  1. Lara Flood Study – Status Update

  2. Lara Traffic Study Update

  3. Geelong Waterfront Safe Harbour Precinct – Master Plan

  4. Councillor Appointment to Tourism Greater Geelong and The Bellarine Inc Committee

  5. Planning Authorisations – Council to Staff



1. Lara Flood Study – Status Update

Source:

Infrastructure Planning, City Services

Director:

Guy Wilson-Browne

Portfolio:

Social and Infrastructure Planning


Purpose

  1. To provide an update on the status of the Lara Flood Study and outline the upcoming project activities.

Background

  1. In May 2018, the City of Greater Geelong (City) in partnership with Corangamite Catchment Management Authority (CCMA) and the Department of Environment Land Water and Planning (DELWP) formed a Project Steering Committee (PSC) which commenced a detailed flood study for the Hovells Creek and Avalon Road Catchments. The study, which was identified as a key regional priority in the CCMA Floodplain Management Strategy, will help authorities to better understand the flood risks in and around Lara, leading to improved land use planning, better emergency planning, response, and community preparation and is expected to be completed in late 2019.

  2. To produce updated and detailed flood mapping within the study area, the City has carried out additional surveys to ensure the latest land use changes and the main drainage details are included in the study model. The surveys included:

    1. Floor surveys of approximately 840 properties in October 2018.

    2. CCTV surveys of 4 main drain alignments (approximately 5 km) in December 2018.

    3. A photogrammetry (the science of making measurements from photographs) survey was also completed for the central Lara area (15 square kilometres) in January 2018.


Key Matters

  1. Further community engagement sessions are scheduled on 28 March and 9 May 2019. The community are encouraged to review the development of new flood mapping at these sessions and at any stage of the project via the “Have Your Say” website. No flood mitigation options will be presented at the community engagement sessions.

  2. A hydraulic and hydrology calibration report was prepared for the PSC. The four historical flood events calibrated as part of the report were February 1973, December 1988, February 2005 and April 2017. The presentation of the findings were made to the PSC on 26 February 2019.

  3. Further PSC meetings will be held upon submission of reports on model design and mapping, flood intelligence outputs, flood affected properties, flood emergency plan, flood warning assessment, flood mitigation options and land use planning. Refer Attachment 2 for project milestones.

  4. It is expected that the final report of this study will be released for public comment during September 2019 and presented at the Ordinary Council Meeting on 26 November 2019.

Councillor Aitken moved, Councillor Grzybek seconded -

  1. That Council:

    1. Notes the progress of the project and the upcoming Community Consultation sessions on 28 March and 9 May 2019; and

    2. Considers the final Lara Flood Study at its meeting 26 November 2019.

Carried.


Attachment 1

Financial Implications

  1. DELWP is the primary funding body for this project with a total of $407,000 funding committed over two financial years 2018-19 and 2019-20. The City’s Engineering Services Team is leading the project delivery with support and advice being provided by the City Development unit.

  2. The study is expected to deliver flood mitigation recommendations including capital works which will be subject to future budget bids.

  3. Current capital flood mitigation planning in the subject site (e.g. McClelland Ave and Kyema Ave drainage upgrade project proposals) has been considered and these options will be tested against the study findings.


Community Engagement

  1. Project officers from the Infrastructure Planning Unit, assisted by the consultant, met the residents from Kyema Drive on site on 9 August 2018 to seek information about their knowledge and experiences of flooding.

  2. Three Community Consultation Drop-In Sessions were held at Lara RSL on 11 September 2018. These sessions have raised awareness of the study and provided opportunities for community input through the collection of photographs and sharing of their experiences of flooding in and around Lara which have helped to validate the flood modelling calibration events.

  3. Another Community Consultation Session is to be scheduled at Lara RSL on Thursday 28 March 2019 to receive feedback from the community regarding available mapping of the historic events (referred to in the calibration report) and to start to discuss mitigation options.

  4. A final Community Consultation Session will be held at the end of the study to present results and seek further feedback on the 9 May 2019.


Social Equity Considerations

  1. There are no social equity implications arising from the subject of this report.


Policy/Legal/Statutory Implications

  1. A Project Steering Committee has been established with representatives from the City, CCMA, DELWP and Victoria State Emergency Service.

  2. The role of CCMA, Vic SES and DELWP in delivery of this flood study is limited to Project Steering Committee membership and successful funding application support/partnership.

  3. Completion of the study addresses a high-priority action for the City and CCMA in the Corangamite Regional Floodplain Management Strategy.

  4. The study is expected to deliver flood mitigation recommendations which will include a proposed planning scheme amendment and flood intelligence to inform the Municipal Emergency Management Plan.


Alignment to Council Plan

  1. The project aims to deliver Improved health and safety of our community by consulting with the community on safety issues that are impacting them, in this case flooding.

  2. Planned sustainable development is also delivered via this coordinated approach to drainage and water sensitive urban design.


Conflict of Interest

  1. No Council officers or contractors who have provided advice in relation to this report have declared a conflict of interest regarding the matter under consideration.


Risk Assessment

  1. The project aims to better understand risks associated with flooding in the Lara area.


Environmental Implications

  1. Although environmental impact is being considered in the study, there are no environmental implications arising from the subject of this report.


Attachment 2

Milestone

Scheduled Date of Completion

Progress

Project Inception Meeting

24/05/2018

Complete

Site Visit

24/05/2018

Complete

PSC Meeting # 1

03/9/2018

Complete

Verification of Data

31/07/2018

Complete

Community Consultation Session #1

11/09/2018

Complete

Data Collation, Review and Methodology Report

14/08/2018

Complete

Floor Level survey

31/10/2018

Complete

Hydrology Model Build and Calibration

31/01/2019

Complete

Hydraulic Model Build and Calibration

31/01/2019

Complete

PSC Meeting # 2

26/02/2019  

Complete

Community Consultation Session #2

28/03/2019

 

Design Hydrology Memo

Mid-April

In Progress

Draft Model Design and Mapping

Mid-April

 

Final Model Design and Mapping

Mid-April

 

PSC Meeting # 3

30/04/2019

 

Flood Behaviour and Intelligence Outputs

30/04/2019

 

Flood affected properties

30/04/2019

 

Municipal Flood Emergency Plan

Mid-May

 

Flood warning assessment report

Mid-May

 

PSC Meeting # 4

Mid-May

 

Community Consultation Session # 3

22/05/2019

 

Structural Flood Mitigations Options Report

30/06/2019

 

Flood warning assessment report

30/06/2019

 

Draft Municipality Flood Emergency Plan

30/07/2019

 

Land Use Planning

30/07/2019

 

Draft Report

30/08/2019

 

PSC Meeting # 5

18/09/2019

 

Final Reporting

30/09/2019

 



[Back to List]

2. Lara Traffic Study Update

Source:

City Services – Engineering Services

Director:

Guy Wilson-Browne

Portfolio:

Transportation and Connections


Purpose

To provide an update on the Lara Traffic Study status and outline upcoming actions.

Background

  1. The Lara Traffic Study commenced following feedback from the communities of Lara and Little River about traffic safety and issues particularly associated with heavy vehicles.

  2. Data collected to support the study included traffic volumes, classification and speed; road hierarchy and condition; quarry access and haulage routes and accident statistics.

  3. In September 2018, the City commenced community consultation, seeking input on opportunities to improve walking, cycling, vehicle, public transport and heavy vehicle routes within and around Lara and Little River.


Key Matters

  1. A summary of the comments received from the consultation and preliminary suggested actions are provided in Attachment 2.

  2. A master plan with suggested actions supporting the comments will be finalised. It will summarise:

    1. The location of comments and officer analysis.

    2. Any current, priority, proposed or future works that relate to the comments.

    3. Further action required by other agencies or stakeholders.

    4. Ways in which suggested works may be delivered through existing programs, individual projects or via funding from stakeholders or agencies.

  3. The master plan will be released on the 28 March 2019 for community feedback.

  4. Some priority actions have been identified and incorporated this year into the 2018-19 program. The program is 75% completed.

  5. The remaining priority actions will be referred to the 2019-20 and future years programs.

Councillor Grzybek moved, Councillor Aitken seconded -

  1. That Council note:

    1. the feedback from the community consultation in September 2018.

    2. that the priority actions will be released on 28 March 2019 for a period of 6 weeks for community feedback.

    3. a final report on the engagement and actions will be presented to Council on the 12 June 2019.

Carried.


Attachment 1

Financial Implications

  1. The priority actions will be referred to current and future capital budgets. Depending on scale, these works may be incorporated into existing programs, others may require specific budget bids or external funding.


Community Engagement

  1. The City opened an online ‘Have Your Say’ page from 26 September 2018 through to 22 October 2018. Hard copies were available on request and written submissions could be mailed in.

  2. Three community forums were held, two sessions on Wednesday 10 October 2018 (9:00am to 12:00pm and 4:00pm to 7:00pm) and one session on Saturday 13 October 2018 (9:00am to 12:00pm).

  3. The draft priority actions are proposed for release on 28 March 2019 for community consultation over a period of 6 weeks.

  4. The City will develop and identify specific actions for each of the comments received and release this plan for a further four week consultation period. The outcomes of this consultation and associated actions are intended to be reported back to Council at 12 June 2019.

  5. The main issues identified refer to the following themes; cycling, heavy vehicles, traffic congestion, lighting, pedestrians, traffic speed, traffic management, public transport, road maintenance.

  6. The priority actions that the City can undertake include; road maintenance, road resurfacing, additional signage, road widening, intersection treatments, road closures, vegetation trimming, pedestrian and cycle path construction, upgrade bridges, manage rubbish dumping.

  7. Other priority actions include liaison with Regional Roads Victoria and Transport for Victoria to investigate and advocate for changes in speed limits, improved public transport, improved pedestrian and cycling facilities, introduction of load limits, review of parking at train station, duplication or widening of major roads and intersection treatments.


Social Equity Considerations

  1. There are no social equity implications arising from the subject of this report.


Policy/Legal/Statutory Implications

  1. There are no policy, legal or statutory implications arising from the subject of this report.


Alignment to Council Plan

  1. Integrated Transport Connections: Aim – Establish a traffic management plan for the northern growth corridor (including Lara).


Conflict of Interest

  1. There is no officer direct or indirect interest in the preparation of this report.


Risk Assessment

  1. There are no risks associated with the content of this report.


Environmental Implications

  1. There are no environmental implications associated with the outcomes of this report.


Attachment 2

LOCATION

TYPE

COMMUNITY FEEDBACK DESCRIPTION

PRELIMINARY RESPONSE (further detail to be provided)

6 Ways

Cycling

Improve bicycle access through the roundabout

Discuss with Regional Roads Victoria - to review 'Green treatment' option or other suitable treatment to improve safety to cyclists.

Heavy Vehicles

Remove heavy vehicles from 6 Way and Forest Rd (north & south)

Discuss heavy vehicle needs with Regional Roads Victoria & Transport for Victoria, with regards to removing trucks from Forest Road North & South.

Traffic Congestion

Congestion during peak times

Discuss with Regional Roads Victoria.

Lighting

Street lighting along Forest Road North and Station Lake Road.

Discuss with Regional Roads Victoria.

Pedestrians

Improve pedestrian crossing safety or consider installing 'pedestrian priority' wombat crossings on all approaches to provide safe crossing points for pedestrians

Discuss with Regional Roads Victoria to investigate opportunities to improve pedestrian crossing facilities at this location.

Traffic Speed

Introduce 40 km/h speed limit

Investigate traffic speeds and liaise with Regional Roads Victoria.

Traffic Management

Consider installing traffic signals to improve safety

Discuss with Regional Roads Victoria.

Alfred Street

Traffic Speed

If unsafe, investigate traffic calming options.

Investigate opportunities if required.

Traffic Management

Review unsafe corner of Fisher Street & Alfred St.

Review and investigate improvement options.

Traffic Management

Monitor traffic movements from Buckingham St to review closure of Alfred St.

Check and if the existing conditions are unsafe for road users, to then investigate impacts of road closure and undertake consultation.

Avalon Airport

Public Transport

We need a bus service to the airport from Lara Station

Notify Transport for Victoria.

Bacchus Marsh Road

Environmental

Control and manage illegal dumping of rubbish

Notify Regional Roads Victoria and the City’s environment department.

Road Maintenance

Improve road surface condition

Notify Regional Roads Victoria.

Traffic Congestion

Needs to be dual highway both ways, 2 lanes either way

Notify Regional Roads Victoria.

Traffic Management

Overtaking lanes required

Notify Regional Roads Victoria.

Bank Street

Traffic Management

Improve access into Forest Road South Rd.

Discuss with Regional Roads Victoria with investigation of ‘6 ways’ intersection.

Bath Street

Road Maintenance

This is used by the new bus route (both ways). Required road surface upgrade.

Discuss with Transport for Victoria. The City’s Maintenance Unit to review road conditions and maintenance levels.

Branch Road

Heavy Vehicles

Install truck travelling times to 6am – 7pm

Discuss with Transport for Victoria & Regional Roads Victoria. Discuss the possibility of installing truck curfew times.

Broderick Road

Other

Consider on & off ramp at Broderick Road and Geelong Ring Rd, which was first recommended when it was built.

Discuss with Transport for Victoria & Regional Roads Victoria. Discuss the viability of this to reduce trucks using local roads.

Buckingham Street

Traffic Management

The concrete channelling across Buckingham Street entry from Forest Rd causes severe shocks to vehicles and occupants (remove concrete channelling).

Review and investigate to consider option to improve road surface conditions.

Traffic Management

Need another exit from Buckingham Street for Lara Lake residents

Investigate further.

Traffic Management

Road width needs to be capable to accommodate buses, parking & through traffic

Review and investigate if there are any opportunities to widen or management options.

Traffic Management

The length of Buckingham St needs to be divided into two, possibly just east of Bath St.(Smeaton St was divided many years ago, and still divided today)

Investigate and review options.

Traffic Speed

Review vehicle speeds via Buckingham Street into Fisher Street

Investigate traffic speeds and if appropriate, look at options for traffic calming measures.

Traffic Speed

Traffic calming in Buckingham street may lead to a rat run along Alfred Street (gravel)

Pedestrians

Complete footpath between Windsor Court and Francis Court (approx. 100m of pavement required)

Review.

Canterbury Road / Canterbury Road East

Cycling / Pedestrian

Would be ideal to have dedicated bike lane, linking up Grand Lakes to Rennie Street - connection to popular reserve/walk to Limeburner’s.

Investigate.

Pedestrians

Improve pedestrian and cyclist infrastructure or install 'Shared path' connection required from Forest Rd South to Grand Lakes via Elcho drain line.

Investigate.

Coles Car Park Access

Traffic Management

Improve dangerous access. When exiting McDonalds, needs to either turn right or go straight.

Investigate, if required, options to improve safety.

Farras Road

Traffic Speed

Reduce speed limit to be 80 km/h to Branch Road. Carriageway too narrow.

Investigate and if required discuss with Regional Roads Victoria.

Flinders Avenue

Cycling

Need off road bike paths along Flinders avenue to You Yangs

Investigate and also consider surrounding cycling network.

Traffic Speed

Unsafe for cyclist to ride in 100 km/h zone

Investigate and also consider surrounding cycling network.

Pedestrians

Improve footpath and guttering along Flinders Avenue

Review.

Road Maintenance

Pot holes filling entire sections of road. The road needs a complete resurface

Investigate and maintain roads according to the City’s Road Management Plan.

Traffic Management

Discontinue before 6 way and connect it to Station Lake Rd near the bridge

Discuss option with Regional Roads Victoria to consider in ‘6 ways’ intersection review.

Road Maintenance

Widen Flinders Avenue from Windermere Road to Branch Road

Review.

Forest Road North

Cycling

Need bike paths - to You Yangs along Forest Road

Investigate and also consider surrounding cycling network.

Cycling

Between Thomas & Patullos Rd - dangerous for cyclists

Heavy Vehicles

Divert B-Doubles on Forest Road North into Windermere Rd. Not allow them access into Station Lake Road. Limit quarry truck use to 6am - 7pm

Discuss with Regional Roads Victoria & Transport for Victoria, to review truck circulation routes within Lara township.

Other

Beautify Forest Road North for the opening of Avalon Airport to International.

Review.

Road Maintenance

Between Thomas & Patullos Rd there are many potholes and edge breaks - unsafe.

Investigate and maintain to roads according to the City’s Road Management Plan.

Traffic Speed

Drop speed limit to 60-80kmh

Investigate traffic speeds and if appropriate, investigate options and discuss with Regional Roads Victoria.

Forest Road South

Cycling

Continue bicycle lanes along Forest Road South

Notify and discuss with Regional Roads Victoria.

Cycling

Widen Forest Road South to have footpaths and bike lanes(off road)

Notify and discuss with Regional Roads Victoria.

Cycling

Deep ruts on shoulders. Re-seal road surface for cyclists

Notify Regional Roads Victoria.

Traffic Congestion

Need double lanes

Notify Regional Roads Victoria.

Traffic Management

Widen Forest Road South to have footpaths/ bike lanes(off road) and have dual lanes

Notify and discuss with Regional Roads Victoria.

Pedestrians

Convert School crossing into a permanent pedestrian crossing with walking legs

Notify and discuss with Regional Roads Victoria.

Pedestrians

Intersection Forest Road South & Buckingham Street -convert existing school crossing to a permanent pedestrian crossing

Other

The disused train tracks across Forest Rd South need to be removed.

Notify Regional Roads Victoria.

Heavy Vehicles

Intersection Forest Road South & Buckingham Street -Limit quarry use to 6am - 7pm

Notify and discuss with Regional Roads Victoria.

Road Maintenance

Intersection Forest Road South & Buckingham Street- Pot holes on Forest Rd south, between Patullos and Canterbury Rd

Notify Regional Roads Victoria.

Traffic Management

Vehicles exiting Canterbury road, drive fast into the intersection. Poor sight distance for Forest Road South vehicles. Unsafe. Or Install traffic signals

Notify and discuss with Regional Roads Victoria.

Traffic Management

Forest Road south at Buckingham Street need traffic island to cross road safely.

Notify and discuss with Regional Roads Victoria

Gibbons Road

Road Maintenance

Lack of regular maintenance for high traffic area

Review temporary road closure and road to be maintained according to the City’s Road Management Plan.

Traffic Management

Review closure of road

Glenoe Drive

Road Maintenance

Seal the road - corrugations, needs frequent grading

Investigate and check against Road Management Plan and investigate road sealing options.

Heales Road

Traffic Management

Link Heales Road to O'Hallorans Road. This would take traffic pressure off Buckingham Street & Forest Road intersection.

Review the need for another connection via residential developed areas.

Intersection - Heales Road & Broderick Road

Traffic Management

Improve dangerous intersection, due to see-through effect

Discuss with Regional Roads Victoria on opportunities to improve this intersection.

Hicks Street

Traffic Speed

Reduce speeds to 40 km/h from McClelland Ave roundabout to past train station.

Investigate traffic speeds and safety, also discuss with Transport for Victoria regarding rail crossing.

Intersection of Mill Road & McIntyre Road

Traffic Management

Improve intersection for turning vehicles

Review this intersection, and investigate opportunities to improve accessibility and safety as required.

Intersection Old Melbourne Road & McIntyre Road

Traffic Management

Unsafe intersection for motorists, improve intersection

Review this intersection, and investigate opportunities to improve accessibility and safety as required.

Intersection - You Yangs Road & Little River Ripley Road

Traffic Management

Improve intersection safe for cyclist & vehicles at You Yangs Road Little River Ripley Road

Review this intersection, and investigate opportunities to improve accessibility and safety as required.

Intersection McClelland Ave & Avalon Road

Traffic Management

Improve intersection due to high speed entering of vehicles

Review this intersection, and investigate opportunities to improve safety as required.

Road Maintenance

Line marking /controls at the intersection of the Princess Hwy northbound off ramp with McClelland Ave needs updating.

Investigate and improve any faded line marking as required.

Intersection Little River Ripley & Kirks Bridge Road

Traffic Management

Improve intersection to stop dangerous hoon behaviour

Investigate driver behaviour and opportunities for traffic management devices to reduce 'hooning' behaviour at this intersection. Also notify this VicPol.

Intersection Windermere Road & Forest Road North

Traffic Management

Trees blocking view at this intersection. Improve safety -Sight distance issues

Review site conditions for sight distance issues and take action to improve as required.

Kees Road

Traffic Management

Upgrade road to have two lanes

Investigate.

Traffic Management

Discontinue before 6 way and connect it to Forest Rd North

Discuss option with Regional Roads Victoria to consider in ‘6 ways’ intersection review.

Traffic Management

High traffic volumes during school times.

Review and monitor.

Road Maintenance

Upgrade gravel section (narrow bitumen) up to Windermere Road. Road in poor condition.

Investigate and maintain as per the City’s Road Management Plan.

Kees Road off-road car park

Traffic Management

Gravel walking path is often blocked by overflow of cars parked all over nature strip and blocking footpath at night. Re-design parking layout to improve safety.

Investigate and, if possible, improve the car parking layout to provide safety to pedestrians and motorists.

Parking

Re-design off street car park

Investigate and if possible improve the car parking layout to provide safety to pedestrians and motorists.

Lara Railway Station & car park

Traffic Management

Review parking in Local roads due to commuter parking

Discuss with Transport for Victoria and monitor on-street issues.

Traffic Management

There is a need for a pedestrian bridge from Mill Road to the station

Discuss with Transport for Victoria for any near future funding availability and any plans to further investigate.

Parking

Need more car parking spaces for ‘park & ride’ at Lara station.

Notify Transport for Victoria

Public Transport

Improve coordination of timing and matching of buses with trains. Review the existing single bus route to the station due to two major new housing developments underway. Increase frequency of buses during peak hours to the station.

Notify Transport for Victoria

Lewton Road

Road Maintenance

Review sealing of Lewton Road due to dust and road maintenance issues.

Investigate.

Little River Ripley Road

Environmental

Install warning signs to stop illegal rubbish dumping.

Monitor and if required notify Local Laws.

Heavy Vehicles

Look at diverting trucks to Mt Rothwell, which is a B double route.

Investigate and discuss with Transport for Victoria and Regional Roads Victoria.

Heavy Vehicles

Re-route trucks via Little River Ripley Road to Bacchus Marsh Road. Limit quarry truck use to 6am - 7pm

Investigate and discuss with Transport for Victoria and Regional Roads Victoria.

Manzene Avenue

Traffic Management

Improve LT & RT from Patullos Road

Review maintain road as per the City’s Road Management Plan and also to investigate the safety and access of turning movements.

Road Maintenance

Repair defective construction at the left edge for turning lane from Patullos Road into Manzene Avenue

McClelland Avenue

Heavy Vehicles

Remove truck advisory signs , Install truck engine brake warning signs and limit quarry truck use to 6am - 7pm

Discuss with Transport for Victoria and Regional Roads Victoria the heavy vehicle routes within Lara and truck curfew initiatives.

Traffic Management

More police enforcement required

Review existing vehicle speeds and discuss with VicPol.

Traffic Management

Review and restore two lanes near the railway crossing and upgrade road surface.

Investigate.

Traffic Speed

Reduce speed to 60 km/h from Avalon Ramp

Investigate and discuss with Regional Roads Victoria.

Traffic Management

Widen road to allow LT & RT.

Investigate and review options to accommodate safe turning movement facilities.

Road Maintenance

Fix the railway crossing section for pedestrians, full of pot holes, surface damages.

Investigate and maintain as pre the City’s Road Management Plan, also discuss with Public Transport Victoria.

Traffic Congestion

Congestion due to Train services

Investigate and discuss with Transport for Victoria.

McIntyre Road

Road Maintenance

Upgrade road surface for cyclists

Check and maintain the road according to the City’s Road Management Plan.

Mill Road

Heavy Vehicles

Enforce 'No truck's on Mill Road.

Discuss with Regional Roads Victoria and VicPol.

Traffic Speed

Review speed limit between McIntyre Road and Plains Road to 70 -80 km/h

Review existing speeds and as required review speed zone and traffic calming measures.

Pedestrians

Complete missing footpaths

Investigate.

O'Hallorans Road

Road Maintenance

Needs maintenance due to large potholes and corrugations.

Investigate and maintain as per the City’s Road Management Plan.

Old Melbourne Road

Bridge Condition

Review Bridge condition

Investigate.

Patullos Road

Parking

Remove Patullos Road angle parking between the intersection & pedestrian crossing. Dangerous area. Angle parked cars reversing into traffic. U turns on Patullos Rd at the southern end of Kees Rd.

Discuss this with Regional Roads Victoria and review parking options with regards to ‘6 ways’ intersection review.

Traffic Congestion

Congestion during peak times

Discuss with Regional Roads Victoria to assess ways to improve vehicle movement with regards to ‘6 ways’ intersection review.

Pedestrians

Complete missing footpaths

Investigate.

Traffic Management

Need a LT lane into Bath St from Patullos Road.

Investigate safety and accessibility of turning movements.

Peak School Road

Traffic Speed

Review and reduce speed limit to 80 km/h.

Investigate and discuss further with Regional Roads Victoria if required.

Traffic Management

Install 'Stop' signs at Mill Road (corner of McIntyre Rd) - cars speeding through 'Give Way' sign.

Investigate and implement safety upgrades as required.

Traffic Management

Upgrade road for Lara Prison Precinct and access of heavy vehicles from You Yangs.

Investigate.

Bridge Condition

Review condition of Culvert, sinking due to B-Doubles

Investigate.

Perkins Road

Pedestrians

Complete missing footpaths

Investigate.

Traffic Speed

Review and maintain 60 km/h and 5 T load limit.

Investigate existing conditions and monitor for any unsafe motorist behaviour.

Plains Road

Traffic Speed

Review and reduce speed limit to 80 km/h, due to gravel surface.

Review existing conditions and monitor for any unsafe motorist behaviour.

Traffic Management

Maintain 5T load limit

Rennie Street

Pedestrians

Hovells Creek shared path near Rennie Street - Path can be under water with no warning at entrance to trail a long detour.

Review and investigate options to improve as required.

Roundabout - Rennie Rd & McClelland Ave

Traffic Management

Review 'school drop off & pick' location in the morning for safety concerns.

Review and investigate options to improve safety as required.

Sandy Creek Road

Environmental

Manage rubbish dumping along this road

Monitor and if required, notify the City’s Local Laws Unit.

Road Maintenance

The width of Sandy Creek Road should match the road hierarchy and repair damaged road surface and shoulders.

Investigate and also maintain as per the City’s Road Management Plan.

Traffic Management

Police presence required to stop 'hoons breaking into properties with guns, doing burn outs'.

Notify VicPol.

Traffic Speed

Review & reduce speeds to 80 km/h.

Investigate vehicle speeds and, if required, discuss with Regional Roads Victoria about options to reduce the posted speed limit.

Traffic Management

Install curve warning signs at the intersection of Branch Road and Forest Road North.

Investigate.

Heavy Vehicles

Permit trucks to use north end and re-route trucks via Little River Ripley Road

Coordinate discussion with stakeholders, including residents, on the opportunity to promote heavy vehicles to use Little River Ripley Rd to access Bacchus Marsh Road and what roads would require upgrading.

Drainage

Review and install a new 'Culvert' at the low point in Sandy Creek Road to reduce water damage to road.

Investigate.

Smeaton Close

Parking

Improve parking facilities

Review existing parking conditions for improvement opportunities.

Station Lake Road

Cycling

Needs wider cycle and pedestrian path and a link to existing and proposed paths

Investigate and develop options to address concerns as required for the entire road segment between ‘6 Ways’ intersection and the bridge.

Traffic Management

Peak Street -Require RT lanes in Station lake Road.

Traffic Management

Beverley Crescent -Install RT turning lanes in Station Lake Rd to reduce damage to shoulders

Traffic Management

Widen road to allow for turning traffic into side streets, turning traffic holding through traffic

Cycling

Install cycling lane from the bridge to the 6way.

Heavy Vehicles

Remove advisory truck route sign at station lake road

Discuss with Regional Roads Victoria to review heavy vehicle circulation within and around Lara.

Pedestrians

Complete missing footpaths

Investigate.

Lighting

Street lighting on Station Lake Road between 6 Way & Hume Bridge is not good.

Review lighting conditions.

Traffic Congestion

Peak Street -Due to congestion along Station Lake Road during peak times, it's hard to enter from Peak Street.

Investigate and discuss with Regional Roads Victoria to find ways to reduce congestion during peak times at ‘6 Ways’ intersection.

Thomas Road

Road Maintenance

Surface dangerous, needs resurfacing

Check and maintain as per the City’s Road Management Plan.

Toynes Road

Cycling

Provide bicycle connection to the reserve from Little River Train Station

Investigate and also consider surrounding cycling network.

Road Maintenance

Improve road surface for cyclists

Check and maintain road as per the City’s Road Management Plan.

Walkers Road

Cycling

Upgrade bicycle lanes

Investigate and also consider surrounding cycling network.

Cycling

Need bicycle lanes in Walker's, Flinders and Curletts roads

Pedestrians

Need pedestrian crossing. Nowhere for people to cross safely.

Investigate and plan a pedestrian crossing as required.

Traffic Speed

Review to reduce speed limits to 40 km/h

Investigate current vehicle speeds of vehicles, and if required discuss Regional Roads Victoria on options to reduce the posted speed limit.

Watts Street

Traffic Management

Dangerous corner for traffic at the corner of Watts Street & Avalon Road, when coming from Geelong to Lara. Exiting off the Princes Highway off ramp or service road to turn left into Watts Street.

Discuss this with Regional Roads Victoria. Monitor this intersection and work with Regional Roads Victoria to improve safety to motorists.

Traffic Management

Widen Watts Street at this corner and install an off ramp service road into Watts Street to avoid any traffic accidents or any road deaths. Alternatively install a roundabout at this corner.

Waverley Road

Cycling

Install bicycle lanes

Investigate and also consider surrounding cycling network.

Windermere Road

Bridge Condition

Review bridge condition

Investigate.

Heavy Vehicles

Restrict heavy trucks movements along Windermere Road East.

Discuss with Regional Roads Victoria to review heavy vehicle circulation within and around Lara.

Traffic Speed

Include speed restrictions along Serendip Sanctuary boundary

Investigate current vehicle speeds, and if required discuss with Regional Roads Victoria about options to reduce the posted speed limit.

You Yangs Reserve

Cycling

Bicycle directional signage within Lara to key activity centres – You Yangs, Train Stations & Township

Discuss with You Yangs Reserve Management about opportunities to improve directional signage and connections to Lara township.

You Yangs Road

Road Maintenance

Review sealing of road

Review and maintain as per the City’s Road Management Plan.

Traffic Management

Install directional signage for cyclists from Werribee and Little River to You Yangs and Melbourne Road

Review opportunities to improve directional signage and connections.

Lara Community Centre

Traffic Management

The location of the bus stop outside Lara community centre obstructs the view of cars pulling out of the community centre car park

Investigate and improve safety as required.

General

Public Transport

Review bus routes

Notify Transport for Victoria.

Public Transport

Improve weekend services.

Notify Transport for Victoria.

Public Transport

Improve existing bus service times which finishes around 7.30pm.

Notify Transport for Victoria.

Public Transport

Need a direct bus from Lara to Geelong

Notify Transport for Victoria.

Public Transport

New bus connection from Lara Train Station to Avalon Airport

Notify Transport for Victoria.

General

Environmental

New signage - 'take rubbish home' signs required.

Investigate.

General

Road Maintenance

Remove weeds out of bike lanes

Investigate and undertake necessary weed control.

General

Road Maintenance

Road maintenance required – Bath St, Buckingham into Forest Rd, Flinders Ave, Kees Rd, McClelland Ave, Lewton Rd, Avalon Rd, Station Lake Rd

Check.

General

Road Maintenance

Area needs to be cleaned up area to prepare for International Tourists

Monitor.

Traffic Management

Need directional signage leading people from Avalon Airport to tourism sites, Lara, Little River townships, Serendip & You Yangs

Discuss with Regional Roads Victoria and Avalon Airport.



[Back to List]

3. Geelong Waterfront Safe Harbour Precinct – Master Plan

Source:

Investment & Attraction

Director:

Brett Luxford

Portfolio:

Social and Infrastructure Planning


Purpose

  1. That Council note the draft “Geelong Waterfront Safe Harbour Precinct – Masterplan” and to endorse the release of the document for further community engagement.

Background

  1. The Royal Geelong Yacht Club (RGYC) have written to Council requesting that the draft Geelong Waterfront Safe Harbour Precinct Masterplan be endorsed by Council.

  2. RGYC have also requested that Council approve the payment of the City’s $3 million contributory funding towards Stage 1 of the project, and provide ‘in principle’ support for the planning process to introduce an incorporated document for the project into the Greater Geelong Planning Scheme.

  3. The Geelong Waterfront Safe Harbour Precinct is a Council priority project. The project is a public infrastructure development to improve public permeability through the precinct, create a boating safe harbour, redevelop the Victorian Sailing School and RGYC buildings and improve the surrounding public realm.

  4. At the Ordinary Meeting of Council on 13 November 2018, Council agreed to extend the $3 million funding towards the $19.1 million stage one of the project contingent on the RGYC securing the remaining funding and a precinct masterplan is endorsed by Council to ensure community benefits of the project are realised.

  5. RGYC have secured the funding for stage one from the following sources: $7.6 million state government; $5.5 million federal government; $3 million RGYC. The full state government funding cannot be released until the City, as the land manager, endorses the masterplan.


Key Matters

  1. An internal comprehensive review of the masterplan document developed by RGYC will be undertaken before Council endorsement is given. This will also include a period of further community engagement, to ensure all feedback is received.

  2. This review is important to evaluate the form and function of key elements within the public realm. It must be ensured that the development provides enhancement of the public experience, safety and a positive contribution to the environment and surrounding waterfront character.

  3. Fundamentals for development on crown land also requires the further examination and addressing of elements in this project. These include: the consideration of reclaiming a new seabed area; maintaining public views; vistas and sightlines; accommodating archaeological and heritage features of the area; enhancing public access to the coast and, minimise loss of open space.

  4. Subject to approvals, construction of the wave attenuator is planned to commence during 2019. Major on land building works will be undertaken during 2020.

Councillor Murrihy moved, Councillor Aitken seconded -

  1. That Council:

    1. Notes the draft Geelong Waterfront Safe Harbour Precinct – Masterplan;

    2. Prior to endorsement of the masterplan, place the draft Geelong Waterfront Safe Harbour Precinct – Masterplan on public exhibition for a period of 21 days to seek further stakeholder feedback;

    3. Receive a report on the community and stakeholder feedback;

    4. Establish a Design Advisory Committee (including internal officer support) to consider the detailed design which is part of the Masterplan and the planning approval for the project; and

    5. Note that future planning approval for the project is likely to be managed under an Incorporated Document introduced into the Planning Scheme via a Ministerial planning scheme amendment.


Attachment 1

Financial Implications

  1. The RGYC have requested that Council commence the process of releasing funding that has been budgeted for this project.The $3 million contribution sought from Council is accounted for in the 2019-20 Strategic Resource Plan as a non-recurrent disbursement in December 2019 in accordance with previous resolutions of Council.

  2. The costings for the project are based on a business case completed in 2015 with all financial risk and future operational costs resting with RGYC. Changes to the public realm through the implementation of the masterplan will be fully assessed before development occurs to ensure ongoing cost implications are known.

  3. A review of RGYC lease rental will be undertaken to determine if any new income opportunities are realised to the City in response to the use of much improved facilities. Any rental increase is likely to be offset by ongoing maintenance of new public realm areas.


Community Engagement

  1. This project has received wide media attention which has been based on the masterplan vision and design concepts. The RGYC has undertaken two rounds of community consultation including targeted stakeholder workshops for local residents, traders and club members. Results have revealed support for the project.

  2. A further community engagement period should be undertaken by Council to ensure all community wide views on the project are obtained. This would include direct letter notification to nearby property owners/occupiers, newspaper notices and the opportunity to view and comment on the masterplan through the City’s website.

  3. Officers believe this period of public consultation on the masterplan is important as the proposed planning scheme amendment would be undertaken by the Minister under Section 20(4) of the Planning and Environment Act 1987 and would not be subject to public exhibition. Approval of more detailed plans under the incorporated document would also not be subject to public notification.


Social Equity Considerations

  1. The project provides new infrastructure supporting event growth and attraction. It will increase the use of the waterfront for public recreation and new community event opportunities.

  2. The new Victorian Sailing School building will open new learn to sail programs for the public and enhance the existing RGYC Sailability program.

  3. A new Changing Places Facility will form part of the new Victorian Sailing School building and will have managed access for the general public. Support for a Changing Places Facility in this location has strong backing from a wide range of community and reference groups and has been funded by the Department of Human Services.

  4. The new wave attenuator will be effective in creating a safe harbour environment and suitable for public accessibility in accordance with Disability Discrimination Act 1992 (Cth) requirements.

  5. The masterplan will be delivered in stages. Stage one will include a 400m public accessible wave attenuator; RGYC marina berths; maritime and education centre (former Sailing School and Off the Beach Club House) and public realm benefits.


Policy/Legal/Statutory Implications

  1. A number of approvals are required to facilitate the proposal. These include a Planning Permit under the Planning and Environment Act 1987, Marine and Coastal Act 2018 consent, Heritage Victoria consent, and various secondary consents for works.

  2. Following an assessment of the possible planning controls by Council and Department of Environment, Land, Water and Planning (DELWP) staff, an incorporated document under Clause 51.01 “Specific Sites and Exclusions” emerged as the most appropriate tool for the development, particularly as the development straddles two zones and is subject to planning scheme overlays. This would exempt the project from the usual planning scheme requirements and a planning permit would not be required.

  3. Council will be required to endorse this approach to enable the RGYC to write to the Minister for Planning, seeking the Minister’s intervention under 20(4) of the Planning and Environment Act 1987.

  4. In lieu of a planning permit the incorporated document will include specific conditions and a requirement for further detailed plans to be submitted for approval by Council officers in consultation with other agencies.

  5. More details on the proposed Ministerial amendment and incorporated document will be included in a further report to Council after the proposed period of community engagement.

  6. The footprint of the RGYC land and seabed lease boundaries will change with the development. The aim will be to minimise the footprint of new structures to prevent loss of open public space. Council in its role as land manager will negotiate the terms and conditions of the new lease. Responsibility between RGYC and Council for the ongoing maintenance of new public realm areas is yet to be determined.

  7. DELWP have recommended that a Design Advisory Committee be established to consider detailed design as part of the Masterplan and planning approval for the project.


Alignment to Council Plan

  1. The Geelong Waterfront precinct is a primary focus for the local community. The project aligns with Council Plan 2018 – 2022: Growing Our Tourism and Events. The project is listed as a 2018-19 aim to support the Geelong Waterfront Safe Harbour Precinct.

  2. The project is also listed within the Central Geelong Action Plan and Revitalising Central Geelong State Action Plan


Conflict of Interest

  1. There are no conflicts of interest in relation to this report.


Risk Assessment

  1. All financial risks rest with RGYC including the future operation and demand for marina services. The Project Control Group (PCG) will take responsibility to manage project risk to ensure that public realm improvements are achieved.

  2. The tender and development steps of the project will be used to look at options to stage the work and provide the City with the opportunity to safeguard public assets and community use of the precinct.

  3. A PCG, which includes all funding stakeholders, has been established to guide the development of the project. The PCG will continue to oversee the implementation of the project to ensure that the community benefit outcomes are achieved.


Environmental Implications

  1. Environmental impact studies have commenced. The planning approval process will inform what final environmental reports are required.

  2. The onshore components of the project essentially involve building new RGYC and Victorian Sailing School accommodation and facilities on the existing RGYC site. It is not expected that any significant incremental environmental impact would result from demolishing and rebuilding on the existing site, assuming that any incremental water, waste-water and sewage requirements are adequately managed. Rather the redevelopment will provide the opportunity to upgrade and optimise the arrangements.

  3. The on-water (marina) development is within or around the area of the existing marina, with the proposed wave attenuator along an alignment to the west of the site previously occupied by the Yarra Street Pier.

  4. Energy consumption in the new facilities will be less due to appliance efficiency and through the communal use of facilities.

  5. Later stages of the works may involve reclamation of seabed and the relocation of storm water outlets and the gross pollutant trap currently in the shallow water adjacent to the sailing school. Any future works must limit the amount of silt and rubbish being discharged and trapped along the shore-line. The Central Geelong Drainage and Flood Study does not provide direct advice in this matter and further investigations will be conducted to ensure improved environmental outcomes.

  6. Any future reclamation of seabed areas will be subject to environmental effects studies and needs to be tested against net positive benefit to the community. Endorsement of the masterplan does not commit Council to a particular view on this matter.


[Back to List]

4. Herne Hill Reserve Master Plan - Final Report

Source:

Governance and Legal Services

Executive Manager:

Rebecca Leonard

Portfolio:

Tourism and Events


Purpose

  1. To appoint a Councillor to the Tourism Greater Geelong and the Bellarine Inc. Committee (Committee).


Background

  1. On 13 March 2018 Councillors were appointed to special and Advisory Committees that are established in accordance with the provisions of the Local Government Act 1989 (Act). Council also appointed representatives to external boards, committees, associations and forums in accordance with the governance requirements of those bodies.

  2. The Committee appointment was for a one-year term and Council appointed
    Councillor Ron Nelson.

  3. Council must appoint its representatives formally by a decision of Council in accordance with the Act.


Key Matters

  1. The Committee appointment was for a one-year term. This report seeks a Councillor nomination to appoint a Councillor representative for a further year.

  2. The Committee’s Statement of Rules and Purpose allows for one Councillor representative.

  3. The appointment of a Councillor to represent Council will continue to support the Council in its effective governance of the municipality.

Councillor Nelson moved, Councillor Sullivan seconded -

  1. That Council call for nominations and appoint a Councillor to the Tourism Greater Geelong and the Bellarine Inc. Committee for a one-year term.

Carried.

Councillor Nelson moved, Councillor Sullivan seconded –

  1. That Councillor Murrihy be nominated as Council’s representative to the Tourism Greater Geelong and the Bellarine Inc. Committee for a one-year term.

Carried.

As there were no further nominations Councillor Murrihy was duly appointed to the position.


Attachment 1

Financial Implications

  1. There are no financial implications with the appointment of a Councillor to the Committee.


Community Engagement

  1. Councillors and officers have been consulted in the preparation of this report. The outcome of this report will be communicated to the Committee.


Social Equity Considerations

  1. There are no social equity issues arising from the subject of this report.


Policy/Legal/Statutory Implications

  1. This is an appointment to an external Committee that is governed by their Statement of Rules and Purpose. There is no legislative requirement to establish this Committee.


Alignment to Council Plan

  1. The appointment of a Councillor to the Committee supports the growing our tourism and events strategic priority of the Council Plan 2018-2022


Conflict of Interest

  1. No Council officers involved in the preparation of this report have any direct or indirect interest.


Risk Assessment

  1. The appointment of a Councillor to the Committee mitigates the risk of the community being under-represented.


Environmental Implications

  1. There are no environmental implications identified for the subject of this report.


[Back to List]

5. Planning Authorisations - Council to Staff

Source:

Governance & Legal Services - Governance

Executive Manager:

Rebecca Leonard

Portfolio:

Sustainable Development


Purpose

  1. To appoint Council officers as authorised officers under the Planning and Environment Act 1987 (P&EA).

Background

  1. Council officers are appointed as authorised officers to exercise statutory powers under various Acts and regulations. Appointments as authorised officers are to individual staff members.

  2. The P&EA regulates enforcement and is reliant on authorised officers acting on behalf of the responsible authority (Council).


Key Matters

  1. Where there is a specific power within an Act, Council should appoint authorised officers pursuant to that Act. This is the case for the P&EA.

  2. Planning staff members have recently been employed by Council and are required to be authorised under the P&EA.

  3. Attachment 2 sets out the Instrument of Appointment and Authorisation under the P&EA and lists the staff members to whom this authorisation applies (instrument).

Councillor Mason moved, Councillor Asher seconded -

  1. In the exercise of the powers conferred by section 224 of the Local Government Act 1989 and the other legislation referred to in the attached instrument, Greater Geelong City Council (Council) resolves that the:

    1. members of Council staff referred to in the instrument be appointed and authorised as set out in the instrument;

    2. instrument comes into force immediately upon the common seal of Council being affixed to the instrument, and remains in force until Council determines to vary or revoke it;

    3. instrument be sealed.

Carried.


Attachment 1

Financial Implications

  1. There are no financial implications arising from the subject of this report.


Community Engagement

  1. Relevant Council managers have been consulted regarding this recommended appointment and authorisation.


Social Equity Considerations

  1. There are no social equity implications arising from the subject of this report.


Policy/Legal/Statutory Implications

  1. The recommended appointment and authorisation of these staff members complies with the relevant provisions of the P&EA and the Local Government Act 1989.


Alignment to Council Plan

  1. The recommended appointments and authorisations of these staff members supports the delivery of Council planning services.


Conflict of Interest

  1. No Council officers who have provided advice in relation to this report have declared a conflict of interest regarding the matter under consideration.


Risk Assessment

  1. There are no significant or high risks associated with the subject of this report.


Environmental Implications

  1. There are no environmental implications arising from the subject of this report.


[Back to List]

Close of Meeting

As there was no further business the meeting closed at 9:01pm on Tuesday 12 March 2019.


Signed: _________________________________________

Councillor Peter Murrihy (Acting Mayor)



Date of Confirmation: _____________________________



[Back to Top]

Contents | Previous Page: Section A - Procedural Matters |