council’s ownership. A remnant portion of the land along the Forest Road frontage does not form part of the subdivision development proposal and will remain in the ownership of L. Bisinella Developments.

Appendix 1 shows the exhibited zoning as described above and Appendix 2 shows the conceptual future development of the site. An aerial photo of the subject land and the surrounding area is Appendix 3.

At its meeting on 12 August 2014 the Council resolved to exhibit the combined Amendment C261/draft permit 1163/2013. The Council report addressed the main issues requiring consideration in the assessment of this proposal which can be briefly summarised as follows:-


Discussion

Amendment C261 was placed on public exhibition from 9 October 2014 until 10 November 2014. Notices were placed in the Geelong Advertiser and Independent and sent to all adjoining and opposite landowners and occupiers and all relevant public authorities.

As a result of the exhibition of the Amendment the Council received 5 submissions, one from the applicant and four from public authorities. These submissions are summarised in Appendix 4.

The next section of the report addresses the issues raised in the submissions:

Applicant’s Submission

The applicant lodged an initial submission seeking removal of the 0.5 ha neighbourhood park on the grounds that the storm water retention basin and wetland reserve would satisfy Council’s 10% open space requirement. The initial submission also sought the following changes to the accompanying permit:

Council officers consider that an unencumbered 0.5 ha landscaped neighbourhood park incorporating a children’s playground must be provided as the minimum open space requirement to serve future residents.

Following further negotiations between Council officers and the applicant, and in an effort to avoid the need for a potentially time consuming and costly Panel hearing, Bisinella Developments has agreed to provide the unencumbered 0.5ha park as described above. In addition Bisinella Developments propose that the stormwater retention basin be constructed and grassed in a manner which also makes it suitable as an informal recreation area, further enhancing the open space provision of the area.

To give effect to these arrangements and provide the applicant with some flexibility in the detailed design of the storm water basin and the 0.5 ha park, Bisinella Developments are seeking removal of the exhibited Public Park and Recreation zone (PPRZ) from the Amendment to be replaced by a Section 173 Agreement requiring provision of the park. In the short term the land to be used for the park will remain in the Farming zone and the PPRZ will be applied when its exact boundaries are established. Council officers support these changes. The proposed S173 Agreement, signed by the applicant, is Appendix 5.

Following exhibition of the Amendment the applicant has submitted evidence, confirmed by Council’s Environment Unit, that the native grassland on the subject land is considered to be “re-growth” which has naturally established and is less than 10 years old. In these circumstances the exemption from a permit requirement as contained in Clause 52.17 applies. The permit to accompany the Amendment has been amended to remove reference to native vegetation removal.

The applicant has decided to withdraw its objection to one of the VicRoads permit conditions as contained in their initial submission.

  1. Barwon Water

    Barwon Water’s only concern is that the residential subdivision needs to be designed such that residential lots and local roads do not impact on its 12 metre wide water supply easement along the west side of Forest Road South. This easement falls within the existing Public Acquisition Overlay (PAO). The permit includes conditions to meet VicRoads requirements that the PAO setback be retained, also addressing Barwon Water’s concern.

  2. APA GasNet

    APA raised the issue of the existence of a high pressure gas pipeline to the south of the subject land. It has subsequently indicated it has no objection to the proposed development proceeding in accordance with the draft permit.

  3. Department of Primary Industries (now Department of Environment, Land, Water and Planning)

    DEPI submitted that the vegetation assessment report submitted with the application required a further review to assess the existence of remnant vegetation.

    No permit is required for vegetation removal for the reasons set out in the above section of this report.

    The Department acknowledges the changed circumstances since it wrote its submission and has no objection to the amendment now proceeding.

  4. Public Transport Victoria (PTV)

    PTV raises no objections to the amendment and has sought the inclusion of additional permit conditions requiring the developer to construct new bus stops on both sides of Forest Road South.

    The additional conditions have been included in the permit and agreed to by the applicant.
    As there are now no outstanding issues to be resolved this Amendment can now be adopted. Appendix 6 is the modified Amendment C261 being recommended for adoption as described in this report. Appendix 7 is Permit 1163/2013 to be recommended to the Minister for Planning for approval incorporating the changes arising from the consideration of issues raised by the applicant and public authorities. The changes made to the exhibited permit are highlighted.


Environmental Implications

The Amendment gives effect to recommendations of the Lara Structure Plan which has addressed the wider environmental implications of development of the town.

A Vegetation Assessment report accompanying the application rates the site as having local significance for biodiversity conservation which does not present limitations to development.


Financial Implications

All the costs associated with the development and the provision of additional services to the area will be met by the developer. The Council will become responsible for the ongoing maintenance of the new retarding basin and neighbourhood park.


Policy/Legal/Statutory Implications

The proposed Amendment is considered to be generally consistent with a range of State and Council planning policies in the Planning Scheme. In particular, this area has been identified for investigation for future residential growth in the adopted Lara Structure Plan as described in this report.

The Lara Structure Plan (a reference document in the MSS) aims to ensure adequate levels of open space are provided within new residential areas to cater for the recreation needs of the community. To achieve this outcome it directs that a 10% unencumbered open space contribution be made as part of residential rezoning applications, unless otherwise negotiated.


Alignment to City Plan

Amendment C261 supports both the Growing our Economy and Sustainable Built and Natural Environment strategic directions of City Plan, particularly insofar as it is facilitating sustainable development in accordance with an adopted township Structure Plan.


Officer Direct or Indirect Interest

No Council officers have any direct or indirect interest, in accordance with Section 80 (c) of the Local Government Act.


Risk Assessment

No risks have been identified in adopting Amendment C261 and the accompanying planning permit as being recommended by this report.


Social Considerations

Whilst the subject land is located on the edge of the town, it is located on a public bus route and is within easy walking distance to Lara Lake primary school. It adjoins existing and developing residential areas and will have good access to the town’s open space network.


Human Rights Charter

Amendment C261 does not impact on any basic rights, freedoms and responsibilities as set out in the Charter. Planning legislation ensures an open Community Consultation process enabling people to freely express their views and obtain a fair hearing before an Independent Panel.

Consultation and Communication

Full public notification of the Amendment was given in accordance with the provisions of the Planning and Environment Act. All adjoining and nearby property owners received direct notification of the exhibition of the Amendment. No owners or occupiers in the surrounding area have made a submission to Amendment C261.


Appendix 1 – Exhibited Zoning

Exhibited Zoning - Amendment C261

Appendix 2: Exhibited Future Site Development

Exhibited Future Site Development - Amendment C261

Appendix 3: Aerial Image

Aerial image - Amendment C261

Appendix 4: Summary of Submissions

No

Name/Company

Attn:

Address

Suburb

Type

Summary of Submission

1

APA GasNet Australia

Lachlan Marshall

P O Box 4204

DANDENONG

No objection

APA advises a high pressure gas pipeline runs parallel to and approx 430 metres south of the southern boundary of the subject land. APA has a direct interest in the design and development of any land within 550 metres of the pipeline to ensure the risk to life and property is reduced in the event of a rupture of the pipeline. It requested further discussion with Council Officers.

Following further advice provided to APA by Council, it has confirmed “that APA GasNet has no objection to the development proceeding” as provided for in the draft permit.

2

Barwon Water

Rhys Bennett

P O Box 659

 

No Objection

All service upgrades to be funded by the developer. Conditions to be included on the permit have been provided. Barwon Water has a 12 metre easement containing the Northern Water Supply Feeder main and requires the proposed residential subdivision to be relocated such that residential lots and a service road avoid the easement (which falls within the VicRoads PAO)

3 DEPI (now DELWP) Geoff Brooks P O Box 103 GEELONG VIC 3220 Further Review DELWPI has reviewed the vegetation assessment report submitted with the application and considers it fails to provide adequate evidence that the native vegetation on the site is not a remnant patch which requires assessment under current decision-making arrangements. Suggests the report requires further review.

4

Public Transport Victoria

Richard McAliece

P O Box 4724

MELBOURNE VIC 3001

No Concerns

PTV has no concerns about the rezoning changes. Requests additional permit condition to improve public transport access requiring provision of new bus stops on both sides of Forest Road South, adjacent to the subject land.

5

TGM Group on behalf of L Bisinella Development P/L

Chris Marshall

P O Box 1137

GEELONG VIC 3220

 

Generally supports the amendment and draft permit which is consistent with the Lara Structure Plan.

The initial submission requested deletion of the 0.5 ha neighbourhood park on the basis the adjoining storm water detention basin and wetland reserve is sufficient to comply with Council’s open space requirements.

The initial submission provided evidence that the subject land has been cropped within the past 10 years. On this basis, deletion of reference to Native Vegetation removal from the permit and conditions 30 and 31 which apply to it are sought.

The initial submission also objects to the VicRoads’ condition which seeks to prevent compensation payable for the Forest Road widening (subject to existing PAO) Submits condition should be deleted.

The applicant has subsequently submitted, in an effort to avoid the need for a Panel Hearing, it will provide the 0.5 ha unemcumbered park as sought by Council. It regards deletion of the exhibited PPRZ to provide increased design flexibility, with the 0.5 park requirement to be implemented by means of a Section 173 Agreement.

The applicant has subsequently withdrawn its initial objection to the VicRoads condition.



Appendix 5: Section 173 Agreement signed by Bisinella Developments

Section 173 Agreement signed by Bisinella Developments - cover page
Section 173 Agreement signed by Bisinella Developments - table of contents
Section 173 Agreement signed by Bisinella Developments - page 1 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 2 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 3 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 4 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 5 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 6 of 7 pages
Section 173 Agreement signed by Bisinella Developments - page 7 of 7 pages
Concept - Overall layout plan

Appendix 6: Amendment to be Adopted

Planning and Environment Act 1987

GREATER GEELONG PLANNING SCHEME

AMENDMENT C261

INSTRUCTION SHEET

The planning authority for this amendment is Greater Geelong Planning Scheme

The Greater Geelong Planning Scheme is amended as follows:

Planning Scheme Maps

The Planning Scheme Maps are amended by a total of 1 attached map.

Zoning Maps

Planning Scheme Map No18 in the manner shown on the attached map marked “Greater Geelong Scheme, Amendment C216.”


End of document

Amendment C261: General Residential Zone = Schedule 1 and Public Use Zone - local government

Appendix 7: Final Planning Permit (No. 1163/2013) for Adoption

PLANNING
PERMIT

Permit No.

1163/2013

Planning Scheme

Greater Geelong Planning Scheme

Responsible Authority

Greater Geelong City Council

ADDRESS OF THE LAND

130-150 FOREST ROAD SOUTH, LARA

THE PERMIT ALLOWS

STAGED MULTI LOT SUBDIVISION GENERALLY IN ACCORDANCE WITH THE ENDORSED PLANS

 

THE FOLLOWING CONDITIONS APPLY TO THIS PERMIT:


AMENDED PLANS

  1. Prior to the certification of the first stage of the Plan of Subdivision, amended plans to the satisfaction of the Responsible Authority must be submitted to and approved by the Responsible Authority. When approved the plans will be endorsed and will then form part of the permit. The plans must be drawn to scale with dimensions and three copies must be provided. The plans must be generally in accordance with the plans submitted with the application, but modified to show:

    1. The plan of subdivision layout revised to incorporate the requirements of VicRoads conditions 30 and 31.

    2. The .5ha Public Open Space in accordance with the requirements of the S173 Agreement accompanying Amendment C261.


ENDORSED PLANS

  1. The layout and site dimensions of the proposed subdivision as shown on the endorsed plan(s) shall not be altered or modified without the written consent of the Responsible Authority. There are no requirements to alter or modify the endorsed plan if a plan is certified under the provisions of the Subdivision Act 1988 that is generally in accordance with the endorsed plans.


CONSTRUCTION MANAGEMENT PLAN

  1. Prior to commencement of works for each stage of the subdivision, a Construction Management Plan must be submitted to and approved by Council’s Engineering Services and Environment departments and must address items including (but not be limited to) the following:

    1. The protection of all existing vegetation and waterways;

    2. Show access locations for construction vehicles;

    3. All appropriate control of site emissions during construction and the defects liability period;

    4. A staging plan for all construction phases including indicative dates for commencement and completion;

    5. Intended access for construction vehicles;

    6. Engineering assessment of assets that will be impacted on by construction and recommended techniques to minimise any adverse impact;

    7. Details of actions to be implemented to in the event of damage to abutting assets;

    8. Details of where construction personnel will park;

    9. Hours/days of construction, including deliveries. (Note: These hours must be consistent with the Environment Protection Authority (EPA) legislation/guidelines);

    10. Phone numbers of on-site personnel or other supervisory staff to be contactable in the event of issues arising on site;

    11. Details of site cleanliness and clean up regimes;

    12. Location of material storage;

    13. Dust suppression management;

    14. Details of measures to be maintained during the housing construction phase of development to prevent sediment entering downstream drainage infrastructure;

    15. Any other measures that are consistent with the following Environmental Protection Authority publications: ‘Environmental Management Guidelines for Major Construction Sites’, ‘Construction Techniques for Sediment and Pollution Control’ and ‘Doing it Right on Subdivisions’

  2. All development and works must be carried out in accordance with the Construction Management Plan endorsed under this permit, all to the satisfaction of the Responsible Authority. Any non-compliance identified by the Responsible Authority must be rectified immediately at no cost to Council.


ENGINEERING

  1. Excavated material shall not be carted off the site except with the written approval of the Responsible Authority.

  2. No material shall be brought onto the site for use as filling within the subject area under this Permit, unless with the written approval of the Responsible Authority. Prior to any approval being issued by the Responsible Authority for imported filling to be used on the site, the applicant must submit for approval to the Responsible Authority, samples of proposed filling, details of the source of the filling, details of proposed traffic routes to be traversed, soil testing results and reports in regard to the presence of contaminants in the filling, and the suitability of filling to be placed on site.

  3. All areas to be filled shall be stripped of vegetation and any top soil shall be removed and stockpiled for reuse over the filled areas. Only approved filling material shall be placed on the site. The filling shall be placed in maximum 150 mm layers, or as approved otherwise by the Responsible Authority, and compacted to the applicable level for filling on allotments and within future roadways in accordance with AS3798, to the satisfaction of the Responsible Authority.

  4. At the completion of the bulk earthworks, and at completion of the works for each stage, all disturbed areas shall be hydro mulched with an approved seed and fertilizer mixture to the satisfaction of the Responsible Authority to suppress dust, and minimise erosion, unless approved otherwise by the Responsible Authority.

  5. All works must be undertaken in accordance with the recommendations of any geotechnical reports.

  6. Prior to the commencement of site works for any stage of the subdivision, the developer is required to submit detailed drainage construction plans to the Responsible Authority for approval. The plans shall generally be in accordance with the TGM Concept Design (Ref 11573-200) and Grand Lakes Regional Hydraulic Modelling and Impact Report – Addendum 8 (BMT WBM, Nov 2013) and include, but not limited to:

    1. Details of pits and pipes sizes;

    2. Finished and existing surface levels;

    3. Creation of appropriate easements;

    4. Detention basin(s) including any required drainage reserves, water quality treatment; and, Connection to the legal point of discharge in accordance with the Drainage Masterplan. The Consulting Engineer must show that the design for the drainage system complies with the requirements of the Infrastructure Design Manual and any other relevant standards. Site run-off shall be limited to equivalent pre-developed levels for rainfall events up to and including the critical 100 year ARI event. An appropriate on site detention system shall be designed to limit site run-off to the pre-developed levels to the satisfaction of the Responsible Authority.

    5. The stormwater drainage system on the site must be designed such that stormwater run-off exiting the land meets the current best practice performance objectives for stormwater quality as follows:

      1. 80% retention of the typical annual load of suspended solids;

      2. 45% retention of the typical annual load of total phosphorous;

      3. 45% retention of the typical annual load of total nitrogen; and

      4. 70% retention of the typical annual load of gross pollutants.

    6. Details of access requirements for maintenance vehicles into the stormwater detention basins and wetlands.

    7. Note: Detailed Design Plans for any stage that result in flood levels on existing properties being adversely affected by the proposed works will not be approved for construction.

  7. Prior to the commencement of site works for any stage of the subdivision, the developer is required to submit detailed roadwork construction plans to the Responsible Authority for approval. The plans shall generally be in accordance with the TGM Concept Design (Ref 11573-200) and Grand Lakes Regional Hydraulic Modelling and Impact Report – Addendum 8 (BMT WBM, Nov 2013) and include, but not limited to:

    1. Fully sealed pavement with kerb and channel for new internal roads;

    2. Construction of Canterbury Road so that the minimum road width is 10m;

    3. Any external roadworks and treatments;

    4. Concrete footpaths;

    5. Line-marking and signage installation.

    Note: Detailed Road Plans for any stage that result in flood levels on existing properties being adversely affected by the proposed works will not be approved for construction.


PRIOR TO CERTIFICATION

  1. Prior to certification of the Plan of Subdivision for each stage, easements for the purposes of ‘Drainage’ must be set aside in favour of the City of Greater Geelong, to the satisfaction of the Responsible Authority.

  2. The plan of subdivision submitted for certification for each stage of the development shall nominate a minimum finished floor level for each lot, to the satisfaction of the Responsible Authority. The FFL shall be a minimum of 300mm above top of kerb or the 1% AEP flood extent as depicted in fig 7-7 of ‘Grand Lakes Regional Hydraulic Modelling and Impact Report – Addendum 8’ (BMT WBM, Nov 2013).


PRIOR TO STATEMENT OF COMPLIANCE

  1. Prior to the issuing of a Statement of Compliance for the relevant stage of the subdivision, road and drainage works, including basin(s), must be constructed in accordance with the approved plans and specifications to the satisfaction of the Responsible Authority.

  2. Prior to the issuing of a Statement of Compliance for the relevant stage of subdivision, relevant street sign/s must be erected to the satisfaction of the Responsible Authority.

  3. Prior to the issuing of a Statement of Compliance for the relevant stage of subdivision, street lighting must be provided within the site and along external frontages in accordance with the relevant Australian Standard(s), unless otherwise agreed in writing by the Responsible Authority and unless it can be demonstrated that existing street lighting is sufficient for public safety to the satisfaction of the Responsible Authority.


TRAFFIC

  1. Prior to works commencing for each stage of the subdivision, an Independent Road Safety Audit must be carried out for the internal and external intersection treatments at the detailed design stage by a suitably qualified auditor in accordance with Austroads “Road Safety Audit” (2002). The findings of the Independent Road Safety Audit must then be formally responded to and implemented by the subdivider with the results submitted to the Responsible Authority for approval.

  2. A Local Area Traffic Management (LATM) plan must be developed prior to the lodgement of Stage 1 construction drawings in conjunction with Council’s Traffic Engineering unit. The developed LATM plan must include indicative lot numbering and street names to coincide with the internal street network and any modifications to intersections.


LANDSCAPE MASTER PLAN

  1. Prior to the commencement of works, a landscape master plan (incorporating a street tree master plan) for the permit area, prepared by a person suitably qualified or experienced in landscape design, must be approved by the responsible authority. When approved, the plan will be endorsed and will then form part of the permit. The plan must be drawn to scale with dimensions and three hard copies plus an electronic copy must be provided. The plan must show and include the following to the satisfaction of the responsible authority:

    1. A survey (including location, size and botanical name) of all existing vegetation on the land;

    2. Any vegetation that is approved to be retained, removed and/or lopped, including details of tree protection zones;

    3. The landscaping theme and graphical concepts to be developed for the subdivision and reserve;

    4. The species to be used for and general layout of all street tree planting;

    5. A species list of all proposed vegetation including aquatic vegetation of local provenance;

    6. The areas which will be available for landscaping;

    7. A play space in the public open space reserve;

    8. Footpath and on-road bicycle linkages through the permit area and public reserves, indicative connections to nearby open space and indicative connections to the external path network;

    9. The location and indicative design of drainage and/or WSUD infrastructure within public reserves;

    10. Maintenance vehicle access points;

    11. The style and location of fencing, which is to be visually permeable, to all private property that directly abuts a reserve (except road reserve).


LANDSCAPING PLANS

  1. Prior to Statement of Compliance being issued for each relevant stage of the subdivision, landscape plans to the satisfaction of the Responsible Authority for all landscape works in that particular stage of subdivision must be submitted to and approved by the Responsible Authority. When approved, the plans will be endorsed and will then form part of the permit. The plan must be drawn to scale with dimensions and three hard copies plus an electronic copy must be provided. The plan must be consistent with the endorsed landscape master plan and provide detailed planting, construction and specification details for all of the proposed landscaping works on public reserves and road reserves. The landscape plan must show the following to the satisfaction of the responsible authority:

    1. A survey (including location, size and botanical name) of all existing vegetation on the land;

    2. The proposed Q10 and Q100 events extent;

    3. Any tree(s) proposed for retention within a road reserve or public open space for any stage of the development must be independently assessed by a suitably qualified arborist which details suitability for retention and ongoing management recommendations for the tree(s). The detailed landscape response for the area in which the tree(s) are located must be informed by the arboricultural assessment;

    4. The layout of new planting in all road reserves and municipal reserves;

    5. The layout and zonation detail of new aquatic planting in waterways and any constructed water bodies in municipal reserves;

    6. A detailed planting schedule of all proposed terrestrial trees, shrubs, and groundcovers including botanical names, common names, pot sizes, sizes at maturity and quantities of each plant;

    7. A detailed planting schedule of all proposed aquatic planting including botanical names, common names, supply sizes, sizes at maturity, zonation detail, planting densities and quantities of each plant with a note that plants must be sourced from local provenance material;

    8. The proposed layout, materials and finishes of paths, areas of pavement, structures, play spaces, fences, maintenance access gates and street furniture;

    9. Detailed planting and construction drawings including site contours and any proposed changes to existing levels including any structural elements such as retaining walls;

    10. Additional supporting information, such as certified structural designs or building forms;

    11. A playground design complying with AS4685:2004 Playground Equipment Safety and AS/NZS4422:1996 Playground Surfacing;

    12. All proposed street tree planting using semi-advanced trees with a minimum container size of 45 litres;

    13. The maintenance schedule for all proposed landscaping, including hard and soft landscaping elements;

    14. Bicycle parking to support cycling routes throughout the subdivision; and,

    15. Details of access requirements for maintenance vehicles into the stormwater detention basins, wetlands and public open space areas where relevant.

  2. Utility service substations, kiosk sites and the like must not be located on any land identified as public open space or land to be used for any municipal purpose unless otherwise agreed by the responsible authority.


COMPLETION OF LANDSCAPE WORKS

  1. The landscaping works shown on the approved landscape plan for each stage must be carried out and completed to the satisfaction of the Responsible Authority prior to the issue of a Statement of Compliance for that stage, or any other time when agreed in writing by the Responsible Authority and suitably bonded to the satisfaction of the Responsible Authority.

  2. Prior to the issue of practical completion of landscaping works, or any other time as agreed in writing by the Responsible Authority, the following must be provided to the Responsible Authority:

    1. Building permits and structural engineering compliance where necessary;

    2. Landscaping maintenance plan including playground inspection regime and asset listing;

    3. As-built landscaping plans in PDF and GIS-ready AutoCAD (DXF) format; and

    4. An independent playground auditor’s report with evidence of rectification of any identified defects. The report must relate to all playground equipment, fitness equipment, natural play elements, soft fall areas and edging to ensure that all aspects of the playground construction meet Playground Standards AS/NZS4422 1996 and AS4685 parts 1-6 2004 and is in good working order and safe condition.

  3. Prior to Statement of Compliance being issued for any relevant stage of the subdivision, any reserve or land set aside for public open space or any tree reserve or the like must be graded, top dressed and sown to grass to the satisfaction of the Responsible Authority unless otherwise agreed in writing by the Responsible Authority and suitably bonded to the satisfaction of the Responsible Authority.

  4. Unless otherwise agreed in writing by the Responsible Authority, a maintenance bond must be submitted to the Responsible Authority at the time of application for practical completion of landscaping works.

  5. Note 1: The incomplete landscape works bond or bank guarantee must be 125 per cent of the estimated cost of incomplete landscape works; the maintenance bond or bank guarantee must be 100 per cent of the estimated cost of maintenance of landscape works for a two (2) year period.

    Note 2: A practical completion inspection is required to satisfy this condition and must be organised by the permit holder with two weeks’ notice given for onsite inspections. The incomplete landscape works bond will be returned on award of practical completion.


MAINTENANCE OF LANDSCAPING

  1. All works forming part of the endorsed landscaping plans must be maintained for a minimum period of 24 months, to the satisfaction of the Responsible Authority. The maintenance period will commence on the date of issue of the Statement of Compliance for all, or a particular stage, or a subdivision only where the landscaping works have been completed to the satisfaction of the Responsible Authority. Where the landscape works are bonded or covered by a bank guarantee, the maintenance period will commence from the time that the landscape works have been awarded Practical Completion by the Responsible Authority. During this time, any dead, diseased or damaged plants, landscaped areas and hard landscape elements are to be repaired or replaced by the permit holder and at no cost to Council. Handovers will not be accepted during the summer period between 1 December and 1 March each year.

    The landscape maintenance bond will be returned on acceptance handover.


COMMUNITY INFRASTRUCTURE CHARGE

  1. Prior to the issue of a Statement of Compliance for each stage, a community infrastructure charge of $900.00 per residential lot created must be paid in relation to any plan of subdivision which creates a residential lot.


TELECOMMUNICATIONS

  1. The owner of the land must enter into agreements with:

    1. A telecommunications network or service provider for the provision of telecommunication services to each lot shown on the endorsed plan in accordance with the provider’s requirements and relevant legislation at the time; and,

    2. A suitably qualified person for the provision of fibre ready telecommunication facilities to each lot shown on the endorsed plan in accordance with any industry specifications or any standards set by the Australian Communications and Media Authority, unless the applicant can demonstrate that the land is in an area where the National Broadband Network (NBN) will not be provided by optical fibre.

  2. Before the issue of a Statement of Compliance for any stage of the subdivision under the Subdivision Act 1988, the owner of the land must provide written confirmation from:

    1. A telecommunications network or service provider that all lots are connected to or are ready for connection to telecommunications services in accordance with the provider’s requirements and relevant legislation at the item; and,

    2. A suitably qualified person that fibre ready telecommunications facilities have been provided in accordance with any industry specifications or any standards set by the Australian Communications and Media Authority, unless the applicant can demonstrate that the land is in an area where the National Broadband Network will not be provided by optical fibre.


VICROADS

  1. The Plan of Subdivision must set aside the area of the Public Acquisition Overlay - Schedule 3 for future road widening of Forest Road South.

  2. Any buildings and works must be setback 2 metres from the Public Acquisition Overlay’s western boundary.

  3. No compensation is payable under part 5 of the Planning and Environment Act 1987 in respect of anything done under this permit.


POWERCOR

  1. The plan of subdivision submitted for certification under the Subdivision Act 1988 shall be referred to Powercor Australia Ltd in accordance with Section 8 of that Act.

  2. The applicant shall provide an electricity supply to all lots in the subdivision in accordance with Powercor’s requirements and standards, including the extension, augmentation or re-arrangement of any existing electricity supply system, as required by Powercor ( A payment to cover the cost of such work will be required). In the event that a supply is not provided the applicant shall provide a written undertaking to Powercor Australia Ltd that prospective purchasers will be so informed.

  3. The applicant shall, where buildings or other installations exist on the land to be subdivided and are connected to the electricity supply; they shall be bought into compliance with the Service and Installation Rules issued by the Victorian Electricity Supply Industry. You shall arrange compliance through a Registered Electrical Contractor.

  4. Any Buildings must comply with the clearances required by the Electricity Safety (Network Assets) Regulations.

  5. Any construction work must comply with Energy Safe Victoria’s “No Go Zone” rules.

  6. The applicant shall set aside on the plan of subdivision for the use of Powercor Australia ltd reserves and/or easements satisfactory to Powercor Australia Ltd where any electric substation (other than a pole mounted type) is required to service the subdivision.

    Alternatively, at the discretion of Powercor Australia Ltd a lease(s) of the site(s) and for easements for associated powerlines, cables and access ways shall be provided. Such a lease shall be for a period of 30 years at a nominal rental with a right to extend the lease for a further 30 years. Powercor Australia Ltd will register such leases on the title by way of a caveat prior to the registration of the plan of subdivision.

  7. The applicant shall provide easements satisfactory to Powercor Australia Ltd, here easements have not been otherwise provided, for all existing Powercor Australia Ltd electric lines on the land and for any new powerlines required to service the lots and adjoining land, save for lines located, or to be located, on public roads set out on the plan. These easements shall show on the plan an easement(s) in favour of Powercor Australia Ltd for ‘Powerline Purposes’ pursuant to Section 88 of the Electricity Industry Act 2000.

  8. The applicant shall obtain for the use of Powercor Australia Ltd any other easement external to the subdivision required to service the lots.

  9. The applicant shall adjust the position of any existing easement(s) for powerlines to accord with the position of the line(s) as determined by survey.

  10. The applicant shall obtain Powercor Australia Ltd’s approval for lot boundaries within any area affected by an easement for a powerline and for the construction of any works in such an area.

  11. The applicant shall provide to Powercor Australia Ltd, a copy of the version of the plan of subdivision submitted for certification, which shows any amendments which have been required.


TENIX

  1. The plan of subdivision submitted for certification must be referred to SP AusNet (Gas) in accordance with Section 8 of the Subdivision Act 1988.


BARWON WATER

General

  1. The owner shall create easements for Pipelines or Ancillary Purposes and or reserves in favour of Barwon Region Water Corporation on the plan of subdivision in accordance with Barwon Water’s Land Development Manual, without cost to Barwon Water, over existing and proposed water and sewerage infrastructure within the land. If further easements or reserves are required following design of water and sewerage infrastructure these must be added to the plan of subdivision prior to seeking baron Water’s consent to the issue of a statement of compliance of the subdivision.

  2. The plan of subdivision must be referred to Barwon Water in accordance with the Subdivision Act 1988 and any subsequent amendments to the plan provided to Barwon Water.

Water

  1. The provision and installation of individual water services to all lots in the subdivision in accordance with Barwon Water’s requirements and Victorian Plumbing Regulations. Note that tappings and services are not to be located under existing or proposed driveways.

  2. The payment of New Customer Contributions for each additional lot created and/or each additional metered connection for water supply within the subdivision.

  3. Reticulated water assets are required to service the proposed development.

  4. Barwon Water’s records indicate that an existing water service and meter is located on this property. A dimensioned plan showing the location of existing meters, and the location of the meter relative to the existing boundaries, and its number, is to be submitted. Private water service pipes are not permitted to cross allotment boundaries and must be plugged and abandoned at the boundaries of such allotments.

Sewer

  1. The provision of sewerage services to all lots in the subdivision in accordance with Barwon Water’s requirements and Victorian Plumbing Regulations. Individual allotment house connection drains are to be provided for and extend into each allotment.

  2. The payment of New Customer Contributions for sewer for each additional lot created and/or each additional metered connection within the subdivision.

  3. Reticulated sewer mains or a sewer main extension are required to service the proposed development.

PUBLIC TRANSPORT VICTORIA

  1. Unless otherwise agreed in writing with Public Transport Victoria, prior to certification of the plan of subdivision for the first stage, amended plans to the satisfaction of Public Transport Victoria must be submitted to and approved by the Responsible Authority. When approved, the plans will be endorsed and will then form part of the permit. The plans must be drawn to scale with dimensions and three copies must be provided. The plans must be generally in accordance with the plans submitted with the application but modified to show bus stops to be constructed:

    1. On either side of Forest Road South, adjacent to the subdivision;

    2. Containing a concrete hard stand for passengers with tactile ground surface ' indicators (based upon PTV standard drawings STD_0064, STD_0065, STD_0066 or STD_0067);

    3. With a barrier kerb for the 9.2m prior to the bus flag position (situated as per PTV standard drawings and barrier kerb built to VicRoads standard design);

    4. Containing a bus stop pole, flag and timetable case to PTV requirements (as per PTV standard drawings STD_0062 and STD_0063).

    5. Compliant with the Disability Discrimination Act — Disability Standards for Accessible Public Transport 2002;

    6. Be provided with connecting path or ramps (if required) built between the bus stop hardstand and the nearby public footpath.

  2. Prior to the issue of a Statement of Compliance for the first stage of the subdivision, all works outlined on the endorsed plans associated with the bus stops on Forest Road South must be completed to the satisfaction of Public Transport Victoria at the full cost of the permit holder.

CFA

Hydrants

  1. Operable hydrants, above or below ground must be provided to the satisfaction of CFA.

  2. The maximum distance between these hydrants and the rear of all building envelopes (or in the absence of the building envelope, the rear of all lots) must be 120m and hydrants must be no more than 200m apart.

  3. Hydrants must be identified as specified in ‘Identification of Street Hydrants for Firefighting purposes’ available under publications on the Country Fire Authority web site (www.cfa.vic.gov.au)

Roads

  1. Roads must be constructed to a standard so that they are accessible in all weather conditions and capable of accommodating a vehicle of 15 tonnes for the trafficable road width.

  2. The average grade must be no more than 1 in 7 (14.4%) (8.1 degrees) with a maximum of no more than 1 in 5 (20%) (11.3 degrees) for no more than 50 meters. Dips must have no more than a 1 in 8 (12%) (7.1 degree) entry and exit angle.

  3. Roads must have a minimum trafficable width of:

    1. 5.5m if parking is prohibited on one or both sides of the road.

    2. 7.3m where parking is allowable on both sides of the road.

EXPIRY

  1. This permit will expire if one of the following circumstances applies:

    1. The first stage of the plan of subdivision has not been certified within two years of the date of this permit.

    2. All stages of the plan of subdivision have not been certified within five years of the date of this permit.

    3. A statement of compliance is not issued within five years of the date of certification of a particular stage of subdivision.

    The Responsible Authority may extend the periods referred to if a request is made in writing before the permit expires or within six (6) months afterwards.

Notes:

  1. The design and construction of civil infrastructure to become council assets must be approved and supervised by council. A fee of 3.25% of the cost of the works is to be paid to council for the checking and supervision of these works.

  2. A maintenance bond of 5% of the cost of the works is to be paid to council and will be returned after successful completion of a 12 month maintenance period.

  3. The developer is to apply to Barwon Water for details relating to costs and conditions required for the provision of water supply and sewerage services to the subdivision. It would be appreciated if all communications between the developer/agent and Barwon Water quote Barwon Water reference number L010609.

  4. All buildings and works must be in accordance with Cultural Heritage Plan #12670 approved on the 14 April 2014 by the Wathaurung Aboriginal Corporation.


Cr Ellis declared an Indirect Interest by a Conflicting Duty in Agenda Item 6 – C274 HO1600 Heritage Review, Batman Park, Indented Head in that he is a Board Member of the Bellarine Bayside Foreshore Committee, and left the meeting room prior to discussion at 8:02pm.


[Back to Top]

6. C274 HO1600 Heritage Review, Batman Park Indented Head

Portfolio:

Planning – Cr Heagney

Source:

Planning and Tourism - Strategic Implementation

General Manager:

Peter Bettes

Index Reference:

Council Reports 2015
Application C274


Purpose

This report acknowledges submissions to Amendment C274 and recommends adoption of the Amendment, including changes to accommodate issues raised in submissions.


Summary

The amendment will:

Cr Heagney moved, Cr Harwood seconded -

That Council:

  1. Adopt the Batman Park and Boat Sheds, The Esplanade, Indented Head Heritage Review, August 2013, as exhibited, with the changes identified in Appendix 4 to this report;

  2. Adopt the Batman Park Indented Head Incorporated Plan, February 2015, in the form contained at Appendix 2 to this report;

  3. Adopt Amendment C274 in the form as outlined in Appendix 1 (A) – (E) to this report; and

  4. Submit the adopted Amendment together with the prescribed information to the Minister for Planning requesting approval.

Carried.


Background

As part of the 2012-2013 budget process a Councillor initiated allocation of $10,000 was set aside to undertake a review of the heritage overlays at Batman Park and adjoining public land at Indented Head.

On the basis of this allocation, in 2013 Council engaged Dr David Rowe to undertake a review of the heritage overlays which apply to parts of Batman Park and some of the boat sheds within the park.

The report is titled Batman Park and Boat Sheds, The Esplanade, Indented Head, Heritage Review, August 2013.

As part of the review process Council consulted with the following groups and individuals:

Amendment C274 seeks to implement the findings of the heritage review.

The Report was modified in a manner consistent with the submissions received prior to the Exhibition of the Amendment.

A table describing the changes sought is contained at Appendix 4.


Discussion

Authorisation to exhibit the Amendment was sought under delegation by Council officers – i.e. without a report to Council – and, following receipt of Authorisation from the Minister for Planning, the Amendment was exhibited from 6th February 2014 to 18th March 2014. Notice of the amendment was given to owners and occupiers of properties on The Esplanade, opposite the land affected by the Amendment, to relevant authorities and Ministers in accordance with the requirements of the Planning and Environment Act 1987.

Submissions were received from the following six (6) public Authorities / organisations:

These submissions are included as Appendix 3(A) – (G).

Consistent with the extensive community consultation which occurred prior to exhibition, no submissions were received from members of the public.

Responses fall into two categories.

  1. No objection responses, received from:

  2. Submissions seeking detailed changes to the controls proposed by the amendment. Received from:

Both Bellarine Bayside and DEPI were concerned that the HO covers a larger area and triggers the need for permits for a broad range of buildings and works – many of which aren’t related to heritage.

The Wadawurrung were concerned that insufficient recognition was given to Aboriginal heritage and to its protection under the Heritage Overlay.

Council officers have met with these three parties and an incorporated plan under the Heritage Overlay has been prepared which addresses the matters raised to the satisfaction of each organisation.

In particular, the additional exemptions allowed under the Incorporated Plan will facilitate Bellarine Bayside to go about their normal management activities without a requirement to apply for planning permits unless the heritage elements identified in the Report and the Incorporated plan are impacted by the proposed works.

As all of the objecting submitters have provided advice in writing that their concerns have been addressed, Council may adopt the Amendment without the need for a Planning Panel to be appointed to consider submissions.

Environmental Implications

The changes to the planning scheme will not have any adverse environmental implications.


Financial Implications

The changes to the planning scheme will have no adverse financial implications for Council.


Policy/Legal/Statutory Implications

The amendment is considered to be consistent with State and Local planning policies as set out in the Explanatory Report, which forms part of the amendment documentation.


Alignment to City Plan

The report and recommendations are consistent with the ‘Built and Natural Environment and Community Wellbeing’ elements of City Plan.
Officer Direct or Indirect Interest
No Council officers involved in the preparation of this report have a direct or indirect interest, in accordance with Section 80(c) of the Local Government Act, to the matters to which this amendment relates.


Risk Assessment

There are no risks to Council associated with the adoption of the revised heritage controls and the inclusion of the Batman Park and Boat Sheds, The Esplanade, Indented Head, Heritage Review, August 2013 as an incorporated document in the planning scheme or with the adoption of the planning scheme amendment.


Social Considerations

No adverse impacts on the community have been identified as arising from the adoption of this amendment.


Human Rights Charter

The recommendations raised in this report recognise and respect those groups connected to Batman Park and environs, including both earlier generations of post contact settlers and pre and post contact activity by the traditional owners of the land.


Consultation and Communication

Amendment C274 has been the subject of community consultation as part of the heritage review, in addition to the formal exhibition process, as a result of which suggestions contained in supporting submissions have been incorporated into the amendment and matters of concern contained in three objecting submissions have been addressed in the revised amendment documentation to be adopted to the satisfaction of the submitters.


Appendix 1 Instruction Sheet and Ordinance and Map Changes

1A Instruction Sheet

Instruction Sheet

1B Amendment Maps

Amendment Map - Delete Heritage Overlay 1601
Amendment Map - Delete Heritage Overlay 1600
Amendment Map - Delete Heritage Overlay 262
Amendment Map - Heritage Overlay 1963

1C – Heritage Overlay Schedule – Changes

Heritage Overlay Schedule – Schedule - page 1 of 2
Heritage Overlay Schedule – Schedule - page 2 of 2

1D Schedule to Clause 61.03

Schedule to Clause 61.03 - page 1 of 3
Schedule to Clause 61.03 - page 2 of 3
Schedule to Clause 61.03 - page 3 of 3

1E Schedule to Clause 81.03

Schedule to Clause 81.03 - page 1 of 2
Schedule to Clause 81.03 - page 2 of 2

Appendix 2 Batman Park Indented Head Incorporated Plan, February 2015

Batman Park Indented Head Incorporated Plan, February 2015 - page 1 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 2 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 3 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 4 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 5 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 6 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 7 of 8
Batman Park Indented Head Incorporated Plan, February 2015 - page 8 of 8

Appendix 3 Submissions to Exhibited Amendment

3A Country Fire Authority

Country Fire Authority submission

3B Corangamite Catchment Management Authority

Corangamite Catchment Management Authority submission - page 1 of 2
Corangamite Catchment Management Authority submission - page 2 of 2

3C Environment Protection Authority

Environment Protection Authority submission

3D VicRoads

VicRoads submission

3E Bellarine Bayside

Bellarine Bayside submission - page 1 of 4 (St Quentin Consulting Pty Ltd on behalf of Bellarine Bayside Foreshore Committee of Management Incorporated)
Bellarine Bayside submission - page 2 of 4 (St Quentin Consulting Pty Ltd on behalf of Bellarine Bayside Foreshore Committee of Management Incorporated)
Bellarine Bayside submission - page 3 of 4 (St Quentin Consulting Pty Ltd on behalf of Bellarine Bayside Foreshore Committee of Management Incorporated)
Bellarine Bayside submission - page 4 of 4 (St Quentin Consulting Pty Ltd on behalf of Bellarine Bayside Foreshore Committee of Management Incorporated)
Bellarine Bayside Coastal Management submission

3F Department of Environment, Land, Water and Planning

Department of Environment, Land, Water and Planning submission - page 1 of 4
Department of Environment, Land, Water and Planning submission - page 2 of 4
Department of Environment, Land, Water and Planning submission - page 2 of 4
Indented Head foreshore map - page 4 of 4
Email received from Department of Environment, Land, Water and Planning

3G Wadawurrung

Email received from Wadawurrung
Aboriginal Affairs Victoria - Map report
Submission - Wathaurung Aboriginal Corporation
Email from John Young - Wadawurrung

Appendix 4 Pre-Exhibition Changes to Batman Park Heritage Report, August 2013

Batman Park Heritage Review: Table of submissions received 2 August 2013

Cr Ellis re-entered the meeting room at 8:03pm


[Back to Top]

7. Private Sporting Infrastructure Capital Co-Contribution Policy

Portfolio:

Sport and Recreation – Cr Irvine

Source:

Projects, Recreation and Central Geelong

Act/General Manager:

Jenny McMahon

Index Reference:

Subject: Leisure and Recreation Facilities / Recreation Facility Issues


Purpose

To seek endorsement for a Private Sporting Infrastructure Capital Co-contribution Policy for capital works on sporting infrastructure not on Council owned or managed land.


Summary

Cr Harwood moved, Cr Irvine seconded -

That Council endorse the Private Sporting Infrastructure Capital Co-contribution Policy (Appendix 1), with the following amendments:

Carried.


Background

The City of Greater Geelong provides a vast array of facilities for community sport and recreation. Many of these facilities play a dual purpose in providing sport and recreation opportunities for surrounding communities and providing open space which the community is free to use outside of formal sports bookings. Council subsidises fees paid for facilities by sporting clubs to ensure that community sport is accessible and to encourage active, healthy communities through the provision of sport and passive open space.

Council has not generally provided subsidies for capital works projects on sporting infrastructure not on Council owned or managed land due to the significant financial cost that would be incurred and limitations of ongoing community access.

Sport and recreation facilities that have been established on private or non-Council managed land are generally the result of a local sporting club/organisation having a desire to establish a facility for their specific purpose. The sporting club/organisation has then subsequently bought or have been gifted a parcel of land to establish a facility. Land ownership has generally (but not exclusively) been in non-residential areas (ie rural, industrial).

At Council’s Ordinary meeting held 28 October 2014 a ‘Privately Managed Sport and Recreation Facilities’ report was presented to determine Council’s position on providing financial assistance to privately owned and/or managed sport and recreation facilities. Council resolved to:

  1. continue to invest in the capital renewal and prioritise the maintenance of Council owned and/or managed sport and recreation facilities;

  2. consider requests from privately owned/managed not for profit sport and recreation clubs and organisations for contribution to capital works that demonstrate community benefit;

  3. direct officers to develop a co-contribution policy that sets out Council’s criteria for contributing funds for capital projects on properties and facilities privately owned/managed by not for profit sport and recreation clubs and organisations whereby Council may contribute an amount up to, or equal to funds contributed by the organisation and/or State and Federal Government;

  4. private clubs that are the recipient of Council funds agree to appropriate organisational wind-up clauses or contractual arrangements to protect Councils investment; and

  5. present a policy for adoption by February 2015.

This report recommends a Private Sporting Infrastructure Capital Co-contribution Policy that provides Council with a clear direction as to the level of contribution it may provide to eligible sporting infrastructure projects that are approved through Council’s annual budget process. Council regularly receives requests from owner/operators of sport and recreation facilities not on Council owned or managed land regarding opportunities for sporting infrastructure capital works support that may include:

For the purposes of this report the term private facilities refers to sport and recreation facilities not on Council owned or managed land that are:


Discussion

Sport and recreation facilities within the City of Greater Geelong provide a wide range of participation opportunities for residents and visitors to the municipality. While the majority of sport and recreation facilities are owned and/or managed by Council, a small number of facilities are privately owned and/or managed by sporting clubs or other management authorities. From time to time, funding for minor capital works and community grants have been made available to clubs operating within private facilities, however no ongoing financial commitments toward capital works have been provided by Council.

The Private Sporting Infrastructure Capital Co-contribution Policy will provide clubs and organisations on privately owned or managed land with clear funding mix guidelines and allow them to plan effectively to implement their project proposal.

The policy encourages a variety of contribution sources so the cost for an eligible sporting infrastructure project is shared and not seen as the sole responsibility of one organisation. The policy also acknowledges the importance of the local contribution from clubs and organisations both in terms of cash, voluntary labour and donated materials.

Maintenance related projects will not be considered.

Facility Categories and Land Ownership/Management

While the majority of sport and recreation facilities within the municipality are located on Council owned and/or managed land, there are a range of facility ownership and management models across the municipality not on Council owned or managed land. The following assets are considered eligible:

The following assets are not considered eligible:

Based on the information above, the asset base of private facilities within the municipality that may be considered for capital works support are:

Sport

Facility Type

Amount

Description

Soccer

Pitches

7

7 x turf

Pavilions

4

3 x large, 1 x medium

Tennis

Courts

31


13 x lawn, 12 x en tout cas, 6 x hard-court, 1 x synthetic grass

Pavilions

2

1 x large, 1 x medium

AFL

Ovals

1

1 x turf

Pavilions

1

1 x medium

Netball

Courts

2

2 x hard courts

Lawn Bowls

Greens

18

8 x turf, 10 x synthetic grass

Pavilions

8

6 x large, 2 x medium


Benchmarking of Local Government Authorities

Benchmarking of current practices regarding local government support of private facilities was undertaken with Mitchell Shire, City of Whittlesea, City of Casey, Surfcoast Shire, Cardinia Shire, Colac Otway Shire, Hume City Council, City of Greater Bendigo, Warrnambool City Council and the City of Wodonga. The outcomes of the benchmarking exercise produced a clear position across all municipalities:

Key Rationale

The following information outlines the key rationale considered in developing the policy:

  1. Contribution to the Open Space Network

    If Council contribute funds for capital works projects on privately owned and/or managed land, the expectation would be that these facilities are made available for community access outside of scheduled training and competition. This would have a positive impact on the provision of open space and access to reserves for the wider community.

  2. Tenancy and Public Access

    Public access to privately owned sport and recreation facilities is at the discretion of the owner/operator and resident sporting clubs are not required to enter into tenancy agreements with Council for the seasonal use of facilities. While priority will be given to funding applications which demonstrate a commitment to facilities being readily available for community use it should be noted that ongoing access can not be guaranteed.

  3. Facility Ownership

    Private facilities may be sold by the owner/s at any time, with Council having limited control over the sale of a privately owned or managed asset. The risk of contributing significant resources to a private facility that could be sold by it’s owner/s at any time is generally seen as prohibitive to contributing capital improvement resources.

    The policy recommends that clubs and organisations that are successful in securing Council support take full responsibility for the ongoing maintenance of any capital project improvements and enter into a formal Project Funding Agreement that outlines commitments of all parties to the project and agree to organisational wind-up clauses or contractual arrangements to protect Council’s investment for the term of the asset life.

    Community access to private facilities raises issues related to public liability and Council’s inability to ultimately control facilities that are being provided by the owner/operator. The public liability risk is considered minimal as the policy does not include maintenance requests and applies to capital works projects only.

  4. Capital Cost to Council

    The financial cost of capital works is generally seen as the most significant obstacle to Council committing to ongoing capital support for privately owned/managed facilities.

    The following estimated capital costs relate to the private asset categories considered in the policy:

    Sport

    Facility

    Components

    Capital

    Lifespan

    Soccer

    Turf field

    One hectare turf, sportlights, irrigation, goals, player shelters and fencing (410 metres).

    $450,000 - $550,000

    15 - 25 years

    Tennis

    Court enclosure

    Two-court enclosure with sportslights, acrylic hard-court surface, nets, posts, fencing and one shelter.

    $117,000 - $143,000

    15 - 25 years

    AFL

    Oval

    1.5 hectare turf, sportslights, irrigation, goals, player shelters and fencing.

    $512,000 - $625,000

    15 - 25 years

    Netball

    Court

    Two-court enclosure with sportlights, acrylic hard-court surface, goals, fencing and one shelter.

    $124,000 - $151,000

    15 - 25 years

    Lawn Bowls

    Green Replacement

    Single green enclosure with four sportslights, one synthetic surface, one shelter and fencing (170m)

    $130,000 - $158,000

    10 - 15 years

    All

    Pavilion (Small)

    250 square metres

    $750,000

    35 - 50 years

    Pavilion (Medium)

    500 square metres

    $1,500,000

    35 - 50 years

    Pavilion (Large)

    1000 square metres

    $3,000,000

    35 - 50 years

    All

    Miscellaneous

    2000 square metres of car park, one water tank, one storage shed.

    $126,000 - $154,000

    25 - 35 years


    The capital works cost on sporting infrastructure not on Council owned or managed land is based on the following assumptions:

    The financial implication of Council assuming entire responsibility for capital works on sporting infrastructure not on Council owned or managed land is projected at:

    It should be noted that not all private facilities will be applying for funding in any given year and submissions will be evaluated via Council’s annual budgetary process and ranked according to urgency. Council contributions to successful community concept projects will be subject to approval through Council’s annual budget process.

Assessment Criteria

Projects are required to demonstrate a strong community benefit and is assessed against the following criteria:

Council’s Recreation and Open Space Unit will rank submissions as mandatory, critical, high, medium or low priority in-line with Council’s annual budget process.

The community value of a project that is not on Council owned or managed land will also be considered in-line with the Department of Transport, Planning and Local Infrastructure‘s Community Facility Funding criteria that considers to what extent the project:

Contribution Framework

The recommended contribution framework for capital works on sporting infrastructure not on Council owned or managed land is:

Council to contribute up to one-third (1/3) of the total project cost, with the club/organisation to contribute a minimum two-thirds (2/3) of the total project cost including any other funding sources.

Considerations


Environmental Implications

There are no environmental implications relating to this report.


Financial Implications

Council contributions to capital works projects will be subject to approval through Council’s annual budget process.


Policy/Legal/Statutory Implications

The following Council policies have implications for the recommendations of this report:

Council’s Open Space Strategy is currently being reviewed, with gaps in open space provision to be determined as part of the planning process. A preliminary review suggests that private facilities provide limited value in the provision of publicly accessible open space.


Alignment to City Plan

This report is aligned to the Community Well-Being objective of City Plan. The provision of sport and recreation facilities promotes healthy lifestyle through physical activity.

Council prioritises the development of sport and recreation facilities within Council owned and managed reserves, however investing in private facility infrastructure improvements will also contribute to providing community well-being outcomes, including physical activity, social connectedness, mental health, inclusion and accessibility.


Officer Direct or Indirect Interest

No persons engaged in the writing of this report have a direct or indirect interest in the matters considered within the report.


Risk Assessment

Should Council agree to contribute funds toward private sport and recreation facilities within the municipality, a number of risks would require consideration:


Social Considerations

Sport and recreation plays a key role in the health of our community. Whilst the physical health of the community is the most apparent benefit, sport and recreation promotes increased mental health, social connection and community leadership. Sporting clubs at private sport and recreation facilities provide similar community benefits as those on Council-owned land, but Council has limited ability to influence club activities through tenancy agreements and licensing.


Human Rights Charter

This report has no impact on compliance with the Human Rights Charter.


Consultation and Communication

No formal consultation process has been undertaken relating to this report. From time to time, Council receives requests from owner/operator(s) of sport and recreation facilities not on Council owned or managed land regarding opportunities for sporting infrastructure capital works support.

The current position is that Council does not provide capital works or maintenance support for privately owned or managed sport and recreation facilities.


[Back to Top]

8. Revised Terms of Reference for Special Committees

Portfolio:

Governance - Cr Lyons (Mayor)

Source:

Strategy and Performance - Financial Services

General Manager:

Dean Frost

Index Reference:

Council Reports 2015


Purpose

To update the Terms of Reference for Special Committees of Council (as defined by Section 86 of the Local Government Act 1989) to reflect changes to the City of Greater Geelong Act 1993 (The Act).


Summary

Cr Heagney moved, Cr Nelson seconded -

That Council endorses the updated Terms of Reference for Special Committees for:

  1. Bellarine Multi Arts Facility (Potato Shed)

  2. Central Geelong Task Force Special Committee

  3. Central Geelong Marketing Committee (no Mayoral appointment to Chair 2015)

  4. Development Hearing Panel

  5. Geelong Major Events

  6. Performance Review – Chief Executive

  7. Planning Committee

Carried.


Background

This report updates Council’s Special Committee Terms of Reference to ensure compliance with Section 11E of the City of Greater Geelong Act 1993 (The Act).


Discussion

The Act gives the Mayor the power to appoint Councillors to certain committees.

The Mayor’s power to appoint Councillors under section 11E (1) (b) is limited to their appointment:

The Mayor may also choose not to appoint a Chair to a special committee and may at any time remove a member from the Chair position.

Section 86 of the Local Government Act 1989 provides for Council to appoint any additional Councillor(s).

Existing Terms of Reference have been reviewed and updated to reflect changes to the Act, for the following special committees:


Environmental Implications

There are no environmental implications associated with the contents of this report.


Financial Implications

Funding arrangements (where in place) are provided within Council’s budget parameters. There are no specific implications in updating the Terms of Reference for Special Committees.


Policy/Legal/Statutory Implications

Terms of Reference have been updated to ensure compliance with the Act.

Special Committee (s86) Meetings are open to the public, except where matters of a confidential nature, as prescribed by the Act, are to be considered. These committees may be delegated various responsibilities by the Council, including the expenditure of monies and entering into contracts.


Alignment to City Plan

Special Committees align with the City Plan objectives of Community Wellbeing, Growing the Economy, Sustainable and Built Environment, and also How We Do Business.


Officer Direct or Indirect Interest

No officer involved in the preparation of this report had a direct or indirect interest.


Risk Assessment

By adopting and reviewing the Terms of Reference of the special committees any perceived risk is minimised and ensures adherence to regulatory requirements. The operations of the committees in this report are designed to offer transparency and to ensure good governance procedures are in place.


Social Considerations

Appointments to special committees allow the Chair and committee members to gain expertise in a variety of social considerations in a forum which is readily accessible and open to the community.


Human Rights Charter

No human rights are impacted by the contents of this report. Committees will generally align with the principles of the Human Rights Charter.


Consultation and Communication

Updated terms of reference and minutes of special committees are available on Council’s website or upon request. All relevant areas of Council were consulted in updating their Terms of Reference.

Cr Nelson declared an Indirect Interest in Agenda Item 9 – Highton Drainage/Flood Study as he owns a property in the flood overlay zone and left the meeting room prior to discussion at 8:12pm.

[Back to Top]

9. Highton Drainage/Flood Study

Portfolio:

Infrastructure, Parks and Gardens – Cr Ellis

Source:

City Services – Engineering Services

General Manager:

William Tieppo

Index Reference:

Flood/Drainage Management – Flood Mitigation


Purpose

This report seeks Council adoption of the Final Report of the Highton Drainage/Flood Study, following the public consultation undertaken in July and August 2014.


Summary

Cr Ellis moved, Cr Fisher seconded -

That Council:

  1. note the report for the Mitigation Options as outlined in the Highton Drainage/Flood Study Final Report;

  2. endorse the Final Report and Flood Extent Map produced by the Highton Drainage/Flood Study as contained in Appendix 1 (Executive Summary) and Appendix 2 (Flood Extent Map);

  3. designate that land identified within the Highton Drainage/Flood Study and shown in Appendix 2 (Flood Extent Map) as likely to be inundated by a 100 year Average Recurrence Interval flood event, as liable to flooding pursuant to Regulation 802(2) of the Building Regulations 2006; and

  4. commence the amendment process to incorporate the relevant flood zones and overlays into the Greater Geelong Planning Scheme, based on the flood mapping produced by the Highton Drainage/Flood Study.

Carried.


Background

The Highton catchment that was studied is known as the Kardinia Creek catchment, named after the creek that has now been piped. This catchment covers a significant urbanised area within the suburbs of Highton, Wandana Heights and Belmont (refer to Attachment 1 for Study Area). The catchment drains to the Barwon River via an outfall located west of Shannon Avenue.

In total the Kardinia Creek catchment has an area of approximately 1,050 ha, with 60% of this area urbanised. The rural portion of the catchment is located upstream of the urbanised portion, with the Geelong Ring Road generally comprising the boundary between the urban and rural portions.

The Kardinia Creek catchment has some serious and frequent drainage-related or ‘stormwater’ flooding. The severity of flooding (significant risk or hazard) within the catchment is reflective of the size, topography, development density and age (up to 60 years) of the contributing catchment, i.e. significant developed catchment with pre-1980 drainage systems. A pre-1980 drainage system typically has underground drainage with limited capacity (lower order minor storms) and a lack of clear overland flow paths for surcharge or excess flows.

Given the scale and complexity of the flooding within the Kardinia Creek catchment, specialist consulting engineers BMT WBM Pty Ltd were engaged to undertake a detailed drainage/flood study.

The Draft Final Report of the Highton Drainage/Flood Study was placed on public exhibition for 4 weeks during July and August 2014. Forty six written submissions and 66 verbal submissions/enquiries were received. The major issues of concern and the City’s responses are listed within Attachment 2. Following the consideration of submissions, the Final Report was prepared. A copy of the executive summary of the Final Report of the Highton Drainage/Flood Study is appended as Appendix 1.


Discussion

The drainage/flood study or flood management plan consists of the analysis and production of flood maps, identification and modelling of flood mitigation options, preparation of cost estimates, feasibility analysis, identification of preferred options and development of a strategy.

Computer modelling was used to assess the extent and depth of flooding over the flood mapping area for both the existing conditions and for each of the mitigation options under consideration.

The study estimated that at least 35 properties would suffer from internal flooding of habitable buildings in the event of a 100-year Average Recurrence Interval flood under existing conditions.

As flooding events tend to occur on a random basis, the cost of flood damage is generally expressed as an average annual amount that can be expected to be incurred in the long term. The annualised cost of flood damage for existing conditions within the Highton catchment is estimated at $389,000 pa. This annualised cost was estimated using the ANUFLOOD and Rapid Appraisal Method, which take account of potential tangible losses such as damage to infrastructure, buildings and contents, loss of production, etc.

In addition to the flood damage assessment, the flood hazard or risk to public safety associated with particular events was quantified. Flood hazard is generally measured using Melbourne Water’s criteria for ‘safe’ flood depth and velocity, with the safety of children as the primary concern. Some of the flooding within the catchment was found to be hazardous or unsafe.

The study proposed the following three major flood mitigation scheme options for consideration:

An additional ‘do nothing’ (structural) scheme was considered as Scheme 4.

The study found that Scheme 1 with capital cost of $6.69 million would alleviate internal above floor flooding of at least 2 of the 35 affected properties for the 100 year Average Recurrence Interval flood event, i.e. $3.35 million capital cost per protected property. The benefit to some of the remaining flood affected properties includes a varying reduction in flood levels and duration of flooding. The Benefit Cost Ratio for this option was estimated as 0.01.

The Benefit Cost Ratio (BCR) is a measure of the benefit of implementing a project, in consideration of direct and tangible costs.

A Benefit Cost Ratio greater than one indicates that the total economic benefit received over the lifetime of the project exceeds the cost of undertaking the works. A Benefit Cost Ratio less than one indicates that the costs exceed the benefits over the lifetime of the project.

Scheme 2 with capital cost of $21.10 million would alleviate internal flooding of at least 5 of the 35 affected properties for the 100 year Average Recurrence Interval flood event, i.e. $4.22 million capital cost per protected property. The benefit to the remaining flood affected properties again includes a varying reduction in flood levels and duration of flooding. The Benefit Cost Ratio for this option was estimated as 0.01.

Scheme 3 with capital cost of $27.25 million would alleviate internal flooding of at least 6 of the 35 affected properties for the 100 year Average Recurrence Interval flood event, i.e. $4.54 million capital cost per protected property. The benefit to the remaining flood affected properties again includes a varying reduction in flood levels and duration of flooding. The Benefit Cost Ratio for this option was estimated as 0.01.

Following an assessment of economic, environmental, social, feasibility and performance factors, Scheme 4 (‘do nothing scheme) is considered to be the preferred mitigation option, in conjunction with an education and awareness program, development controls and further investigation into property-specific measures to manage flood risk. The other potential schemes (structural) were found to have very low BCR’s with high capital costs per floor saved; in the order of $4 million in capital cost. This reflects the high cost of ‘retrofitting’ major drainage works into an established urban area.

The study was deliberately limited to an examination of improvements to the drainage system and broad scale improvements to reduce the extent and public safety risk of flooding within the affected areas. It did not provide a detailed examination of property specific measures such as flood proofing. These are options that may be considered further, as to date the City has only investigated provision of community benefit infrastructure to deal with the problems on a catchment-wide basis.
The study analysed flood behaviour and produced flood mapping that needs to be incorporated into the City’s flood-prone areas information system in accordance with the City’s statutory obligations under Regulation 802 of the Victorian Building Regulations 2006. Council’s designation of the new flood mapping is requested in this report to Council following the public exhibition and subsequent consideration of submissions. Designation enables control of minimum floor levels via building permits and disclosure of flood status of flood affected properties within Land Information Certificates and other statutory information certificates. A planning scheme amendment to create flood overlays normally follows the designation of flood mapping by Council.

The overall flood management strategy recommended in the Highton Drainage/Flood Study comprises the following:


Environmental Implications

The designation of an area as being liable to flooding does not result in any significant adverse environmental impacts.

The proposed flood management strategy for the Highton catchment recommends that best practice environmental management for stormwater runoff be encouraged as part of development and subdivision applications in order to reduce runoff and improve water quality, where not a statutory requirement.


Financial Implications

The overall flood management strategy recommended in the Highton Drainage/Flood Study comprises further investigatory work and non-structural measures, which in the main are covered by departmental operating budgets. Project specific funding may need to be sought to enable flood zones/overlays to be prepared and implemented within the Greater Geelong Planning Scheme.


Policy/Legal/Statutory Implications

The City has various statutory responsibilities for drainage management and flood management as set out in the Local Government Act 1989, Local Government Regulations 1990, Planning and Environment Act 1987, Building Regulations 2006, Water Act 1989, Subdivision Act 1988 and Emergency Management Act 1986. The study complies with these statutory obligations.

The study is also consistent with the Victoria Flood Management Strategy and the COGG Flood Management Plan.

The flood data produced by the studies will assist the City in meeting its statutory obligations with regard to flood data within the catchment. Regulation 802(2) of the Victorian Building Regulations 2006 provides Council with the powers to ‘designate’ land liable to flooding. Regulation 802(3) provides that consent must be obtained from Council for an application to build on land liable to flooding.

Section 229 of the Local Government Act and Regulation 2.10 of the Victorian Building Regulations provide for the issue of information certificates containing prescribed information, including the flood status of properties.

The flood data will also assist in improving the quality of the flood risk assessment within the Municipal Emergency Management Plan.

The proposed flood management strategy has the overall objective of addressing flooding problems resulting from inadequacies in the Council’s drainage system within the Highton catchment and enabling Council to meet its obligations in tort to extend its duty of care to the community. The legal implications of not providing appropriate drainage infrastructure or flood management strategies, and not implementing appropriate development controls, are mainly related to liability for subsequent flood damages.

The flood management strategy recommended in the final report is also considered to be consistent with any other relevant Council policies.


Alignment to City Plan

The Highton Drainage/Flood Study aligns with City Plan, mainly within the strategic directions of Sustainable Built and Natural Environment (drainage and flood management strategies and plans) and Community Wellbeing (emergency response).


Officer Direct or Indirect Interest

There are no officer direct or indirect interests with respect to this report.


Risk Assessment

Failure to manage its drainage responsibilities in a reasonable manner and to provide reasonable main drainage infrastructure or flood management strategies, all circumstances considered, may expose the City to litigation for the cost of resultant flood damages. It may be possible to establish the City’s liability if a flooding problem has occurred over a significant period of time, and the City has been aware of the problem and not taken ‘reasonable’ measures, given all the circumstances, to remedy the problem. In the case of flooding problems within the Highton catchment, the City could be vulnerable if the proposed flood management strategy was ignored and no action planned, given the long history of flooding.

Council also has a significant risk exposure through its statutory obligations under the Victorian Building Regulations to:

  1. designate land as liable to flooding where it reasonably knows it to be prone to flooding;

  2. specify minimum floor levels in consultation with the relevant floodplain management authority, the Corangamite Catchment Management Authority; and

  3. refuse consent to building applications where there is likely to be a danger to life, health or safety due to flooding.

This drainage/flood study is a key step toward minimising Council’s exposure to risks within the Highton catchment.


Social Considerations

The frequency and duration of flooding in the Highton catchment has an adverse social impact on business owners, employees, customers, visitors and residents. The drainage/flood study has considered social factors in the identification and assessment of mitigation options.

With regard to the designation of flood mapping, Council has a responsibility to the community to provide the best possible information on areas that are flood-prone. Providing flood-prone areas information is generally stating the fact relating to a natural event. Such information is also important in managing response and recovery operations during flooding emergencies.


Human Rights Charter

No human rights are adversely affected by the contents of this report.


Consultation and Communication

The Draft Final Report of the Highton Drainage / Flood Study was placed on public exhibition with an invitation for submissions. The general public was advised of the exhibition via a public notice, and owners of properties affected by the 100 year Average Recurrence Interval flood event within the study area – approximately 2300 properties - received individual letters with explanatory fact sheets.

Forty six written submissions and 66 verbal submissions/enquiries were received. Each written submission was provided with a written response. Verbal submissions/enquiries were answered by phone or face-to-face. The major issues of concern and the City’s responses are listed within Attachment 2.

This consultation is not a substitute for the future and formal planning scheme amendment to incorporate the relevant flood zone/overlay into the Greater Geelong Planning Scheme, where again the community would be able to make submissions.

An education and awareness program is proposed to inform landowners how to minimise the magnitude of damage in a flood event.


Attachment 1

Study area and flood mapping limit

Attachment 2

PUBLIC SUBMISSIONS AND RESPONSES

Forty six written submission and 66 verbal submissions or enquiries were received. Some of the submitters acknowledged that their properties or roads had experienced flooding in the past in a manner consistent with the Study’s flood-mapping.

The major issues of concern raised by owners of affected properties are listed below with the relevant responses:

  1. How can my property be considered subject to flooding when it has never flooded (e.g. November 1995 flood event)?

    Response:

    It cannot be assumed that flooding has not previously or will not occur at any given property, on the basis that there are no records of flooding or flooding to the extent identified by the mapping of the 1 in 100 year or 100 year Average Recurrence Interval (ARI) overland flows.

    There is no evidence that the 1 in 100 year or 100 year ARI flood event for the catchment or sub-catchments studied has occurred within living memory. When reliable rainfall figures from a suitably located pluviograph have been available, proper analysis has indicated that actual storms were less than the critical event for 1 in 100 year flooding within the catchment or sub-catchments.

    Flooding of the Barwon River in November 1995 was due to riverine flooding rather than stormwater or drainage related flooding due to runoff from local catchment exceeding capacity of drainage systems.

  2. Where do the flood waters affecting my property come from?

    Response:

    In general the flood water consists of stormwater runoff from higher land within the sub-catchment upstream of your property. Flood water is the portion of runoff that can not be accommodated within the drainage system due to lack of capacity, i.e. runoff flow from upstream that exceeds the capacity of the drainage system. Easement and property drainage systems are not designed to capture and convey 100 year ARI runoff.

  3. How can my property flood when it is “on top of a hill”?

    Response:

    In all such cases, a check of topography and existing drainage systems has confirmed that the properties in question are located on the side of a hill with a large enough upstream sub-catchment and substandard drainage systems (property, easement and street), allowing surface flows to be generated within private property. Even modern property or easement drainage systems are not designed to capture and convey 100 year ARI runoff.

  4. I don’t consider the sheet flow of stormwater (on the surface) within my property to be ‘flooding’.

    Response:

    This type of inundation is considered to be flooding within the relevant best practice guidelines, strategies and legislation.

  5. I don’t believe the flood mapping is accurate.

    Response:

    The flood mapping is based on industry best practice computer modelling techniques, which have been carried out by reputable specialist consulting engineers. The modelling outcomes were also validated against available records of real time flood events. The flood mapping at the location in question is considered to be credible. (A significant number of locations under question were sampled and analysed in detail using alternative best practice methods).

  6. Why is my property considered to be liable to flooding when the neighbouring property is not?

    Response:

    The difference in flood status is normally due to the hydrological and hydraulic routing of overland flows across the terrain and the location of the relevant properties within the terrain relative to the overland flows. The “flood-free” properties tend to have a higher elevation. A decision was also made to clip shallow flood depths from the initial flood mapping in order to have flood extents that equated to a real flood risk or material flood damages. This has removed the flood extent from some lots.

  7. Are flood mitigation works proposed?

    Response:

    The drainage/flood study found that major drainage works could not be justified, and recommended further investigation into the feasibility of localised flood mitigation measures, such as lifting footpaths and/or underground drainage augmentation, in order to reduce the flood risk for properties that have been the subject of previous drainage/flooding requests for service that have identified capacity deficiencies rather than blockages. These investigations would be undertaken in accordance with the priority ranking established by the City's prioritisation method for drainage investigation/design work.

  8. Will my rates increase as a result of the study’s recommendations?

    Response:

    The Study does not propose major drainage works. (In recent years the Council has fully funded major drainage works).

  9. Shouldn’t the City fix up the drainage system rather than spend money on study?

    Response:

    The limited expenditure on the Study would have little or no beneficial impact if diverted to improving council drainage systems, given costs involved. The Study is also required to identify effective mitigation measures in a holistic manner for the complex drainage system, rather than wasting funds on ineffective works or works that transfer problems from one location to another.

  10. Will the designation affect my house insurance?

    Response:

    The Insurance Council of Australia has advised Melbourne Water that most home insurance policies, which provide coverage for storm damage, include cover for damages resulting from overland flows. Residents are advised to check with their insurance companies, but the nature of flooding, i.e. drainage-related rather than waterway, would need to be disclosed to the insurer.

    As with any type of insurance cover, a premium is applied for flooding based on the insurance company’s assessment of flood risk as it applies to a property. Some insurance companies have indicated that they would be prepared to re-assess the premium following evidence being provided by the property owner that the flood risk has been over-estimated by the company. Property owners also have the option of ‘shopping around’ for an insurance company that is more competitive with respect to premiums.

  11. Designation of my property will result in significant addition construction costs in the event of any new building works.

    Response:

    The freeboard requirements for floors of habitable buildings on designated properties can impact on slab-on-ground construction costs, particularly when compared with common practices that are non-compliant with the Building Regulations requirements for minimum floor heights on non-designated properties. There may be a marginal increase in construction costs when a waffle raft slab system is used instead of a conventional slab system. The additional expenditure however results in improved property drainage and reduced flood risk.

  12. Is the information being gathered by Council going to affect property values or saleability?

    Response:

    It is important to note that designation of an area as liable to flooding does not cause or change the likelihood of flooding, but recognises the existing condition of land.

    The designation will not be described on title, but will be disclosed in Land Information Certificates issued under the Local Government Regulations, and for building permits under the Building Regulations.

    The value of any property is determined by the complex interplay of many different factors such as demand/supply, location, streetscape and amenity, and it is difficult to assign what effect if any, the identification of land as liable to flooding may have on the value of a property. Devaluation of properties (identified as being liable to flooding) is considered unlikely once the nature of flooding is explained and taken into account

  13. If the value of my property is adversely affected by the flood mapping information, is there compensation available?

    Response:

    There is no reason for payment of compensation, as nothing has changed about the likelihood of a severe storm occurring or the path that overland flow will take. The City now has accurate information which, in many cases, may already be known by people who have lived at a property for many years.

    There is also no case for compensation for subdivision of flood-prone land or construction of dwellings without elevated floors as subdivision and building permit applications were assessed in accordance with the planning scheme provisions and the building regulations, respectively, which were in place at that time

  14. Why was designation or a flood overlay not applicable to my property prior to purchase?

    Response:

    The City’s knowledge of actual flooding within the catchment studied has tended to be anecdotal in nature and therefore it was not suitable for designation of the 1 in 100 year flood extent, as required under State Government legislation. Reliable and credible flood data relating to the 1 in 100 year flood event is needed and this data can only be derived from a detailed flood study such as the Highton Drainage/Flood Study.

    The proposed flood overlay on the Planning Scheme is a future planning scheme amendment, as recommended in the Study. The planning scheme amendment generally follows designation by Council under the Building Regulations 2006.

  15. Will the flooding information and planning scheme overlay controls stop redevelopment of my property?

    Response:

    Generally not. The information will only be used to ensure that any future development of your property is carried out in a manner that recognises the location of areas that may be subject to flooding. Requirements for any proposed development will depend upon the flooding characteristics of the land such as depth and velocity, and the nature of the development proposed. Both Corangamite Catchment Management Authority and Council officers can provide preliminary advice on any likely requirements that will need to be met.

    It should be noted that development controls, apart from minimum floor levels, are only applicable in a statutory context once the flood overlay is created within the planning scheme. The overlay creation requires a planning scheme amendment where again submissions from the public are invited.

  16. I object to the flood status of my property being disclosed on a Land Information Certificate

    Response:

    The City is obligated under State Government legislation to disclose the flood status of a property that is considered to be liable to flooding as defined in the Building Regulations 2006.

  17. Can’t wording on Land Information Certificates be altered to provide property specific information such as impact of 1 in 100 year flood event or that flooding is stormwater flooding that is insurable?

    Response:

    Wording used on Land Information Certificates reflects State Government legislative requirements.

  18. I believe flooding of my property is due to blocked drains and pits.

    Response:

    Flooding is due mainly to lack of hydraulic capacity within older drainage systems that were designed to the lower standards that were applicable at that time, as well as the lack of easement drainage in some areas.

    The City’s Infrastructure Operations Unit endeavours to check critical council drainage assets for blockages or obstructions, in order to maximise use of capacity that may be available.


Appendix 1

Executive Summary - page 1 of 6
Executive Summary - page 2 of 6
Executive Summary - page 3 of 6 - Map of existing conditions 1% AEP Peak Flood Depth - figure E-1
Executive Summary - page 4 of 6 - Map of existing conditions 1% AEP Peak Flood Depth - figure E-2
Executive Summary - page 5 of 6
Executive Summary - page 6 of 6

Appendix 2

Highton Drainage/Flood Study - page 1 of 2
Highton Drainage/Flood Study - page 2 of 2

[Back to Top]