Council Minutes - Section B: Reports - 25 August 2015

Contents | Previous Page: Section A - Procedural Matters | Next Page: Section C - Assembly of Councillors

Reports tabled at the Ordinary Meeting of Council on Tuesday date held at the Council Conference and Reception Centre in City Hall, Little Malop Street, Geelong.


  1. Amendment C315 Rezoning Reformed Theological College and Christian College, 125-135 Pigdons Road, Waurn Ponds – Adoption of Amendment

  2. Leopold Land Capability and Bay Access Report

  3. Future Proofing Geelong Program Updates – Low Carbon Growth Plan for Geelong 2015 – Update and Impact Statement 2011-2014

  4. Development Contribution Plans – Annual Report 2014-15

  5. Sport and Recreation Infrastructure – Confirmation of Election Commitments

  6. Simonds Stadium – Stage 4 Development

  7. City Plan 2013-2017 Progress Report to June 2015

  8. Annual Financial Report for the Year Ended 30 June 2015

  9. 2015-2016 Budget Amendments

  10. Local Government Rates Capping and Variation Framework Review July 2015

  11. Digital Geelong Implementation Plan

  12. Chief Executive Officer Recruitment



1. Amendment C315 Rezoning Reformed Theological College and Christian College, 125-135 Pigdons Road, Waurn Ponds – Adoption of Amendment

Portfolio:

Planning – Cr Michelle Heagney

Source:

Planning and Tourism – Strategic Implementation

General Manager:

Peter Bettess

Index Reference:

Amendment C315


Purpose

The purpose of this report is to consider the submission received in relation to Amendment C315 and to adopt the Amendment.


Summary

Cr Heagney moved, Cr Nelson seconded -

That Council solves to:

  1. adopt Amendment C315 in the form as outlined in Appendix 2 of this report; and

  2. submit the adopted Amendment with the prescribed information to the Minister for Planning requesting approval.

Carried.


Background

Amendment C315 has been requested by the Reformed Theological College and Christian College. Appendix 1 shows the subject land.

The amendment proposes to apply Schedule 15 to the Special Use Zone, which provides for private education centres, to the land, with changes to address the matters raised by the Minister administering the Pipelines Act 2005.

Schedule 15 to the Special Use Zone provides a range of use and development options that are appropriate for a Private Education Centre.

The amendment will:


Discussions

The land to be re-zoned is located on the western side of Pigdons Road, immediately south of the Geelong Ring Road. To the south of the Reformed Theological college is the new Epworth Private Hospital, which is presently under construction, and is located in Schedule 14 to the Special Use Zone.

To the south of the Epworth Hospital is the Waurn Ponds campus of Deakin University, which is located in the Schedule 2 to the Public Use Zone, (PUZ2).

Both the Reformed Theological College and Christian College are long standing existing uses on the land, which pre-date the re-zoning of the land to Rural Zone – now Farming Zone – with the introduction of the Victoria Planning Provisions (VPP) based planning scheme. Prior to the introduction of the VPP based planning scheme the land was zoned for Special Use, generally equivalent to the schedule to the Special Use Zone which is now proposed to be applied to the land.

While both Colleges enjoy existing use rights under Clause 63 of the Scheme, the Farming Zone is limited in the discretionary uses available and education facilities (both use and development) are prohibited. Hence it is seen as appropriate to apply to both Colleges the schedule to the Special Use Zone which is designed to cater for private education institutions.

In accordance with the directions of the Regional Manager, Planning and Development Barwon South West Region, Regional Development Victoria, limited notice of Amendment C315 was given to the following prescribed Ministers:

Following Exhibition a submission was received on behalf of the Minister administering the Pipelines Act 2005, indicating that the amendment was not supported in the exhibited form, due to the presence of a gas transmission pipeline on the eastern side of Pigdon’s Road, opposite the land to be re-zoned.

Following discussions with the officers of the Earth Resources Regulation unit of the Department of Economic Development, Jobs Transport and Resources (DETJTandR) and employees of Ausnet Services, which operates the pipeline, the Amendment was supported, subject to changes to both Schedule 15 to the Special Use Zone and Clause 66.04, which specifies the circumstances in which permit applications are required to be referred to referral authorities. The amendment to be adopted, see Appendix 2, contains the changes agreed to with DETJTandR.

Correspondence was received from DETJTandR confirming that the alterations to the amendment, as now proposed to be adopted addressed the concerns initially expressed on behalf of the Minister administering the Pipelines Act 2005, see Appendix 3.

As the only submission which was received has been resolved Council is now able to adopt the amendment and forward it to the Minister for Planning seeking approval.


Environmental Implications

No adverse environmental consequences have been identified as arising from this proposal.


Financial Implications

It is not expected that the proposal will result in any financial implications for Council.


Policy/Legal/Statutory Implications

The proposal supports the planning policy framework and will allow for the expansion of educational services for which there is a growth in demand in Geelong.


Alignment to City Plan

The Amendment supports the ‘Community wellbeing’ and ‘Sustainable built and natural environment’ strategic directions of City Plan.


Officer Direct or Indirect Interest

No Council Officers involved in the preparation of this Report have any direct or indirect interest, in accordance with Section 80 (c) of the Local Government Act to which this amendment relates.


Risk Assessment

No significant risks have been identified as being associated with implementing the recommendation contained in this report.


Social Considerations

The amendment is seen as being positive in terms of social effects. Both the Reformed Theological College and Christian College already exist on the land. The amendment will provide the framework that acknowledges the use on the site, and provides for increased certainty for the longer-term development of both institutions.


Human Rights Charter

The amendment will not impact on basic human rights, freedoms and responsibilities as set out in the Charter. Planning legislation provides for the exemptions to the usual consultation process for amendments, which the Minister for Planning duly granted.


Consultation and Communication

Limited exhibition of the Amendment, to Ministers specified in Section 19(1)(c) of the Planning and Environment Act, 1987, was undertaken in accordance with the direction under delegation from the Minister for Planning, as set out in correspondence from the Regional Manager, Planning and Development Barwon South West Region, Regional Development Victoria, dated 26 November, 2014.


APPENDIX 1 – SUBJECT LAND

Subject land

APPENDIX 2 – AMENDMENT TO BE ADOPTED

Amendment C315 - Instruction Sheet
Amendment C315 - Local Provision
Amendment C315 - Schedule 15 to the Special Use Zone - page 1 of 3
Amendment C315 - Schedule 15 to the Special Use Zone - page 2 of 3
Amendment C315 - Schedule 15 to the Special Use Zone - page 3 of 3
Amendment C315 - Schedule to Clause 66.04 - page 1 of 3
Amendment C315 - Schedule to Clause 66.04 - page 2 of 3
Amendment C315 - Schedule to Clause 66.04 - page 3 of 3

APPENDIX 3 – Letter from Department of Economic Development, Jobs, Transport and Resources.

Letter from Department of Economic Development, Jobs, Transport and Resources
[Back to List]

2. Leopold Land Capability and Bay Access Report

Portfolio:

Planning - Cr Heagney

Source:

Planning Strategy and Urban Growth

General Manager:

Peter Bettess

Index Reference:

Project: North of Portarlington Road, Leopold


Purpose

The purpose of this report is to present the findings of the Leopold Land Capability and Bay Access report, prepared by Spiire consultants, in response to a direction in the Leopold Structure Plan 2013.


Summary

Cr Heagney moved, Cr Macdonald seconded -

That the report be deferred.

Carried.


[Back to List]

3. Future Proofing Geelong Program Updates – Low Carbon Growth Plan for Geelong 2015 – Update and Impact Statement 2011-2014

Portfolio:

Environment and Sustainability - Cr Richards

Source:

Planning Strategy and Urban Growth

General Manager:

Peter Bettess

Index Reference:

Subject: Future Proofing Geelong


Purpose

This report provides an overview of the Low Carbon Growth Plan for Geelong 2015 Update and the Future Proofing Geelong Impact Statement 2011-2014 and current work of Cleantech Innovations Geelong. The report recommends that Council note the findings in both documents and Future Proofing Geelong’s work on actions that facilitate: energy efficiency retrofitting in commercial buildings, developing the market for clean technologies, and sustainable living in the residential sector.


Summary

Cr Richards moved, Cr Harwood seconded -

That Council note the findings of the Low Carbon Growth Plan for Geelong 2015 Update; the Future Proofing Geelong Impact Statement 2011-2014; and Future Proofing Geelong’s work on actions that facilitate energy efficiency retrofitting in commercial buildings, developing the market for clean technologies, and sustainable living in the residential sector.

Carried.


Background

The Low Carbon Growth Plan for Geelong was published in 2011 is included in Appendix 1. It identified key opportunities to transition Geelong’s economy towards a low carbon future while achieving positive economic and social benefits. These key opportunities included:

The focus of Future Proofing Geelong has been to promote and support new and existing initiatives from business, industry, the community and government that seek to improve environmental, social and economic outcomes for Geelong. Initiatives that lead to jobs, skills development and business development, will further enhance the prosperity of Geelong for future generations.

Following the expiry of the Sustainability Covenant, which united the partners of Future Proofing Geelong from 2011-2014, a Memorandum of Understanding (MOU) was signed in late 2014 to further cement a three-year partnership to deliver the objectives of Future Proofing Geelong. The partners (signatories) to this MOU include: the City of Greater Geelong, the Geelong Manufacturing Council, Deakin University, the Geelong Chamber of Commerce, Barwon Water, the Committee for Geelong, Barwon Health, Geelong and Region Trades and Labour Council, The Gordon and the Barwon South West Waste and Resource Recovery Group. The parties are represented as an Advisory Board chaired by Cr Richards and which involves the Mayor and Councillors Macdonald, Harwood and Ellis.


Discussion

An Impact Statement for Future Proofing Geelong was prepared in 2014 to record outcomes between 2011 and 2014, against the original Low Carbon Growth Plan. It identified emission reduction outcomes and significant opportunities.

The Future Proofing Geelong Impact Statement 2011-2014 is in Appendix 2.

The results in the Impact Statement 2011-2014 point to significant progress been made in establishing Geelong as a more liveable, productive and sustainable city. This work continues to bring benefits to the Geelong community; creating sustainable jobs, building skills and expanding businesses.

The success of Future Proofing Geelong and the early benefits identified in the Impact Statement 2011-2014, highlight the significant role of the MOU partners and their willingness to champion such a significant initiative. This partnership has harnessed a ground swell of community, business and industry support to deliver the commitments of the Low Carbon Growth Plan for Geelong. The Future Proofing Geelong team has played a significant role in the implementation of the Low Carbon Growth Plan for Geelong recommendations, highlighting the importance of Local Government’s role in this initiative and the long-term gains that can be made in the Geelong community over the coming decades.

The Low Carbon Growth Plan for Geelong 2015 Update identified future opportunities to be explored in Geelong including a more collaborative approach by partnering with other Councils possibly on the procurement of energy, continued approaches to State and Federal Government to secure assistance for businesses and industries which can diversify the economy to a low carbon future and continued work with Cleantech Innovations Geelong.

Cleantech Innovations Geelong is an alliance of business, industry, academia and non-government organisations looking to develop markets for clean technologies. The aim is to establish Geelong as a Centre of Excellence for cleantech in Australia, by attracting investment, creating jobs and building skills. Clean Technology includes economically viable products, services and processes that harness renewable materials and energy sources, dramatically reduce the use of natural resources and cut or eliminate emissions and wastes.

Since its launch in 2013, Cleantech Innovations Geelong has provided a focus for businesses in Geelong looking to establish their next generation of innovation. A market analysis has shown that the growth areas in cleantech include clean cities, renewables, energy efficiency, waste management and recycling, water, green buildings, biomaterials and bio fuels. The multiplier effect of cleantech jobs is that for every job created, anywhere between 2 to 6 peripheral jobs will be generated.

Cleantech Innovations Geelong facilitates a robust level of support to stimulate demand for cleantech goods and services, and develops the Geelong market to respond to this increased demand. Cleantech Innovations Geelong will improve the productivity and competitiveness of participating businesses and industry, by facilitating the delivery of strategically planned projects which secure market development opportunities. Projects have already been identified to support manufacturing and engineering, green buildings and environmental product and service providers.

The program is a partnership between the Geelong Manufacturing Council, the City of Greater Geelong and the Manufacturing Productivity Network Program (state government).

The work of Cleantech Innovations Geelong is overseen by an Advisory Board co chaired by CoGG and Geelong Manufacturing Council.


Environmental Implications

Future Proofing Geelong is delivering positive environmental outcomes through education and assistance to businesses and the wider community to improve energy, water and waste efficiency, and reduce carbon emissions.


Financial Implications

Future Proofing Geelong is funded for $350,000 in the 2015/16 financial year to continue implementation of the MOU (dated 2014-2017) and therefore the recommendations of the Low Carbon Growth Plan for Geelong.


Policy/Legal/Statutory Implications

Future Proofing Geelong is a key program in delivering the outcomes of the recently adopted Environmental Management Strategy (EMS) for the City of Greater Geelong. Future Proofing Geelong is directly responsible for the implementation of seven actions in the EMS.


Alignment to City Plan

The Community Wellbeing strategic direction in City Plan identifies the need to build upon existing capacities in local communities. Future Proofing Geelong has provided a mechanism to facilitate collaboration across community groups committed to sustainability and to grow the capacity of these groups, and provide an aggregation of sustainability initiatives in the Geelong region.

Under the Growing Our Economy strategic direction, the priorities of supporting existing business and encouraging new and emerging growth sectors refers to the “support and encouragement of new and emerging low carbon industries and sectors” and “link local businesses with growth opportunities and government funding”. The Future Proofing Geelong program and specifically the Cleantech Innovations Geelong initiative under this program support this priority.

The Future Proofing program is directly involved in “proactively targeting and attracting new investment to Geelong and promoting our regions benefits” and being an “advocate for and support innovative and new technological initiatives”.

Under the Sustainable Built and Natural Environment, Future Proofing Geelong/Low Carbon Growth Plan is identified as a key strategy. Future Proofing Geelong delivers priorities under this direction to support our community to live sustainability, and advocate for and promote sustainable design and development.


Officer Direct or Indirect Interest

No Council Officers have a direct or indirect interest in accordance with Section 80(c) of the Local Government Act in the issue to which this report relates.


Risk Assessment

There are no risks associated with this report.


Social Considerations

The Future Proofing Geelong project has positive social impacts through community engagement, job creation and skills development.


Human Rights Charter

This report has no impact on the human rights charter, however it is noted that the aims of Future Proofing Geelong support the human rights charter.


Consultation and Communication

The Future Proofing Geelong website is regularly updated to showcase the work the City of Greater Geelong and other Future Proofing Geelong partners are doing to deliver the vision of the program, and to deliver the recommendations in the Low Carbon Growth Plan.


A communications plan exists for key deliverables within Future Proofing Geelong including the Sustainable Living Festival, the work with commercial building owners/tenants and Cleantech Innovations Geelong.

Geelong Cats footballer, Tom Lonergan, has agreed to be the Future Proofing Geelong Ambassador in May 2015. His first public appearance in this role was to launch the Low Carbon Growth Plan for Geelong 2015 Update.


[Back to List]

4. Development Contribution Plans – Annual Report 2014-15

Portfolio:

Finance - Cr Lyons (Mayor), Cr E Kontelj and Cr Farrell

Source:

Planning and Tourism

General Manager:

Peter Bettess

Index Reference:

Development Contribution Plans - Governance


Purpose

As part of Council’s Development Contribution Governance Framework an annual report is to be presented to Council and the Audit Advisory Committee reporting on the income, expenditure and general performance of Development Contribution Plans over the past 12 months.


Summary

Cr Farrell moved, Cr E Kontelj seconded -

That Council notes the 12 month report on Development Contribution Plans and the current funding gap of approximately $22.5M over the next 15-20 years.

Carried.


Background

Geelong is experiencing significant urban growth across the municipality and with this growth comes the need for delivering key infrastructure to service these new communities.

One of the key funding avenues to deliver this infrastructure is the use of development contributions, or more formally, the use of a Development Contribution Plan (DCP).


A DCP is an incorporated document within the planning scheme that allows Council to levy a charge upon a specific area / precinct of development in order to facilitate the delivery of future projects specifically required to service this area / precinct (e.g.: traffic lights, recreation reserves, community centres, etc).

Council’s DCPs require the delivery of approximately $482M in essential projects to service urban growth, with the current performance of these DCPs reflecting a remaining liability of approximately $437M and remaining income of approximately $415M expected over the next 15 - 20 years. This represents a current funding gap of approximately $22.5M.

Over the past five years the City of Greater Geelong has been implementing a detailed governance framework for the administration of DCPs. The framework is aimed at ensuring all DCPs are managed and administered in a strategic, consistent, accountable and transparent manner (Refer Appendix 1 – CoGG DCP Governance Framework).

A recognised component of the governance framework was the need to provide an annual report to Council detailing the performance of Council’s DCPs over the past financial year.

The report is aimed at summarising the following key features:

These themes are also consistent with the recommendations made by the Standard Development Contribution Advisory Committee responsible for recommending reforms within the State Government’s new development contributions system. This new system is planned for implementation in 2016.

Council has previously undertaken an external audit of its total DCP Governance Framework (Crowe Horwath, CoGG Management of Development Contributions, Nov 2013). The report provided positive feedback on the management of DCPs within the City of Greater Geelong.

During 2014-15 Council officers identified continuous improvement opportunities for the system and areas that would benefit from a formal internal audit on an ongoing basis.

The key improvement areas identified by officers include the communication of key DCP principles and financial obligations to Councillors and the community; the development of key performance indicators to assist with communication, reporting and decision making; and continued utilisation of a risk management approach to DCP administration.

In relation to the indexation performance of Council’s DCP Levies Appendix 4 – Development Contribution Plan Levies – Indexation Trends (4 years) shows the average annual increase of between 1.3% and 1.7% per annum for Council’s DCP Levies. A key factor in this variation is based on DCP levies being indexed via three separate indices for land, civil works and building projects.


Discussions

DCP INCOME RECEIVED

Council currently has three DCPs generating income from either the Development Infrastructure Levy (DIL) or the Community Infrastructure Levy (CIL, $900 / dwelling), or both (refer Appendix 2 – DCP Summary Report).

The total income received across these three DCPs (Armstrong Creek East and West and Jetty Road) was $2.046M ($1.39M for DIL and $0.65M for CIL).

The total income received for all three DCPs since their approval is $4.96M.

DCP WORKS IN KIND PROJECTS

Works in kind projects are those projects delivered by developers in exchange for a credit against their developments DCP liability.

A total of six (6) works in kind projects were delivered either in full or in part during 2014-15; two being within the Armstrong Creek East Precinct (drainage / creek works) and four being within the Armstrong Creek West Precinct (intersection, shared paths and drainage works).

The credited value of these DCP projects was $18.30M. For a detailed breakdown refer Appendix 2 – DCP Summary Report.

DCP PROJECTS DELIVERED BY COUNCIL

Council has completed works associated with four (4) DCP projects during 2014-15, one of these being a land project detailed under the next section of this report (DCP Funded Land).

The remaining three projects include an intersection within the Armstrong Creek West Precinct (delivered in partnership with VicRoads as part of the construction of Baanip Boulevard), a set of pedestrian lights on Jetty Road (delivered in partnership with other Bellarine rail trail surfacing works) and the waterway improvement works along Griggs Creek.

Across these three projects, savings of $733,578 have been achieved as a direct result of strong strategic and proactive procurement processes. These savings can be reinvested back into the DCP to cover the cost to the Council of future over expenditure of other higher risk projects (e.g.: land acquisition projects).

The value of these DCP projects totalled $1.13M. For a detailed breakdown refer Appendix 2 – DCP Summary Report.

DCP FUNDED LAND

During 2014-15 only three land projects were undertaken within Council’s DCP growth areas (refer Appendix 2 – DCP Summary Report).

Two of these projects were land for drainage projects within the Armstrong Creek West Precinct (totally 1.219 hectares of unencumbered land, credited at $0.36M), while the third project only involved preliminary legal costs associated with compulsory acquisition of the Jetty Road North South Connector Road (Part A).


DCP FUNDING GAPS

A critical component of managing Council’s DCPs is a clear understanding of the funding gap associated with delivering Council’s legal obligations under the DCPs.

Council DCPs require the delivery of approximately $482M in essential projects to service urban growth. The current performance of these DCPs reflects a remaining liability of approximately $437M with remaining income of approximately $415M expected over the next 15 - 20 years.

Council’s total funding gap across all active DCPs is $23.7M, however due to project savings and the delivery of projects that require Council matching funds, this funding gap has now been reduced to $22.5M (as at 30 June 2015).

For a detailed breakdown of Council’s current liabilities and gap funding refer Appendix 3 - Development Contribution Plans - Whole of Life Remaining Liability, Income and Funding Gap.

DCP GROWTH AREAS – DEVELOPMENT ACTIVITY

Another important aspect of DCP management is understanding the development activity that supports the generation of income for the DCPs and also triggers the need for DCP projects that service these new communities.

The Federal Government’s 2011 census information is used as the basis to undertake long-term development and population forecasting for the City of Greater Geelong. This forecasting assists with the forward planning of DCP projects, particularly those requiring Council delivery.

Appendix 5 – Armstrong Creek Annual Dwelling Activity by Suburb (Compared to forecast) illustrates the development activity within the City’s major growth area, Armstrong Creek. The table highlights the need for strong financial planning and early infrastructure investment to ensure Council delivers DCP projects are required under the DCP (e.g.: facilities like community and recreation facilities, land projects to facilitate other projects and in some case drainage projects required to unlock / service fragmented development fronts).

The table in Appendix 5 shows the Armstrong Creek growth area (ie: the two active suburbs of Armstrong Creek and Mt Duneed) are delivering dwellings at 57% above that forecast for the 2012/13 to 2014/15 period (i.e.: projected dwellings of 1,019 versus actual dwellings 1,603). This is 146 additional dwellings per annum above the dwelling forecast for the same period.

The Jetty Road growth area has seen dwelling activity relatively consistent with the forecast for the area.

GENERAL DCP PROGRESS REPORT

Jetty Road Urban Growth Area Stage 1

The Jetty Road development (a.k.a. Curlewis Growth Area) is significantly advanced with the Curlewis Parks estate nearing completion. Another four developments are also well underway.

Council has constructed the Bellarine rail trail pedestrian lights at Jetty Road and partial works for the Griggs Creek Rehabilitation and Revegetation.

Council has received Community Infrastructure Levies for 97 lots during 2014/15 (with 126 being received in 2013-14).


Armstrong Creek East Precinct

The Armstrong Creek East Precinct’s main developer, Warralily, is progressing development on multiple fronts on Barwon Heads Road and Surf Coast Hwy.

Warralily is continuing to provide the Armstrong Creek drainage and waterway improvement works between Barwon Heads Road and Surf Coast Highway to offset its DCP liabilities. An additional two estates, Horizon Cover and Armstrong Waters, are also progressing development to the west of Barwon Heads Road.

Council has received Community Infrastructure Levies for 406 lots during 2014/15 (with 449 being received in 2013-14)

Armstrong Creek North East Industrial Precinct

The Armstrong Creek North East Industrial Precinct Development Contribution Plan was approved in 2010. Development is yet to commence in this precinct.

Armstrong Creek West Precinct

The Armstrong Creek West Precinct’s main development Armstrong Mt Duneed estate has continued development west of Surf Coast Highway. As part of offsetting its DCP liabilities it has constructed the intersection at Surf Coast Highway and Burvilles Road and a shared path along Sovereign Drive. The developer is also continuing to provide the Armstrong Creek waterway improvement and drainage works between Surf Coast Highway and Sovereign Drive.

As part of the Armstrong Creek West DCP, Council has completed construction of the intersection at Baanip Boulevard and Sovereign Drive.

Council has received Community Infrastructure Levies for 224 lots during 2014/15 (with 71 being received in 2013-14).

Lara West Growth Area

Amendment C285 - Lara West Growth Area DCP was approved by the Minister for Planning on 17 July 2014. The first development, Manzeene Village, will commence development during 2015/16.

Armstrong Creek Town Centre Precinct

Amendment C267 Armstrong Creek Town Centre Development Contributions Plan was approved by the Minister for Planning on 23 October 2014. The DCP includes eight intersections, shared paths, drainage works and contribution towards the construction of a Regional Library. Development is expected to commence in 2016-17 financial year.

Horseshoe Bend Precinct

Amendment C259 Armstrong Creek Horseshoe Bend Development Contribution Plan was approved by the Minister for Planning on 27 November 2014. The Horseshoe Bend DCP includes active open space, intersections, drainage works and community centres. Development is expected to commence in 2015-16 financial year.


Environmental Implications

There are no significant environmental impacts as a result of the management and administration of Council DCP system.


Financial Implications

One of the main features of the development contributions system is to ensure that new development funds essential infrastructure required to service these new communities.

The system is also setup to ensure these new development doesn’t create an unfair burden on the existing community. Therefore it is important to recognise the $22.5M funding gap in DCP projects and ensure these funds are included in Council long-term financial plan and various funding strategies are put in place to secure these funds when required with minimal impact to the existing community.


Policy/Legal/Statutory Implications

The report has been prepared to reflect Council’s obligations under the Victorian Local Government Act (1989) and Planning and Environment Act (1987).


Alignment to City Plan

The report supports the How We Do Business strategic direction of City Plan, in particular the priority of ‘responsible and sustainable financial management.


Officer Direct or Indirect Interest

There is no direct or indirect officer conflict.


Risk Assessment

As part of the Governance Framework a detailed risk assessment has been undertaken to capture the management of development contribution within Council. Key risks have been recorded on Council corporate risk register, while lesser risks have been included as part of the DCP administration process / procedures.

Some of these risks include failure to delivery infrastructure projects; over expenditure on DCP projects; and early claims for property purchase / compensation.


Social Considerations

There are no significant social impacts as a result of the management and administration of Council DCP system.


Human Rights Charter

Council officers have taken into consideration the Human Rights Charter relative to the subject matter of this report.


Consultation and Communication

A summary of the report has been included in the draft City of Greater Geelong 2014-15 Annual Report.


APPENDIX 1

CITY OF GREATER GEELONG
DEVELOPMENT CONTRIBUTION GOVERNANCE FRAMEWORK

Development contribution governance framework
[Back to List]

5. Sport and Recreation Infrastructure – Confirmation of Election Commitments

Portfolio:

Sport and Recreation - Cr Irvine

Source:

Projects, Recreation and Central Geelong - Sport and Recreation

I/General Manager:

Jenny McMahon

Index Reference:

Subject: Sport and Recreation Grants and Funding -Incoming


Purpose

The purpose of this report is to inform Council of sport and recreation infrastructure projects funded (or part funded) by the State Government following commitments made prior to the last state election.

To seek Council endorsement of these projects and to confirm Council’s financial contribution as documented in Council’s four year Strategic Resource Plan.


Summary

Cr Macdonald moved, Cr Ellis seconded –

That Council:

  1. Note the State Government’s financial commitment to:

    1. The Drysdale Sports Precinct – Stage 1 Development

    2. Leopold Memorial Recreation Reserve – Pavilion Upgrade

    3. Barwon Heads Football Netball Club - Facility Upgrade

    4. South Barwon Football Club – Oval and Sports Lighting

    5. Barwon Heads Village Park – Spectator Viewing Area

    6. Geelong Soccer Club – Soccer Pavilion Upgrade

    7. Shell Road Reserve - Improvements

  2. Enter into funding agreements with the State Government of Victoria for these projects.

  3. Confirm Council’s forward financial commitment for the Leopold Memorial Recreation Reserve project in accordance with the four year Strategic Resource Plan as published in the adopted 2015/16 Budget.

  4. Confirm and bring forward Council’s financial commitment to the Drysdale Sporting Precinct project from 2017/2018 to 2016/2017 to allow this project to be delivered as soon as possible.

  5. Request from the State Government that the election commitment funding for the Drysdale Sporting Precinct be released as early as possible to expedite the commencement of the project.

Carried.


Background

The State Government of Victoria has confirmed funding for seven (7) sporting infrastructure projects following commitments made prior to the last state election.

These projects include:

  1. The Drysdale Sports Precinct – Stage 1 Development

  2. Leopold Memorial Recreation Reserve – Pavilion Upgrade

  3. Barwon Heads Football Netball Club - Facility Upgrade

  4. South Barwon Football Club – Oval and Sports Lighting

  5. Barwon Heads Village Park – Spectator Viewing Area

  6. Geelong Soccer Club – Soccer Pavilion Upgrade

  7. Shell Road Reserve - Improvements

The State Government has requested further information from Council to confirm these projects are ready to proceed prior to entering into agreements.

A further financial contribution from Council is required for two of the listed projects. Funding from the State Government for these two projects is contingent upon the Council funds being confirmed.


Discussion

The projects along with the required Council contribution, if applicable, are listed below:

  1. Project: Drysdale Sports Precinct – Stage 1 Redevelopment

    Project description: Construction of sporting field(s) and supporting infrastructure including car parking, sports lighting and pavilion facilities at the Drysdale Sports Precinct Site.

    Total project cost: $6,726,000

    State Government commitment: $3,500,000

    Council 2015/16 budget: Nil

    Council contribution required in 2017/2018: $3,226,000 - in accordance with the four year Strategic Resource Plan as published in the adopted 2015/16 Budget.

  2. Project: Leopold Memorial Recreation Reserve Pavilion Upgrade

    Project description: Construction of new netball change rooms, two netball courts with sports lighting to training standards and upgrade to the existing pavilion.

    Total project cost: $2,545,000

    State Government commitment: $1,500,000

    Council 2015/16 budget: $445,000 (carry over 2014/15)

    State Government Sport and Recreation Victoria (SRV) Country Football Netball Grant for 2015/16: $100,000

    Council contribution required in 2016/2017: $500,000 - in accordance with the four year Strategic Resource Plan as published in the adopted 2015/16 Budget.

  3. Project: Geelong Soccer Club Pavilion Upgrade

    Project description: Redevelopment of the pavilion and change facilities at the Stead Park soccer facilities. The project scope is dependent on a proposed sponsorship to be negotiated by the club.

    Total project cost: $750,000

    State Government commitment: $100,000

    Council budget allocation 2015/16: $250,000

    Proposed club sponsorship amount: $400,000 (unconfirmed)

    Council contribution required: Nil

  4. Project: Barwon Heads Football Netball Club Facility Upgrade

    Project description: The Barwon Coast Foreshore Committee has committed to managing this project. Council will act as an auspice for the funding agreement only.

    Total project cost: $225,000

    State Government commitment: $225,000

    Council contribution required: Nil

  5. Project: South Barwon Football Netball Club Oval and Lighting Upgrade

    Project description: This project involves new sports lighting to Australian Standards, a new electronic scoreboard and landscaping to provide improved spectator viewing including a terraced area, new coach’s boxes and improved accessibility to the sporting ground.

    Total project cost: $180,000

    State Government commitment: $150,000

    State Government Sport and Recreation Victoria (SRV) Local Facilities for Local Clubs program: $30,000 (confirmed)

    Council contribution required: Nil

  6. Project: Barwon Heads Village Park (Cricket) Improved Spectator Viewing Area

    Project description: Improved spectator shade at Barwon Heads Cricket Club (Barwon Heads Village Park). Specific project details are unknown, further scoping is required.

    Total project cost: $100,000

    State Government commitment: $100,000

    Council contribution required: Nil

  7. Project: Shell Road Reserve Improvements

    Project description: Council received a State Government grant of $100,000 towards an electronic scoreboard for Shell Road Reserve prior to the 2014 election. A further commitment of $60,000 was made to this project by the State Government, with funds to be made available in the 2016/17 financial year.

    The Ocean Grove Football Netball Club (OGFNC) has indicated that the scoreboard must be delivered by the start of the 2016 football season using the existing $100,000 grant. The remaining $60,000 is proposed to be used for construction/installation of sport and recreation infrastructure relating to the use of Shell Road Reserve. The project scope will be determined in consultation with the OGFNC.

    Total project cost: $60,000

    State Government commitment: $60,000

    Council contribution required: Nil

The above projects are summarised in table format see Attachment 1.


Environmental Implications

There are no foreseeable environmental implications associated with this report; all projects developed will include environmentally sustainable design initiatives.


Financial Implications

The State Government commitments provide an additional income to Council totalling $5,635,000.00.

Two (2) of the seven (7) commitments have a Council allocation in the current financial year (2015/16), they are:

Five (5) of the seven (7) commitments require no further financial contribution from Council, they are:

Two (2) of the seven (7) commitments are contingent on a forward commitment of funding by Council, including:

The Council contributions requested are in accordance with the four year Strategic Resource Plan as published in the adopted 2015/16 Budget.


Policy/Legal/Statutory Implications

To secure funding connected with the State Government commitments, Council will need to enter into agreements which require contributions for the Drysdale Sports Precinct and Leopold Memorial Recreation Reserve Projects.

There are no other legislative or legal ramifications associated with the adoption of this report.


Alignment to City Plan

The State Government commitment projects align to the City Plan’s priority of Community Wellbeing, encouraging healthy lifestyles and connected communities through active recreation and participation in sport.


Officer Direct or Indirect Interest

There are no officer conflicts of interest relating to the project being proposed for submission or this report.


Risk Assessment

There are no immediate risks associated with this report. A component of the project will entail relevant risk management and OHandS.


Social Considerations

The expected population growth within the municipality necessitates the increased and improved provision of community sport facilities which provide a social outlet for the local community.

Participation in sport and recreational activities has long been recognised as an important contributor to community health and well being. Benefits of physical activity are well documented and include improved health, development of social skills, increased community connectedness and enhanced self-esteem.


Human Rights Charter

This report has no impact on human rights.


Consultation and Communication

Council officers will communicate and consult directly with sporting clubs to ensure the efficient delivery of State Government commitments that aligns with funding availability.


[Back to List]

6. Simonds Stadium – Stage 4 Development

Portfolio:

Sport and Recreation – Cr Irvine

Source:

Projects, Recreation and Central Geelong / Sport and Recreation

I/General Manager:

Jenny McMahon

Index Reference:

Property #214458 Simonds Stadium


Purpose

The purpose of this report is to seek Council’s approval for the capital development of Simonds Stadium (Stage 4) as land manager for the site.

To resolve Council’s consideration of a financial contribution to the capital development of the Simonds Stadium (Stage 4).

To consider the request from the Kardinia Park Trust for an annual contribution of $1.5M to support ongoing operations at the site.


Summary

Cr E Kontelj moved, Cr Irvine seconded -

That Council:

  1. As land manager, approve the development of Simonds Stadium (Stage 4) subject to :

    1. the State Government of Victoria agreeing to take ownership of the new stand, including asset and maintenance obligations;

    2. the State Government of Victoria accepting financial liability for any works triggered as a consequence of the development within the broader parklands and internal road network;

    3. the reinstatement of Legends Plaza to the satisfaction of Council; and

    4. all additional costs associated with delivering events in the venue over the construction period, being borne by the project.

  2. Agrees in principle to commit up to $6M to the Stage 4 Simonds Stadium development and authorises the CEO to sign funding agreements with the Geelong Football Club for up to $6M, conditional on the following, that:

    1. the payment is not due until the conclusion of the 2017/2018 financial year;

    2. the State Government enters into an agreement with Council agreeing that the State Government will:

      • assume management and operations of Simonds Stadium and Kardinia Park;

      • absolve and indemnify Council of any ongoing financial contributions to the operation  and management of Simonds Stadium and Kardinia Park;

  1. Council, the Geelong Football Club and State Government enter into a sponsorship agreement that recognises Councils contribution to the Project.

  2. Supports the staged implementation of the Kardinia Park Trust Working Group and authorises the CEO to:

    1. enter into negotiations with the Victorian State Government and Kardinia Park Trust to transition operations;

    2. decline the request for continued operational funding for the Trust; and

    3. report back to Council on negotiations prior to the conclusion of the calendar year.

Carried Unanimously.


Background

Council is currently the Committee of Management for Kardinia Park under the Geelong (Kardinia Park) Land Act 1950. As Committee of Management, Council must approve any developments on site prior to seeking consent from the Crown or the Department of Environment, Land, Water and Planning (DELWP). This Committee of Management role also places a set of obligations upon Council for the management, improvement and maintenance of the reserve.

Simonds Stadium via the Geelong Football Club (GFC) was successful in the last Victorian State Election in securing a $75M commitment to replace the Jennings and Brownlow stands.

The replacement of these stands continues the redevelopment of Simonds Stadium, which commenced in 2003. The City of Greater Geelong’s total capital contribution over these three stages was $10.5M. This capital contribution is in addition to the annual net cost of approximately $1.5M to operate the stadium.


The table below notes the stages and Council’s contributions since 2003.

Year

Stage

Council commitment

Period

Funding source

2003

Stage 1 – Hickey Stand

$6M

2003-04 $2M
2004-05 $2M
2005-06 $2M

Capital Works Programme

2008

Stage 2 – Premiership Stand

$1.5M

2009-10 $1.5M

Capital Works Programme

2011

Stage 3 – Players Stand

$3M

2013-14

Capital Works Programme


The replacement of the Jennings and Brownlow Stands also coincides with the formation of a Kardinia Park Trust Working Group that will establish a Trust similar to that of the Melbourne Cricket Ground and the Melbourne and Olympic Park Trusts.

The Geelong Football Club has sought a contribution from the City of Greater Geelong of $6M towards the proposed $90M development.

The funding mix initially proposed by Geelong Football Club for the development is outlined below.

Funding Source

GFC Requested Contribution

Committed Contribution to Date

State Government

$75M

$75M

Geelong Football Club

Up to $ 4M

Up to $4M

The Australian Football League

$5M

$4M

City of Greater Geelong

$6M

$0


An economic impact analysis of the Simonds Stadium (Stage 4) development was commissioned by the Geelong Football Club and sought to understand the impact of the development on the local economy.

In this analysis, the Stage 4 development was considered as the first two stages in a six (6) stage development. The report did not consider the first two stages, as currently proposed, in isolation. The staging in the analysis is as follows:

Should the total development be completed as proposed in the analysis, it would increase viewing capacity to 37,423 and deliver an increased annual spend in the local economy of $15M. The replacement of the Jennings and Brownlow Stands as now proposed will increase capacity by approximately 3,000 taking the ground’s capacity to 34,379.

Architects have been appointed and the project is underway. Confirmation of the total funding available is required prior to the end of August 2015. This will ensure the project can commence in time to allow for demolition and installation of temporary facilities to support major events, including the A-League game, over the summer period.

Aligned with the stadium development will be the implementation of the Victorian Labor Government’s commitment to establish a Trust for Kardinia Park. A Kardinia Park Trust Working Group has now been established and it is understood that the enabling legislation to create the trust will be introduced into parliament later this year.

The exact scope of the Trust’s responsibility at this stage is unknown, with a variety of models being considered by the working group. The scope options range from complete management responsibility for the Kardinia Park precinct, to management of the Simonds Stadium as a separate entity.

Early discussions with the State Government and the Trust Working Group’s chair, the Honourable Steve Bracks AC, indicate that the Trust will seek to manage the entire precinct, excluding the aquatic facility. It is expected that Trust’s formation will extinguish Council’s role as Committee of Management and in doing so, will transfer the obligations for management, improvement and maintenance of the reserve to the Trust.

The Chair of the Kardinia Park Trust Working Group and has written to Mayor Cr Darryn Lyons seeking that Council continues its role in the Kardinia Park Precinct until such time as the Kardinia Park Trust is developed, which will require approximately 12 months from the enacting of the legislation.


Discussions

The Geelong Football Club’s request for funding support for the Simonds Stadium (Stage 4) development, in advance of the establishment of the Kardinia Park Trust, is a difficult proposition due to numerous unknown and/or unresolved issues regarding the future management of the precinct.

Council’s contribution to and involvement in Stage 3 of the stadium development was made on the basis that Council is the asset owner and bears responsibility for the ongoing maintenance and potential replacement of the assets and infrastructure within the stadium. It is expected that the Committee of Management and the aforementioned obligations will be extinguished with the implementation of the Trust, releasing Council from its obligation for asset management.

The Geelong Football Club has sought a response from Council by the conclusion of August 2015, to allow the project to commence in September 2015 subject to Open Space and Land Managers approval. This construction timeline will have the least impact to AFL seasons and allow for temporary broadcast and media facilities to be in place for the 8 January 2016 A-League fixture.

The resolution of the Kardinia Park Trust, the proposed management model and scope of responsibilities is projected to come before parliament prior the end of this calendar year. The consequence of this timing being that Council at this time does not fully understand its future role at Simonds Stadium while considering its position on financial support for Stage 4.

The following points note the range of considerations for Council in making its decision. Given the complexity and relationships between the issues, the funding support for the Stage 4 development should not be considered in isolation. The following sections consider these points.

Stage 4 Development Land Managers Consent

The Stage 4 development will see an approximate increase of 2,500 to 3,000 seats and will replace the Jennings and Brownlow Stands. This stage of the development is the most complex of all stages to date, as it includes the area that houses all the stadium’s broadcast facilities, most of the Geelong Football Cub’s football department and Club Cats. Many of the services in this area are critical for stadium operations and need to be established on a temporary basis during the construction phase to ensure the stadium remains operational.

As the current Committee of Management for Kardinia Park, Council is required to consent to any development on the site should it be deemed appropriate. Under normal circumstances, this consent to development would trigger a number of conditions to mitigate Council’s future obligations on the site and address any broader implications with respect to the change of business that would impact park infrastructure or operations.

Discussions with the Victorian Government have confirmed that it will accept liability for the new stand asset and also any obligations that the stand’s development will trigger, such as the requirement for additional parking. This agreement is reflected as a condition of land managers approval.

Stage 4 Development $6M Contribution

The current confirmed budget for the Simonds Stadium (Stage 4) development inclusive of the requested Council contribution is $89M. Council’s contribution would enable the project to be completed in its current proposed form and minimise the impact on the AFL 2016 home and away season with a scheduled completion early in the 2017 season.

The immediate time critical factor in the development is the demolition of the current stands and the erection of temporary facilities ready for the A-League fixture in January 2016.

Should Council elect not to financially support the project, it is assumed that a process of value management would need to be undertaken to re-scope the project to fit with the revised budget. This process has the potential to delay the critical timeline of demolition and erection of the temporary facilities.

Kardinia Park Trust

The Honourable Steve Bracks AC has sought that Council continue its operational role at Kardinia Park Precinct until the Trust has had an opportunity to become fully operational. At this stage the exact scope of the Trusts role is not known and could range from the operations of Simonds Stadium to full management of the Kardinia Park precinct, this will only be confirmed once the necessary legislation has been enacted.

The Honourable Steve Bracks AC has sought from Council that it continues its normal operations in the reserve until the Trust is operational; he has also sought from the Council an ongoing annual financial commitment of $1.5M.

Given that the scope of Trust is not yet known and Councils role within it, it is difficult to quantify any potential savings and or cost associated with this request, however it has been recognised that due to the complex nature of the site a staged handover would be prudent.


Environmental Implications

There are no environmental implications as a result of this report.


Financial Implications

Council has not budgeted to support the Simonds Stadium (Stage 4) redevelopment in the 2015-16 budget or in Council’s Strategic Resource Plan.

Similarly, Council has not budgeted for an ongoing annual financial commitment of $1.5M to support the operations of the stadium once the Kardina Park Trust is in place, however the savings that would come with the cessation of Council’s operational role have not been factored in.

The following options have been identified as possible means of funding the $6M request for Stage 4 of the Simonds Stadium development

  1. Borrowings

    Debt levels greater that 60% of the rate revenue represents potential for longer term concern over ability to repay debt according to the Victorian Auditor Generals Office (VAGO). If Council was to borrow $6M in 2016-2017 it would cost Council $7.3M over 10 years to repay the loan and would increase debt levels well over the self imposed 75% threshold of the recommended 60% level recommend by VAGO.

  2. Loan balance histgory and projection including additional $6m
  3. Rate increase

    If Council was to consider funding the Simonds Stadium (stage 4) development via a rate increase, it would need to consider that a 1% rate increase equated to $1.4M. To achieve $6M funded over a 3 year period would require a single rate increase of 1.5% in the first year. The Essential Services Commission in its draft Blue Print for Change (July 2015) recommends a process whereby a variation to rate capping may be sought and notes five matters that the variation should address in seeking the variation. The Blue Print also recommends that variations can only be approved for a single year in the 2016/2017 year.

    Whilst an opportunity exists for Council to apply for a variation the outcome would not be known until May 2016. This timing of advice would pose a significant financial risk to Council.

  4. Revise Capital Works Priority

    Council could review its long term plan capital works and make a contribution to the Geelong Football Club of an amount equal to or less than $6M from the future capital works programme subject to the programme being amended with future projects being deferred.

  5. Savings

    The transition of the stadium and potentially park operations to the Kardinia Park Trust represents a significant savings opportunity for Council that, if realised, has the capacity to fund the $6M request. The subsequent request for $1.5M to support the Trusts operations significantly affects that capacity to realise savings from the transition. Currently operational funding for the Stadium is in the order $1.5M and $700k for the parkland, the capacity to realise these savings will be dependant on an understanding of Council’s future financial obligations to the Trust.


Policy/Legal/Statutory Implications

Council is currently the Committee of Management for the reserve under the Geelong (Kardinia Park) Land Act 1950. Council is obligated to meet requirements set out by the Department of Environment, Land, Water and Planning in it’s duties as the Land Manager.

It is anticipated that legislation will be placed before parliament before the end of this calendar year that will transfer this obligation to the Kardinia Park Trust.

The Geelong Football Club at this stage has not fulfilled all its obligations under the conditions of Council’s contribution to Stage 3. The delivery of a Kardinia Park Master Plan remains outstanding. Discussions with the Kardinia Park Trust chair have indicated that it would be willing to fulfil this obligation.


Alignment to City Plan

Kardinia Park contributes to Council achieving objectives outlined in the City Plan 2013-17:


Officer Direct or Indirect Interest

No Council officers involved in the preparation of this report are known to have a direct or indirect interest in matters to which this report relates.


Risk Assessment

In providing consent for the development, Council exposes itself to a significant operational funding increase to maintain the $90M stand (based on the industry norm calculation of maintenance costs at 1% to 2% capital cost).This cost could amount to an obligation of up to $2M annually. This risk has been mitigated with the inclusion of the recommendation seeking that the Victorian Government accepting the Stand asset.


Social Considerations

Kardinia Park provides a range of social and health benefits through the provision of sport and recreation opportunities to the wider community. Kardinia Park and in particular Simonds Stadium, is a place of great value to the community due to its status as Geelong’s premier sporting precinct.


Human Rights Charter

This report has no impact on compliance with the Human Rights Charter.


Consultation and Communication

The Victorian State Government through Sports and Recreation Victoria, The Kardinia Park Trust and the Geelong Football Club have been consulted with in the formation of this report.


[Back to List]

7. City Plan 2013-2017 Progress Report to June 2015

Portfolio:

Governance - Cr Lyons (Mayor)

Source:

Strategy and Performance – Corporate Strategy

General Manager:

Dean Frost

Index Reference:

Corporate Strategy Planning


Purpose

Council at its meeting on 24 June 2014 adopted the 2014-2015 Update of City Plan 2013-2017, which outlines the Strategic Directions and Priorities planned by the Council over the four-year period, and the Annual Business Plan Actions planned for the coming 12 months.

This report is the progress report to Council of the organisations achievements against these actions.


Summary

Attachment A details the status and provides commentary against the Annual Business Plan actions. The key to the status of actions is:

On Schedule:

Green

69

Completed:

Black

123

Major Issue:

Red

5

Minor Issue:

Yellow

22

Not Started:

White

13

Total Actions

 

232


Cr Farrell moved, Cr E Kontelj seconded -

That Council receives and notes the City Plan Progress Report to 30 June, 2015.

Carried.


Background

Council at its meeting on 24 June 2014 adopted the 2014-2015 Update of City Plan 2013-2017 which outlines the Strategic Directions and Priorities planned by the Council over the four-year period, and the Annual Business Plan Actions planned for the coming 12 months.

Community Wellbeing

Healthy Together Geelong: to enhance health, wellbeing and quality of life of Greater Geelong Communities.

Growing Our Economy

Securing Geelong’s economic future.

A Sustainable Built and Natural Environment

Partnering with our community to protect and enhance our natural ecosystems and to encourage sustainable design and reduced resource consumption.

How We Do Business

We will focus on developing and maintaining effective working relationships to deliver Council’s strategic directions and cost effective services that meet the changing needs of the community.


Discussion

This report and attachment indicates the status of the actions in City Plan 2013-2017 for the 2014-2015 financial year as at 30 June, 2015.

The attachment provides status and comments for each of the 232 actions within the four strategic directions.

There has been significant progress in the June quarter towards achieving the actions in 2014-2015 including:

Community Wellbeing

Status Summary:

On Schedule:

30

 

Completed:

61

 

Major Issue:

3

Minor Issue:

10

 

Not Started:

6

 

 

 


Growing Our Economy

Status Summary:

On Schedule:

24

 

Completed:

23

 

Major Issue:

2

Minor Issue:

1

 

Not Started:

4

 

 

 

Sustainable Built and Natural Environment

Status Summary:

On Schedule:

9

 

Completed:

14

 

Major Issue:

0

Minor Issue:

8

 

Not Started:

2

 

 

 

How We Do Business

Status Summary:

On Schedule:

6

 

Completed:

25

 

Major Issue:

0

Minor Issue:

3

 

Not Started:

1

 

 

 


Environmental Implications

There are several actions under the Sustainable Built and Natural Environment Strategic Direction within City Plan that aim to enhance and protect natural areas and ecosystem health, support our community to live sustainably, advocate for and promote sustainable design and development, and minimise our environmental footprint.


Financial Implications

Council’s Annual Budget provides the Resource Plan to support the initiatives identified within the adopted Annual Business Plan.


Policy/Legal/Statutory Implications

Council’s external auditors will undertake a Performance Audit of the planned Key Strategic Activities and prepare a report as part of the ‘sign off’ of the Annual Accounts.


Alignment to City Plan

This report is the quarterly progress report of the organisation’s achievements against the adopted City Plan 2013-2017, 2014-2015 actions.


Officer Direct or Indirect Interest

There is no conflict of interest to be disclosed.


Risk Assessment

The risks arising from the actions are managed within the framework of the Council’s adopted Policies, Procedures and Risk Management strategies.


Social Considerations

Several of the actions identified within City Plan are aimed at improving the quality of life for the residents in the City of Greater Geelong. This is particularly the case for actions within the Community Wellbeing Strategic Direction.


Human Rights Charter

This report provides an update on the implementation of City Plan 2013-2017 and will be made available on Council’s website and on request at Council’s Customer Service Centres as part of the Council meeting minutes. There are no known positive or negative effects.


Consultation and Communication

A comprehensive report on the 2014-2015 City Plan actions will be published in the City of Greater Geelong Annual Report by September 30, 2015, which will be submitted to the Minister for Local Government and available to the public in hard copy and on the Council’s website (www.geelongaustralia.com.au).


[Back to List]

8. Annual Financial Report for the year ended 30 June 2015

Portfolio:

Finance - Cr Lyons (Mayor) Cr E Kontelj and Cr Farrell

Source:

Strategy and Performance - Financial Services

General Manager:

Dean Frost

Index Reference:

Financial Management - Reporting


Purpose

To authorise two Councillors to certify the 2015 Financial Statements and Performance Statement.


Summary

Cr E Kontelj moved, Cr Farrell seconded -

That Council:

  1. gives approval in principle to the “Financial Statement of Accounts” (as per Appendix 1) and the “Performance Statement” (as per Appendix 2); and

  2. authorise two Councillors being the Mayor, Cr D Lyons and Cr E. Kontelj to certify the Statements subject to any changes recommended and agreed with the Auditor General.

Carried.


Background

Under Section 131 of the Local Government Act 1989 (LGA), a Council must in respect of each financial year, prepare an Annual Report that includes audited Financial Statements and a Performance Statement for the financial year. These statements must be prepared in the prescribed manner and form and be certified by Council’s auditors. Council’s current auditors are Victorian Auditor Generals Office (VAGO).

Under section 131(4) of the Local Government Act, the Performance Statement must contain the prescribed indicators and measures of service performance outcome, financial performance and sustainable capacity.

In addition to the performance statement, council’s are also required to disclose:

Along with the Performance Statement indicators, these will also be required to be reported on the State Government ‘Know Your Council’ website.

The draft Financial Statements and Performance Statement have been reviewed by VAGO and there were no major issues of high risk indentified in the draft closing audit report. VAGO representatives attended the Audit Advisory meeting on 24 August 2015 to present and discuss the 2014-2015 Audit Management letter.

Under Section 132 of the LGA, Council is required to approve “in principle” the Statements prior to receiving final certification from the Auditor General. Council’s approval requires nominating two Councillors to certify those Statements together with Chief Executive Officer and Principal Accounting Officer.

The Final Statements may then be subject to any changes recommended and agreed with VAGO. A final audit certification is then issued.

The Financial Statements and the Performance Statement form part of Council’s Annual Report that must be submitted to the Minister within three months of the end of the financial year. Further, Council must also review the Annual Report in a meeting open to the public as soon as possible after the report is sent to the Minister.


Discussions

The Financial Statement of Accounts 2014-2015 record a satisfactory period of operation with a favourable operating surplus, high closing cash balances and significant asset growth.

COMPREHENSIVE INCOME STATEMENT

The surplus result for 2014-2015 of $76.3M is

$M’s

• 

Early receipt of 2015-2016 Grants Commission entitlement

9.7

• 

Non capital projects unspent amount

7.9

• 

Net Income/expenses

(1.6)

Recurrent Surplus

16.0

• 

Capital Grants Income/ Dev. Cap 26.9

• 

Recognition of Infrastructure less Disposals 33.4

 

Non Recurrent Surplus

60.3

   

SURPLUS/(DEFICIT) FOR THE YEAR

76.3

Net Asset revaluation decrement

(2.6)

TOTAL COMPREHENSIVE RESULT

73.7


This surplus result was $2.7M favourable to adopted Budget and included the following favourable and unfavourable Income and expenditure items (refer Note 2A Appendix 1)

Income of $369.1M was $3.1M favourable to budget mainly due to:

Offset by the following items:

Expenditure of $292.8M was $0.4M unfavourable to budget due to:

Offset by the following items:

BALANCE SHEET

The Balance Sheet shows that Council has a very strong asset position with over $2.1 billion worth of assets that are used to provide services to the community.

Current Assets are $104M which is predominately due to an increase in cash balances due to loans being drawn down and lower than budget capital spend.

Current liabilities have remained at $61M but non current liabilities have increases to $73.9M due to the drawing down of $37.6M in loans during 2014-2015 (total loan balance has increased to $64.5M).

STATEMENT OF CASH FLOWS

Council’s cash position at the end of the year is $91.9M, an increase of $16.6M from the prior year. This is due to:

The cash balance will provide funds to complete Capital and Non Capital projects carried over from 2014-2015 and working capital to ensure service provision continues at the same levels in 2015-2016.


STATEMENT OF CAPITAL WORKS

Council has an extensive capital works program to renew, upgrade and provide new assets to ensure the continuation and improvement of services provided to the community. Council spent $106.7M on capital works in 2014-2015 and included the following highlights:

 

 

$M

• 

Geelong Library and Heritage Centre

24.1

• 

Road replacement and construction

18.2

• 

Leopold Community Hub

5.9

• 

Grovedale Integrated Children’s Centre

4.6

• 

Plant and Vehicles

3.7

• 

Drysdale Landfill Cell 6

3.6

• 

Windsor Park Children and Family Hub

3.5

• 

Barwon Heads Kindergarten

2.8

• 

Footpath replacement and construction

2.7

• 

Drainage replacement and construction

2.7

• 

Corio Landfill Rehabilitation

2.5

• 

Shell Road Reserve Masterplan

2.2

• 

Kerb and Channel replacement and construction

1.6

• 

Drysdale Landfill Cell 4a

1.5

• 

Ocean Grove Neighbourhood House Upgrade

1.4

• 

Austin Park Redevelopment

1.1

• 

Parking Machines Upgrade

0.9

• 

Building Renewal Works

0.9

• 

IT Asset Replacements

0.6

• 

Purchase of Gym Equipment

0.6

• 

Windsor Park Land Purchase

0.6

• 

Bellarine Rail Trail Pathway Improvements

0.6

• 

Playground Development Program

0.5


AUDIT

The external audit, conducted by the Victorian Auditor Generals Office (VAGO), was completed on Friday 7 August as per the audit plan. There were no major issues affecting the Financial Statements. A closing report summarising the Audit findings has been reviewed by the Audit Advisory Committee.


Environmental Implications

Incomes and Expenditures on Council’s environmental preservation and enhancement programs are included in the Financial Statements.


Financial Implications

As detailed within accompanying financial statements – refer Appendix 1.


Policy/Legal/Statutory Implications

Under Section 131 of the Local Government Act the Council must in respect of each year prepare an Annual Report, which includes audited financial statements for the financial year.

Under Section 131 a Council must not submit the Financial Statements to its auditors or the Minister unless it has passed a resolution giving approval “in Principle” to the statements.

Under Section 131 a Council must authorise two Councillors to certify the Statements in their final form after any changes recommended, or agreed to with the auditor.

The actions outlined in this report are aimed at complying with the requirements of the Act.


Alignment to City Plan

The Financial statements and the Performance Statement highlight that 2014-2015 Council operations have been managed in a responsible manner. The results contribute to responsible and sustainable financial management as aligned in Council’s City Plan objective on the How We Do Business.


Officer Direct or Indirect Interest

Council staff preparing this report have no direct or indirect interest.


Risk Assessment

The Statements are released as a draft and are still subject to being signed off by the Auditor General.


Social Considerations

The attached report represents a full and open disclosure of the financial position for the benefit of the community.


Human Rights Charter

There are no known positive or negative effects.


Consultation and Communication

The Financial Statement of Accounts and the Performance Statement will be available to the public as part of the published Annual report and accessible via www.geelongaustralia.com.au.

The prescribed indicators and measures of service performance outcome, financial performance and sustainable capacity as per section 131(3) and 131(4) of the Local Government Act 1989 will also be available on the State Government ‘Know Your Council’ website from November 2015.


[Back to List]

9. 2015-2016 Budget Amendments

Portfolio:

Finance - Cr Lyons (Mayor) Cr E Kontelj and Cr Farrell

Source:

Strategy and Performance - Financial Services

General Manager:

Dean Frost

Index Reference:

Financial Management / Reporting


Purpose

Amend the 2015-2016 Budget that was adopted on 23 June 2015.


Summary

Cr E Kontelj moved, Cr Farrell seconded

That Council amends the adopted 2015-2016 Budget to include the following:

  1. Capital Programs carryover as per Appendix 1, other budget amendments affecting Capital Projects Budget as per Table 1;

  2. Non Capital Programs carryover as per Appendix 2, other budget amendments affecting the recurrent Budget as per Table 2;

  3. Deferred 2014-2015 Land Sales affecting the non-recurrent Surplus as per Table 3.

Carried.


Background

At 30 June each year Council reviews the preliminary financial results to determine funded Capital and Non Capital programs that are incomplete and are required to be carried over into the subsequent financial year. These carryover requirements are recommended to be incorporated as amendments to the adopted budget. This practice avoids unnecessary variance reporting, given there is no impact on the budgeted closing cash position.

The review has been undertaken in the following key areas:

  1. Carryover requirements to complete 2014-2015 Capital projects in 2015-2016.

  2. Carryover requirements to complete 2014-2015 Non Capital projects in 2015-2016.

  3. Other budget amendments requested or influenced by year end accounting matters.

2014-2015 Preliminary Financial Results Summary

 

Full Year Actual
$M

Full Year Amended Budget
$M

Variance Fav / (Unfav)
$M

Recurrent Surplus/(Deficit)

15.97

(6.87)

22.84

Non-Recurrent Surplus/(Deficit)

60.36

74.15

(13.79)

Net Surplus/(Deficit)

76.33

67.28

9.15

Capital Expenditure

106.73

139.71

32.98

Closing Net Cash Positive/(Negative)

91.92

58.86

33.06


Discussion

Capital Projects Budget Amendments

Carryover requirements

Of the 268 projects listed in 2014-2015, project managers have advised that 112 projects have been fully completed, with 156 projects identified as requiring some carryover funds in 2015-2016 to complete works.

During the 2015-2016 Budget development the Capital carryover was projected to be $28M. At the end of the 2014-2015 financial year a review was carried out to determine the actual Capital Program carryover requirements. The review indicates a net carryover of $47.41M (refer to Appendix 1 for details) comprising of $52.27M expenditure and $4.86M income is required to complete the projects planned for 2014-2015, The net variance between actual Net ($47.41M) and estimate included in 2015-2016 Budget ($28.00M) is $19.41M.

Main increases are: – Higher carryover than estimated on Corio Landfill Rehabilitation $1.27M, Geelong Library and Heritage Centre Car Park $0.51M, Central Geelong Advancement Fund $0.50M and Home for Cycling Pavilion $0.39M. Other incomplete projects – Drainage Construction $1.88M, Central Road Drainage $1.63M, Geelong Library and Heritage Centre $1.53M, Street Construction SRC $1.21M, Austin Park Redevelopment $1.20M, Heavy and Dedicated Plant Replacement $1.19M,

Myers St Unifying Streetscape Works $0.92M, Shell Rd Reserve Masterplan $0.70M, PABX Replacement $0.54M and Clifton Springs Boat Harbour $0.52M.

Other Capital Program amendments:

Table 1 – Amended 2015-2016 Capital Program

Council adopted the 2015-2016 Budget on 23 June 2015 that included a gross Capital Projects Program of $84.87M with Capital Income of $21.53M – Net $63.34M.

The net 2015-2016 Capital Program is recommended for amendment to $92.88M to reflect the additional $47.41M carried over from 2014-2015 plus other Budget amendments as indicated in Table 1 below.

 

Expenditure
$M

Income
$M

Net Expenditure
$M

Council adopted 2015-2016 Budget - New Capital Funding (excluding Carryover)

84,873,105

21,533,027

63,340,078

2014-2015 Capital Carryover Requests

52,268,914

4,863,209

47,405,705

Other Budget Amendments:

 

 

 

Budget Submission – Osborne House

30,000

0

30,000

Budget Submission – Geelong Cycling Strategy

100,000

0

100,000

Vic Roads Funded Works

743,000

743,000

-

Adjusted 2015-2015 Capital Program

138,015,019

27,139,236

110,875,783

Planned Carryover into 2016-2017 (June 2016)

(18,000,000)

-

(18,000,000)

Amended 2015-2016 Capital Program

120,015,019

27,139,236

92,875,783

 

Operating Budget Amendments

Non Capital Projects Carryover requirements

In addition to the Capital Program, Project Managers have undertaken a review of the Non Capital Projects budgeted for in 2014-2015 that have been requested to be carried over into the 2015-2016 financial year.

The 2014-2015 Recurrent Operating result was favourably impacted by $7.90M of incomplete Non Capital programs as per Appendix 2.

Requested Discretionary Program Carryover:

 

$

Expenditure

8,196,199

Income

298,337

Net Expenditure

7,897,862


Other Operating Budget amendments:

The impact of the requested Discretionary Program Carryover, along with the other Budget amendments that affect the recurrent position, is on the 2015-2016 recurrent surplus / (deficit) (Refer Table 2 below).

Table 2 – Amended 2015-2016 Recurrent Surplus / (Deficit)

 

Expenditure $

Income $

Surplus / (Deficit) $

Council adopted 2015-2016 Budget - Recurrent Surplus / (Deficit)

307,912,756

308,661,167

748,411

2014-2015 Discretionary Carryover Requests

8,196,199

298,337

(7,897,862)

Other Budget Amendments

238,212

(9,626,816)

(9,865,028

Amended 2015-2016 Recurrent Surplus / (Deficit)

316,347,167

299,332,688

(17,014,479)


Non-Recurrent Budget Amendments

A number of Land Sales budgeted in 2014-2015 did not eventuate in the past financial year, but are projected to occur in 2015-2016, therefore it is recommended that the 2015-2016 budget be amended to include these sales.

Properties are as follows:

  1. 400 Melbourne Rd, North Geelong

  2. 1-39 Rollins Rd, Bell Post Hill

  3. 18 Wilkins Close, Corio

  4. 128-130 Asbury St, Ocean Grove

  5. GREP – Lot 1 Production Way

  6. GREP – Lot 5 Success Court

  7. GREP – Lot 7 Success Court

  8. GREP –South O’Briens Rd Stage 1

Total expected Sales value is $8,217,600 with Written Down Value of $3,484,000 giving net Gain/(Loss) on sale of $4,733,600.

The impact of the requested Land Sales amendments is on the 2015-2016 Non- recurrent surplus / (deficit) (Refer Table 3 below).

Table 3 – Amended 2015-2016 Non-Recurrent Surplus / (Deficit)

 

Expenditure $

Income $

Surplus / (Deficit) $

Council adopted 2015-2016 Budget - Non-Recurrent Surplus / (Deficit)

5,290,000

60,721,894

55,431,894

Land Sales Amendments – Gain/(Loss)

0

4,733,600

4,733,600

Capital Income Carryover

0

4,863,209

4,863,209

Amended 2015-2016 Non-Recurrent Surplus / (Deficit)

5,290,000

70,318,703

65,028,703



Environmental Implications

The adoption of the 2014-2015 carryover program provides the required funding to complete the environmental programs previously approved as part of the 2014-2015 Budget.


Financial Implications

There are no funding implications associated with this report, with higher than projected cash balances as at 30 June 2015 funding additional budgeted expenditure in 2015-2016.

The program variances and carryover requests are detailed within the accompanying financial reports (refer Appendices 1 and 2).


Policy/Legal/Statutory Implications

Section 144A part 1 of the Local Government Act states “A Council must prepare a revised budget if circumstances arise which cause a material change in the budget and which affect the financial operations and position of Council.”

In the context of the total budget the recommended variation to the budget is not considered material.


Alignment to City Plan

This amended budget report contributes to responsible and sustainable financial management as aligned in Council’s City Plan objective on How We Do Business.


Officer Direct or Indirect Interest

Council staff preparing this report have no direct or indirect interest.


Risk Assessment

Capital projects by their nature are susceptible to delays for a large variety of reasons including weather, delays in approvals (i.e. Special Rates and Charges programs) contractor availability, performance, etc.

The carryover Capital Program (refer to Appendix 1) if approved, will result in a gross capital program for 2015-2016 of $120.02M.


Social Considerations

The adoption of the 2014-2015 carryover program provides the required funding to complete the social programs previously approved as part of the 2014-2015 Budget.


Human Rights Charter

No Human Rights are affected by this report.


Consultation and Communication

Project Managers have submitted requests for carryover and will be advised of the outcome pending consideration of this report by Council.


[Back to List]

10. Local Government Rates Capping and Variation Framework Review July 2015

Portfolio:

Finance - Cr Lyons (Mayor), Cr E Kontelj and Cr Farrell

Source:

Strategy and Performance - Financial Services

General Manager:

Dean Frost

Index Reference:

Financial Management / Reporting


Purpose

To provide Councillors with an overview of the proposed rates capping and variation framework in order for Council to submit a written submission by 28 August 2015.


Summary

Cr Farrell moved, Cr E Kontelj seconded -

That Council, in response to the release of the draft report – Local Government Rates Capping and Variation framework review July 2015, supports making a submission to the Essential Services Commission regarding each recommendation contained in the framework, along the lines of this report.

Cr Nelson left the meeting room at 9:02pm

Carried.


Background

In January 2015 terms of reference were received by the Essential Services Commission (ESC) from the Minister of Finance and Local Government to conduct a review and report on local government rate capping. The Commission was asked to design a ‘framework’ to meet the Government’s commitment to cap annual rate increases as well as to develop a workable process to assess proposals from councils for above cap increases (‘variation process’).

In April 2015 a consultation paper was released identifying a set of eight (8) principles which received widespread support and these principles were used as the basis for the development of the proposed ‘framework’.

A draft report outlining the proposed ‘framework’ (Volume I and 2) was released on 31 July 2015 with Council having until 28 August 2015 to respond to the proposed ‘framework’.

The proposed ‘framework’ is designed to provide confidence to ratepayers and the broader community in regard to the decision-making process used to determine council rates. The proposed ‘framework’ has three elements:

The report outlines eleven draft recommendations designed to assist in implementing each element of the framework.


Discussions

The draft recommendations are broken into three categories, The Cap, Variation and Monitoring. Commentary has been provided on each recommendation along with identified issues which should be covered in Council’s submission.

Element 1: The Cap

Recommendation 1:

The Commission recommends that there should be one rate cap that applies equally to all councils in Victoria

This recommendation is supported as a fair approach with the one rate cap to apply equally to all Victorian councils. Having different caps for either Country, Regional or Metropolitan councils could be seen as inequitable.

Recommendation 2:

The Commission recommends that:

This recommendation is supported with the rightful exclusion of Service charges, Special rates and the State Government Fire Services Levy.

Recommendation 3:

The Commission recommends that the cap should be applied to rates and charges paid by the average ratepayer. This is calculated by dividing a council’s total revenue required from rates in a given year by the number of rateable properties in that council area at the start of the rate year.

This recommendation is supported. Currently rate increases are reported in terms of the average increase on residential properties.

For 2015-2016 this was 4.45% and using total average rates for all differentials as proposed the average increase would be 3.82%. The difference is due to the decreases in the petroleum, automobile and aluminium capital improved values.

Recommendation 4:

The Commission recommends that the annual rate cap should be calculated as:

Annual Rate Cap

= (0.6 x increase in Consumer Price Index)

 

+ (0.4 x increase in Wage Price Index)

 

- Efficiency factor

With CPI = Department of Treasury and Finance (DTF)forecast published in December each year

WPI = DTF’s forecast published in December each year

The efficiency factor will initially be set at zero in 2016-17 but increasing by 0.05 percentage points each year from 2017-18. The Commission will undertake a detailed productivity analysis of the sector to assess the appropriate long-term rate for the efficiency factor.

This recommendation to include CPI and WPI is supported as it takes into account the high proportion of employee costs in Councils operating cost base. Other cost factors have not been included in the cap, for example the costs of materials of construction or the broader range of costs indentified in the MAV Local Government cost index.

The inclusion of an efficiency factor is not supported. The criteria for assessing variation requests includes efficiency factors such as good value-for-money. The variation request would demonstrate council has considered the budgeting need, service priorities and funding options. Applying a further efficiency factor as proposed is an arbitrary approach to apply a task on councils that is not realistic.

Indicative forecast for the cap is 3.05% to apply from 2016-2017:

 

2016-17

2017-18

2018-19

Underlying CPI forecast (60 per cent weighting)

2.75

2.50

2.50

PLUS

 

 

 

WPI forecast (40 per cent weighting)

3.50

3.50

3.50

LESS

 

 

 

Efficiency factor

 

0.05

0.10

FORECAST ANNUAL RATE CAP

3.05

2.85

2.80


This indicative forecast highlights a funding gap in Councils Strategic Resource Plan assumption of 3.5% for rates and 3% for municipal charge. This is equivalent to ($0.7m) 2016-2017, ($1.8m) 2017-2018, and ($3.1m) 2018-2019. Therefore, Council is likely to lodge a variation request for 2016-2017 and also the following year for the two years 2017 to 2019 based on forward commitments.

Recommendation 5:

The Commission recommends that the 2015-16 rates (general rates and municipal charges) levied on an average property should be adopted as the starting base for 2016-17

This recommendation is supported to define the base year for setting the cap as actual rates levied.

Element 2: Variation

Recommendation 6:

The Commission recommends that the framework should not specify individual events that would qualify for a variation. The discretion to apply for a variation should remain with councils.

This recommendation is supported as it enables council to apply for a variation without having to prequalify based on any prescriptive criteria.

Recommendation 7:

The Commission recommends that the following five matters be addressed in each application for a variation –

This recommendation is supported however the process requires more detail and the following points would be included in the submission.

  1. There is no difference in process when applying for a minor variation to the rate cap (up to 0.5%) compared to a major variation to the rate cap increase. A tiered approach to recognise minor and major variations above the cap, which then determines the application requirements would be more appropriate.

  2. There is no appeal process if a rate cap variation is not approved, nor can approval be given for a lower increase. It is proposed that the ESC is not given the power to substitute an alternative rate increase to the one proposed. An appeal process based on certain grounds is considered necessary.

  3. It is considered that a scoring or weighting system needs to apply to the five criteria to provide transparency in the assessment process. A simple acceptance or rejection of the application is not considered sufficient given the implications on Councils communication with ratepayers as part of the budget process.

  4. It is unclear when councils will receive advice re. approval or refusal of a variation application. The proposed timeline does not adequately take into account Councils budget process and rate notice process and changes are necessary.

Recommendation 8:

The Commission recommends that in 2016-17, variations for only one year be permitted. Thereafter, councils should be permitted to submit and the Commission approve, variations of the length set out below.

First Year of Variation

Length of Permissible Variation

2016-17

one year (ie 2016-17 only)

2017-18

up to two years (ie 2017-18 only or 2017-18 and 2018-19)

2018-19

up to three years (ie up to 30 June 2021)

2019-20 and beyond

up to four years (ie up to 30 June 2023)


This recommendation for 2016-2017 is supported, however variation requests from 2017-2018 should be up to four years.

The 2017-2018 year will be the first year of the Council Plan where a four year Strategic Resource plan will be developed. Therefore the 2017-2018 year should provide for a variation request up to four years in order to deliver on the Council Plan commitments.

The existing assumptions included in the 2015-2016 Strategic Resource Plan should be considered relevant and be accepted as prima facie grounds for lodging a variation request for 2016-2017. The 2015-2016 budget and Strategic Resource plan recognised the commencement of rate capping in 2016-2017 with future planned rate increases reduced to a necessary 3.5%. This plan should be recognised by ESC as justification when there are minor variations to the rate cap.

The draft report mentions a detailed productivity analysis of the sector to assess the appropriate long-term rate for the efficiency factor. There is no mention of when this may occur. (Vol 2, page 52).

Recommendation 9:

The Commission recommends that it should be the decision-maker under the framework, but only be empowered to accept or reject (and not to vary) an application for variation.

This recommendation does not provide for any basis for appeal and does not require ESC to outline the reasons for acceptance or rejection of the variation request.

A right of appeal through the Local Government Minister should be incorporated in the framework outlining specific grounds for appeal. Whilst an appeal process may create timing implications for the budget process it is appropriate in a Local Government context.

When considering an application for a variation, the ESC, will like any decision maker, be constrained by Administrative law principals. A failure to give real and proper consideration to a councils application will risk any decision being legally vulnerable. Providing an appeal process through the Minister could minimise this risk.

A tiered variation process with increasing levels of scrutiny was suggested by many submitters in May 2015. (Vol 2, page 177). It is considered that a scoring or weighting system needs to apply to the five criteria to provide transparency in the assessment process. The communication of a score by the ESC on each criteria would allow councils to know where improvements need to be made for future variation applications.

Element 3: Monitoring

Recommendation 10:

The Commission recommends that it monitor and publish an annual report on council’s adherence to the cap and any approved variation conditions.

This recommendation is supported as it may provide an insight into what types of variations are approved and rejected. The ESC will publish reports detailing the outcome of each application for a variation above the rate cap (approval or refusal) (Vol 1, page 34). However each councils variation application needs to be published as part of the Commissions report to enable all councils to compare applications to outcomes.

Clarification is required as to when the report will be published but this should be May each year.

Recommendation 11:

The Commission recommends that it monitor and publish an annual monitoring report on the overall outcomes for ratepayers and communities.

This recommendation is supported as indicative of a transparent process.

2016-2017 Implementation timetable of Rate Capping

The proposed timeline is considered inappropriate and fails to take into account Councils budget process and rate setting timetable.

ESC Timeline

2015-16

ESC announces cap

December 2015

All Councils submit baseline data (budget)

January 2016

Councils notify ESC intention to seek variation

January 2016

Council applies for variation, submits baseline data (budget

March 2016

ESC assesses council variation applications

March-May 2016

ESC notifies councils of decisions

May 2016

Councils consult on draft budget

May 2016

Councils formally adopt budget

June 2016


The following amended timetable takes into account the budget process.

Councils to notify ESC and submit variation requests by 31 January. ESC assesses council variation requests and advises outcome by 1 April to enable the budget process to be completed by the end of June each year.

Greater Geelong City Council Suggested Timeline

2015-16

ESC announces cap

December 2015

All Councils submit baseline data (budget)

January 2016

Councils notify ESC intention to seek variation and Council applies for variation

31 January 2016

ESC assesses council variation applications

1February- 31 March 2016

ESC notifies councils of decisions

1 April 2016

Councils consult on draft budget

May 2016

Councils formally adopt budget

June 2016


Delaying the adoption of the budget will impact on the issuing on the annual rate notice in July/August each year.

Other comments

  1. ESC should expect that in the first year most councils will lodge a variation request in response to assumptions made in the Strategic Resource plan.

  2. Both Volumes say ‘we do not expect a large number of applications each year’ (Vol 2, page 78)

    The report discusses the costs of administering the framework. It mentions an application fee for considering variation applications, but this has not been substantiated at this time. The fee is aimed to recover ESC costs and could be a fixed, variable or a combination of both (Vol 1, page 39). Further guidance must be provided as to what fee Councils can expect when lodging a variation.

    The majority of submissions lodged in May 2015 were of the view that the State Government should bear the costs of administering the framework (Vol , page 202).

    Council will incur costs in preparing variation applications such as additional staff resources, external expertise (if required) and additional community consultation if our current engagement program is considered lacking. Therefore it is reasonable that either party should bear their own costs.

  3. The ESC propose to consider submissions from the public on variation applications (Vol 2 page 79). There are already processes in place for interested parties to comment on the annual budget process to councils directly.

    The above comments will be contained in councils submission. Other comments may need to be made within the submission as further details arise. A copy of the submission will be distributed to each Councillor.


Environmental Implications

There are no environmental implications associated with this report.


Financial Implications

The indicative cap included in the draft framework highlights a funding gap between Councils Strategic Resource Plan assumption and the cap rate increase. This imposes reduced revenue target in developing the budgets for 2016-2017 of ($0.7m), 2017-2018 of ($1.8m) and 2018-2019 of ($3.1m). The combined shortfall of ($5.6m) over 3 years will require redistribution of resources through the 2016-2017 budget or preparation for variation requests through ESC.

The report mentions an application fee for considering variation applications, but this has not been substantiated at this time. The fee is aimed to recover ESC costs and could be a fixed, variable or a combination of both.

There will be additional staff resources required to prepare detailed variation requests to provide best possible opportunity of gaining approval.


Policy/Legal/Statutory Implications

Section 185b of the Local Government Act 1989 provides the Minister for Local Government the ability to cap council general income. The Government has announced a commitment to cap annual rate increases.


Alignment to City Plan

This report contributes to responsible and sustainable financial management as aligned in Council’s City Plan objective on How We Do Business.


Officer Direct or Indirect Interest

No Council officers involved in the preparation of this report have a direct or indirect interest in any matter to which this report relates.


Risk Assessment

Council has a statutory obligation to adopt the annual budget by 30 June each year. The rate capping framework must minimise risks for councils of creating uncertainty in development of the annual budget and strategic resource plan.


Social Considerations

The rate capping framework is designed to create a Fairer Rating system to honour a Labour party Election commitment. There may be an impact on provision of council services to ratepayers as a consequence of resource redistribution.


Human Rights Charter

There are no known positive or negative effects.


Consultation and Communication

The ESC has released ‘A Blueprint for Change, Local Government Rates Capping and Variation Framework Review – Draft Report Volume 1 and 2, July 2015’ on 31 July 2015.

Interested parties have been invited to comment on the above paper by providing a written submission by 28 August 2015. Council intends to provide a submission by the due date.

All submissions will be publicly available on www.esc.vic.gov.au

Public information sessions are being held in Melbourne and regional Victoria from 10 August 2015 to 26 August 2015.

The final report from the ESC to the Minister for Local Government and the Minister for Finance is due at the end of September – following this; the report will be released publicly.


[Back to List]

11. Digital Geelong Implementation Plan

Portfolio:

Knowledge Economy - Cr Macdonald

Source:

Strategy and Performance – Information Services

General Manager:

Dean Frost

Index Reference:

Subject – Information Services Strategies


Purpose

To seek Council endorsement for the Digital Geelong Strategy Implementation Plan.


Summary

Cr Macdonald moved, Cr Richards seconded -

That Council:

  1. note the Digital Geelong Strategy Implementation Plan (Appendix 1);

  2. acknowledge the plan will be reviewed annually.

Cr Nelson re-entered the meeting room at 9:08pm.

Carried.


Background

Digital Geelong was commissioned to ensure that the City of Greater Geelong is at the forefront in engaging with and serving its community and businesses, in whatever medium they wish to use

A key aim is to maximise the efficiencies and benefits available from digital technologies, at a time of pressure on public finances, to deliver even more value for money and impact to Geelong by placing the city as a nationally recognised leader within the digital economy

Driven by internet-enabled convergence, the strategy and this subsequent implementation plan, deals with:


Discussions

The Digital Geelong strategy implementation plan has identified 63 projects or actions across the 30 recommendations.

As Digital Geelong covers both a broad cross section of Council business and also emerging concepts, there is crossover in projects delivered in other Council strategies. Some of these are existing or being revisited currently.

An example of this is the myGeelong projects to digitally enable and transform Council’s own service delivery. This project is also part of the Customer Service strategy.

Consequently a number of these projects are already underway, or in fact will be projects that run over multiple years of the plan. Projects can have an impact on multiple recommendations. There 38 identified projects that impact the Internal CoGG Focus recommendations of the strategy; 18 that impact the Community Focus recommendations; and 17 that impact the Business Focus recommendations.

The plan identifies the wide range of partners required to be engaged and involved in the delivery of the implementation plan. These include:

A cross functional team lead by Councils Information Services, has been established to oversee the implementation plan.

What also needs to be acknowledged is the rapid pace of change digital disruption is causing to all industries and communities. Consequently this action plan will require annual review.


Environmental Implications

The projects in the Digital Geelong strategy implementation plan are considered to have impacts in respect to some of the environmental challenges facing the region, through reductions in consumption of various resources that are offset through the adoption of digital initiatives in the local and global context.


Financial Implications

Digital Geelong is a significant undertaking for the Council and it is important that funding is identified to carry out the implementation plan. However, recognising existing or future projects that will be delivered from current resources is fundamental, so as to understand the future return on investment of the strategy.

All costs shown in the plan are estimated and also identifies existing or in-kind resources.

Even though funds are identified it does not assume ratification of Council and Projects/Initiatives will be required to go through the normal budget process.

Projects delivered through the Geelong Regional Library Corporation (GRLC), as a significant partner in the Community Focus area, are represented in the plan. The GRLC has an existing digital strategy with separate costs not included in the financial component of the implementation plan.

15/16 - Existing - In Kind Funds / New Funds

$ 612,500

$ 325,000

16/17 - Existing - In Kind Funds / New Funds

$ 190,000

$ 455,000

17/18 - Existing - In Kind Funds / New Funds

$ 110,000

$ 315,000

 

 

 

TOTAL EXISTING

$ 912,500

 

TOTAL NEW

$ 1,095,000

 

TOTAL COST

$ 2,007,500

 



Policy/Legal/Statutory Implications

There are no known direct policy, legal or statutory implications, however each project will review these components as part of the delivery requirements.


Alignment to City Plan

This report aligns to ‘The Growing the Economy’ and ‘How we do business’ planning framework of our City Plan.


Officer Direct or Indirect Interest

No officer involved in the preparation of this report has declared a direct or indirect conflict of interest in this report.


Risk Assessment

There are no notable risks associated with accepting the recommendation in this report. Each project will review the risk elements as part of the delivery requirements.


Social Considerations

There is a growing body of evidence that shows the importance of and direct correlation between digital inclusion and better social and civic engagement, improved quality of life and higher educational achievement.

Digital inclusion also enhances the ability to participate in the workforce and benefit from economic development opportunities. Such digital inclusion is not just a matter of equity or democratic renewal. The really transformational impact for Geelong’s public services – for cost reduction and service efficiency – will come when the largest proportion possible in a local government area is able to engage and transact online.


Human Rights Charter

This report has no direct impact on the human rights of the residents of the City of Greater Geelong.


Consultation and Communication

Significant consultation was conducted throughout the development of the Digital Geelong strategy and the development of the implementation plan.

This was achieved through a series of workshops and individual meetings with delivery stakeholders identified with responsibility in the body of the plan.


[Back to List]

12. Chief Executive Officer Recruitment

Portfolio:

Governance, Cr Lyons (Mayor)

Source:

Strategy and Performance - Organisation Development

General Manager:

Dean Frost

Index Reference:

Subject: Organisation Development


Purpose

The purpose of this report is for Council to appoint the Executive Recruitment Agency to conduct the recruitment of a new Chief Executive Officer.


Summary

Cr Harwood moved, Cr Richards seconded -

That in exercise of the powers conferred by sections 86 and 87 of the Local Government Act 1989 ("the Act"), Council resolves that McArthur be appointed to conduct the Chief Executive Officer recruitment for the City of Greater Geelong.

Carried.


Background

A recruitment process for a new Chief Executive Officer was initiated following the resignation of the former CEO, Dr Gillian Miles.

This report addresses the appointment of an Executive Recruitment Agency to assist Council.


Discussion

It is proposed that an Executive Recruitment Agency be appointed to conduct the advertising, search, assessment, shortlist, and interview process on behalf of Council.

The appointed agency will work with the selection committee in accordance with the Terms of Reference for the Selection Committee - Chief Executive. The Committee will report back to the Council at appropriate intervals during the recruitment process to advise the Council on progress.


Environmental Implications

There are no environmental implications associated with this report.


Financial Implications

Anticipated costs for the recruitment process including consultancy, advertising and other costs are estimated to be in the order of $40,000 to $60,000. These costs will be reported as projection changes in 2015-2016 financial management reports.


Policy/Legal/Statutory Implications

There are some specific requirements in the Local Government Act relative to the appointment of a Chief Executive.

While the appointment is to be made by the Council, a Committee may be appointed in accordance with section 86 and 87 of the Local Government Act 1989 with delegated powers to undertake designated steps in the recruitment process.


Alignment to City Plan

The Manager Organisation Development, and the selected Recruitment Consultant, will ensure the recruitment brief reflects the strategic initiatives of the City Plan.


Officer Direct or Indirect Interest

There is no officer direct or indirect conflict of interest.


Risk Assessment

A professional approach to the recruitment will minimise risk. It is important that attendance at meetings of the Committee be consistent. Unless committee members can attend all interviews they should not participate in interviews at all.


Social Considerations

There are no known social considerations.


Human Rights Charter

Human Rights Charter has been considered and no impacts have been identified.


Consultation and Communication

At the appropriate time the vacancy will be publicly advertised. It is imperative that information regarding candidates remain strictly confidential throughout the process.


[Back to List]

Contents | Previous Page: Section A - Procedural Matters | Next Page: Section C - Assembly of Councillors